THEMIS-SCM. SCM SCHEDULE. The CETP maintains a dedicated Schedule for SCM (MS-Project) the most important activities and dates are reported in the Themis Schedule Very simple for the moment, it shall be completed and improved

Download Presentation

THEMIS-SCM

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Themis scm

THEMIS-SCM

SCM SCHEDULE

The CETP maintains a dedicated Schedule for SCM (MS-Project)

the most important activities and dates are reported in the Themis Schedule

Very simple for the moment, it shall be completed and improved

The main sub-contractor, 3D+, also maintains an internal Schedule

the delivery date of the cubes to CETP is an entry for the SCM Schedule

The other sub-contractors are less critical and no formal schedule is requested for teir activities – just the delivery dates

Bertrand delaPorte

THM-SCM-PDR – 2003.10.10


Themis scm

THEMIS-SCM

SCM SCHEDULE

The milestones for SCM are the delivery dates to UCB

According to the current schedule:

EM delivery to UCB : 16-Apr-04 - no difficulty expected

FM-1 30-Jul-04 - very difficult for the PA

FM-2+3 24-Sep-04 - very tight for the PA

FM-4+5 19-Nov-04 - no difficulty expected

FM-6 14-Jan-05

No difficulty is expected for any SC

Because there is a screening at the end, all FM cubes (for all Models), will be delivered at the same date – according to the contract: 01-Aug-2004

Bertrand delaPorte

THM-SCM-PDR – 2003.10.10


Themis scm

THEMIS-SCM

26-Jan-04

3D+ date

31-Jan-04

EM to UCB

16-Apr-04

PA /EM manufacturing & delivery

Bertrand delaPorte

THM-SCM-PDR – 2003.10.10


Themis scm

THEMIS-SCM

31-May-04

3D+ date

01-Aug-04

FM-1 to UCB

30-Jul-04

26-Jul-04

FM-2, 3 to UCB

24-Sep-04

PA /FM-1,2,3 manufacturing & delivery

Bertrand delaPorte

THM-SCM-PDR – 2003.10.10


Themis scm

THEMIS-SCM

SCM SCHEDULE - CONCLUSION

Real difficulty to delivery the PA /FM1 at the date currently specified

Various solutions can be envisaged with UCB or with 3D+ to avoid any impact on the Integration Schedule of the Project

All other Models can be delivered in time

Bertrand delaPorte

THM-SCM-PDR – 2003.10.10