Construction Activities: - PowerPoint PPT Presentation


  • 92 Views
  • Uploaded on

Engineering & Construction Management Department. Augs Report, 2011. Project . General Project Description: Consultant is designing a park pond extending from Radford to Bowie and I-10 to Rosa, the pond will supplement the storm water management system of the Government Hills Outfall .

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Construction Activities:' - willem


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Engineering & Construction Management Department

AugsReport, 2011

Project

  • General Project Description: Consultant is designing a park pond extending from Radford to Bowie and I-10 to Rosa, the pond will supplement the storm water management system of the Government Hills Outfall

Park Pond

Construction Activities:

  • Contractor has paved ~95% of the neighborhood, pending one portion of Durazno
  • Contractor has installed sod within both of the soccer fields
  • Project should be substantially complete by end of the first week of August

Photo

Project Schedule

Page 1 of 2

slide2

Engineering & Construction Management Department

AugustReport, 2011

Project

  • General Project Description: Consultant is designing a park pond extending from Radford to Bowie and I-10 to Rosa, the pond will supplement the storm water management system of the Government Hills Outfall

Project Budget: $5,273,754.15

Notes

Funding Source: EPWU funds

Storm 2006 and 2009 Certificates of Obligation

Project Contact

Project Manager Yvette Hernandez

915-541-4200

Design Consultant Quantum Engineering

Construction Contractor Martinez Brothers

Page 2 of 2