Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26

Loading in 2 Seconds...

play fullscreen
1 / 5

Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26 - PowerPoint PPT Presentation


  • 59 Views
  • Uploaded on

Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26. The fundamental function checks of EWO, WPT-Pre, and IPD and their I/F checks will be done inside the MHI.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26' - wylie


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Plan of the PME integration/interface tests in 2008 (tentative)

2008.7.26

  • The fundamental function checks of EWO, WPT-Pre, and IPD and their I/F checks will be done inside the MHI.
  • Function and I/F checks of the LF-SC/DB-SC with the SC-Pre. will be conducted in Kanazawa Univ. But the schedule is not fixed at this moment.
  • The PME integration/interface tests in Kyoto univ. will start on August 25 (see the schedule table of the next page).
  • The extension tests of the WPT-S and MEFISTO-S are conducted during the system EM integration test (not conducted in Kyoto univ.).
  • PME unit level environment tests will move to June 2009..

<<Request>>*Please update your plan, and submit the following information

to Y. Kasaba ([email protected]) &

H. Kojima ([email protected])

(1) 1st I/F test (Mainly focusing on the analogue I/F)[Sep.-Oct. , 2008]

When you can join?

Which configuration of EM or BBM for this?

What is your minimum plan from the point of your view ?

(2) EWO-FPGA/MDP I/F test

(Mainly focusing on the digital I/F)[Nov., 2008 – Dec., 2008]

(3) 2nd I/F test (Check of the whole PME system) [Apr., 2009]

slide4

PME Unit Level check:

Site: EM shield chamber room of RISH, Kyoto

Configuration: PME + MDP simulator without the PSU

Installation of each board into the PME chassis and brief function check

April 1-3: EWO/IPD

April 6: SORBET

April 7: MEFISTO

April 8: AM2P

April 9: SC/WPT-pre

April 10: MGF-I/MGF-O

PME function tests

April 13-17 Function tests: All PME teams

C&DH interface test #2

May 18-June 12, 2009

Since the tests will be conducted in the end-to-end,

the whole PME will join this test.

The detailed schedule will be announced in the design meeting.