An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. School Board Work SessionNovember 28,2011Revised December 8, 2011 Purpose of Meeting: • Presentation of Options Related to Building Utilization – Overall Cost Analysis* • Public Hearing • Fluvanna County School Board Discussion *Figures are estimated throughout from 2010 budget guidelines

  2. Current Expenditures* School Utilities Costs Staff Costs Central Elementary $193,000 $8,600,000 Cunningham Elementary $32,500 $2,225,000 Columbia Elementary $19,000 $960,000 Middle School $146,000 $5,600,000 Fluvanna County High School $313,000 $6,900,000 _______________________________________________________________________ Total: $703,500 $24,285,000 *Schools only and all figures have been approximated and rounded

  3. New High School • Utilities Costs $426,000.00 • Staffing Costs $330,000.00 (3 CTE Teachers and 5 Custodial / Maintenance) _______________________________ TOTAL $756,000.00

  4. OPTION 3 School Grades Students Capacity 2016-17 (Projected) (Based on 11/11) (SOQ Per Sq. Ft.) Central Elementary PK - 2 644 1060 671 Cunningham Elementary PK – 2 180 224 190 Columbia Elementary PK – 2 137 162 137 Upper Elementary 3 – 4 576 720 608 Intermediate School 5 – 7 857 1070 912 Fluvanna County H.S. 8 – 12 1475 1611 1520 2016-17 projections based on 3,958 students / 13 = 304 per grade level Revised 12/8/11

  5. OPTION 3 COSTS • Additional Staffing $300,000 ( 7 custodians, 2 office staff, 1 admin conversion ) • Modular Utilities (Keep 2 units) - $60,000 • Modular Leases -$165,000 • VPSA Funds -$26,000 ______________________________________________ 2012-13 Additional Option 3 Total $49,000 Revised 12/8/11

  6. OPTION 3 COSTS (Cont’d) • 2012-13 Additional Option 3 Total $49,000 • Utilities (Current) $703,500 • Staffing (Current) $24,285,000 • Modular Tear-Down (One time fee) $84,000 • New High School Costs $756,000 Total $25,877,500 Revised 12/8/11

  7. OPTION 3 Possible Implications Academic • Provides up to 4 years at a home school site for PK*-2 and ready access to looping for students needing continued structure and familiarity with staff and program • Lessens the number of students in each school PK – 2, 3-4 and 5-7 • Provides opportunity to redistribute itinerant staff to school site, thus expediting services for children • Provides opportunity to bring Head Start children into our buildings • Expedites response time to staff related to staff development needs, student achievement needs, and system-wide initiatives • Maintains intimate school sites (Cunningham and Columbia) • Offers 8th graders possible increased opportunities to academic enrichment\extension courses • Allows for an extra $26,000 in VPSA technology money * Pre-Kindergarten and early childhood are selected group of children (Approx. 100)

  8. Transportation • High probability that we could run K – 7 bus routes and lessen the number of bus runs and possibly limit usage of older buses Utilities and Operations • Eliminates the need for mobile units across the division; consequently moving approximately 600 students into buildings • Provides opportunity to move operations personnel into former high school site or Palmyra Administrative Office site • Potential for moving alternative education and adult education into Abrams (as appropriate) • Lowers the flow rate at the WWTP (Current HS site) by 800– 900 students Other • Minimal costs associated with required renovation / refurbishment of building • Allows for future increase in enrollment • Grade 5-7 design will change SOQ implications and school coding

  9. OPTION 6 School Grades Students Capacity 2016-17 (Projected) (Based on 11/11) (SOQ Per Sq. Ft.) Central Elementary PK - 4 970 1060 1009 Fluvanna Elementary PK – 4 567 660 587 Intermediate School 5 – 7 857 1070 912 Fluvanna County H.S. 8 – 12 1475 1611 1520 2016-17 projections based on 3,958 students / 13 = 304 per grade level Revised 12/8/11

  10. OPTION 6 COSTS • Renovation Costs$1,400,000 • Modular Utilities (Keep 2 units) - $60,000 • Modular Leases -$165,000 • Cunn. and Columbia Utilities -$51,500 • Staff Redistribution Costs $0 • VPSA Technology Funds $52,000 ______________________________________________ Option 6 Total $1,175,500 Revised 12/8/11

  11. OPTION 6 COSTS (Cont’d) • 2013-14 Additional Option 6 Total $1,175,500 • Utilities (Current – C&C) $652,000 • Staffing (Current) $24,285,000 • Modular Tear-Down (One time fee) $84,000 • New High School Costs $756,000 Total $26,952,500 Revised 12/8/11

  12. OPTION 6 Possible Implications Academic • Provides up to 6 years at a home school site for PK*-4 and access to looping for students needing more structure and familiarity with staff and programs • Provides for consolidated resource availability for children • Provides for increased accountability for vertical planning and growth • Potential for streamlining staff development related to district initiatives, collaboration, and needs related to student achievement issues • Probable need for redistricting to address building capacity for students PK – 4 • Loss of intimate small school sites • Potential marked difference in the student demographics of the two PK-4 schools • Offers 8th graders possible increased opportunities to academic enrichment\extension courses * Pre-Kindergarten and early childhood are selected group of children (Approx. 100)

  13. Transportation • Need for staggered start; therefore, a possible more efficient use of staff and buses Utilities and Operations • Eliminates two school sites; therefore ability to redistribute the savings in utilities from Columbia and Cunningham • Possibility of need for 4 mobile units at Central to accommodate number of students • Cannot go to Option 6 without a transition plan • Potential for closing two school sites that we may need in the future and not be able to obtain Other • Does not allow for increased enrollment / open with maxed capacity (PK-4) • Cannot go to Option 6 without major renovation costs ($1.4m) and we will lose capacity space at the current MS to remain SOQ compliant for PK - 1 • Potential negative public perception from closing 2 schools and risk of faulty conclusions being drawn related to definite need for future space • Grade 5-7 design will change SOQ implications and school coding

  14. Option 6 Brings a Need to TransitionWhat does that look like?

  15. Transition Option 6 COSTS • Renovation Costs $1,400,000 • Modular Utilities (Keep 10 units) - $44,000 • Modular Leases -$125,000 • Middle School Utilities (Approx. reduction) -$70,000 • Staff (2 Custodians) $60,000 • VPSA Funds $26,000 ______________________________________________ Transitional Option 6 Total$1,247,000 Revised 12/8/11

  16. Possible Transitional Implications Option 6 • Closing the middle school would have to occur in order to prepare for the $1.4m renovation project to convert this site into a Pre-K to 4 elementary school. • Uncertainty of funding for the renovation of this site; therefore, it would be tough to predict when we would move into two Pre-K -4 sites. • Creates a need to continue to have 8 modular units at Central and Cunningham (4 each).

  17. Could Option 3 bring a NEED to transition?If so, what does that look like?

  18. Transition Option 3 COSTS • Modular Utilities (Keep 10 units) - $44,000 • Modular Leases -$125,000 • Middle School Utilities (Approx. reduction) -$70,000 • Staff (2 Custodians at new middle) $60,000 • VPSA Funds $26,000 ______________________________________________ Transitional Option 3 Total-$153,000 Revised 12/8/11

  19. Possible Transitional Implications Option 3 • Offers an opportunity for us to redistribute the funds associated with the costs of utilities for that site to the costs for opening the new high school for one year. • Increases the risk of public perception that the building is not needed and enrollment is flat or dwindling. • Increases the risk for not being able to predict when we would be able to financially support the re-opening of the school. • Creates a need to continue to have 8 modular units at Central and Cunningham (4 each).

  20. What does it all mean when it comes to final costs and comparison?Note: Savings will be embedded and figures will change yearly.

  21. Costs Comparison Summary Revised 12/8/11

  22. What about our other buildings?Could we save money by closing one?Yes, but…•Abrams - $20,000 SBO - $23,000•Reality – Moving technology and the infrastructure at this point would be very expensive (money and time).•Renovation costs for office space and ADA compliance could easily begin to exceed $500,000.•All of these associated costs would remain constant under any option and only vary in impact if staffing came into consideration.

  23. Questions and Discussion???Thank You!