WiFi Project Updates. (P17870) WiFi Vendor Comparison and RFP. Program Agenda. (P17870) WiFi Vendor Comparison and RFP Authentication re-design Roll out plan – Complete FY13 budget $1.7M FY14 budget $3.5M FY15 budget $2.6M. WiFi RFP Update - (P17870) WiFi Vendor Comparison and RFP.

Download Presentation

WiFi Project Updates

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Wifi project updates

WiFi Project Updates

(P17870) WiFi Vendor Comparison and RFP


Program agenda

Program Agenda

  • (P17870) WiFi Vendor Comparison and RFP

  • Authentication re-design

  • Roll out plan – Complete

    • FY13 budget $1.7M

    • FY14 budget $3.5M

    • FY15 budget $2.6M


Wifi rfp update p17870 wifi vendor comparison and rfp

WiFi RFP Update - (P17870) WiFi Vendor Comparison and RFP

  • RFP complete as of 04-May-2012

  • Rollout plan complete and communicated

  • Access point placement training complete

  • Hardware STR applied for – expected 11-OCT-2012

  • Engineering Package for controllers – Complete and approved, additional engineering package for the actual installation needs to be completed

  • Controller purchase requisitions are placed – Installed and working HQ,ADC,RMDC,JAPAN, SG-almost complete. EMEA,AU,India may have to wait until after freeze.

  • Controller installation guide – completed (12-Oct-2012)

  • Complete pilot sites – in work

  • Change existing WiFi hardware standards for other locations – Complete

  • Work with authentication and management team on new design and start pilot – in work

  • Order other infrastructure components - this includes authentication and management system components

  • Authentication design package into CSARB and STR – in work

  • Authentication design package into technical review

  • Change WiFi design standard

  • Order authentication and management equipment

  • Install authentication and management equipment

  • Implement new authentication method into production