Plan of the PME integration/interface tests in 2008 (tentative)
This presentation is the property of its rightful owner.
Sponsored Links
1 / 5

Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26 PowerPoint PPT Presentation


  • 32 Views
  • Uploaded on
  • Presentation posted in: General

Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26. The fundamental function checks of EWO, WPT-Pre, and IPD and their I/F checks will be done inside the MHI.

Download Presentation

Plan of the PME integration/interface tests in 2008 (tentative) 2008.7.26

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Plan of the pme integration interface tests in 2008 tentative 2008 7 26

Plan of the PME integration/interface tests in 2008 (tentative)

2008.7.26

  • The fundamental function checks of EWO, WPT-Pre, and IPD and their I/F checks will be done inside the MHI.

  • Function and I/F checks of the LF-SC/DB-SC with the SC-Pre. will be conducted in Kanazawa Univ. But the schedule is not fixed at this moment.

  • The PME integration/interface tests in Kyoto univ. will start on August 25 (see the schedule table of the next page).

  • The extension tests of the WPT-S and MEFISTO-S are conducted during the system EM integration test (not conducted in Kyoto univ.).

  • PME unit level environment tests will move to June 2009..

<<Request>>*Please update your plan, and submit the following information

to Y. Kasaba ([email protected]) &

H. Kojima ([email protected])

(1) 1st I/F test (Mainly focusing on the analogue I/F)[Sep.-Oct. , 2008]

When you can join?

Which configuration of EM or BBM for this?

What is your minimum plan from the point of your view ?

(2) EWO-FPGA/MDP I/F test

(Mainly focusing on the digital I/F)[Nov., 2008 – Dec., 2008]

(3) 2nd I/F test (Check of the whole PME system)[Apr., 2009]


Plan of the pme integration interface tests in 2008 tentative 2008 7 26

EM Schedule for PME(July – December, 2008)


Plan of the pme integration interface tests in 2008 tentative 2008 7 26

EM Schedule for PME(Jan. – Jun., 2009)


Plan of the pme integration interface tests in 2008 tentative 2008 7 26

PME Unit Level check:

Site: EM shield chamber room of RISH, Kyoto

Configuration: PME + MDP simulator without the PSU

Installation of each board into the PME chassis and brief function check

April 1-3:EWO/IPD

April 6:SORBET

April 7:MEFISTO

April 8:AM2P

April 9:SC/WPT-pre

April 10:MGF-I/MGF-O

PME function tests

April 13-17Function tests: All PME teams

C&DH interface test #2

May 18-June 12, 2009

Since the tests will be conducted in the end-to-end,

the whole PME will join this test.

The detailed schedule will be announced in the design meeting.


Plan of the pme integration interface tests in 2008 tentative 2008 7 26

PME Environment test (Baseline: Proposal)


  • Login