Maintenance Dec 5, 2007. Accelerator Access. LINAC will remain on for BLIP. Booster- am Access only. AGS- CA 0730-1200hrs. RHIC Experimental and select areas on RA. Sweeps start at 1200hrs. RHIC RF area on 1004b control am. AC work in 4Z2 in the am.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha

Download Presentationdownload

Maintenance Dec 5, 2007

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Maintenance dec 5 2007

Maintenance Dec 5, 2007


Accelerator access

Accelerator Access

  • LINAC will remain on for BLIP.

  • Booster- am Access only.

  • AGS- CA 0730-1200hrs.

  • RHIC Experimental and select areas on RA. Sweeps start at 1200hrs.

  • RHIC RF area on 1004b control am. AC work in 4Z2 in the am.

  • RHIC RF Cooling tower cleaning RF on by 1400hrs.


Schedule

Schedule:

  • Injectors off at 0630hrs.

    • BLIP REMAINS ON!

  • RHIC off at 0800hrs or dump.

  • AGS secured at 1200hrs.

  • RHIC MMPS testing begins at 1200hrs.

  • RHIC areas swept as work is completed or by 1400hrs.

  • Experiments Swept at 1500hrs.

  • RHIC secured by 1600hrs.


Major impact jobs

Major impact jobs

  • RHIC alcove and PHENIX Air Conditioning.

  • Substation R, building 929 RF equipment affected. May be rescheduled if parts do not arrive.

  • RHIC RF tower cleaning.

  • RHIC generator switch tests.


Reminders

Reminders:

  • Be sure to inform the MAINTENANCE COORDINATOR of issues on machines undergoing maintenance.

  • Approved jobs only-NO JOB TOO SMALL!

  • Testing period after jobs completed.

  • Affected groups input for job closeout.

  • Personnel availability until systems prove operational.