Mantoloking & Super Storm Sandy
This presentation is the property of its rightful owner.
Sponsored Links
1 / 14

Mantoloking & Super Storm Sandy PowerPoint PPT Presentation


  • 117 Views
  • Uploaded on
  • Presentation posted in: General

Mantoloking & Super Storm Sandy. Update #3. Mantoloking & Super Storm Sandy. AGENDA : Overview Current Status Short-Term Plan Long-Term Plan Resources. 2. Mantoloking & Super Storm Sandy – Current Status. INFRASTRUCTURE: STATE DOT Project : Finished

Download Presentation

Mantoloking & Super Storm Sandy

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy

Update #3


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy

  • AGENDA:

  • Overview

  • Current Status

  • Short-Term Plan

  • Long-Term Plan

  • Resources

2


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy – Current Status

  • INFRASTRUCTURE:

  • STATE DOT Project:

  • Finished

  • Working traffic light on Herbert

  • Guardrails in place

  • Sidewalks, curbs, grass (!?!)


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy – Current Status

  • INFRASTRUCTURE:

  • DEBRIS REMOVAL:

  • 26,000 tons to date

  • Continuous

  • Private Property Debris Removal (including demolition) under discussion

  • with FEMA.

  • SAND REMOVAL/RE-USE:

  • Army Corps dredging Lyman

  • Temporary sifting station will be in place immediately after dredge work is complete.


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy – Short-Term Plan

  • Access:

  • New Access System in place

  • Priority: First Responders / Residents

  • Contractors next


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy – Short-Term Plan

  • Administration:

  • Tax reassessment- Complete assessment by Property by March, 2013

  • Prepare for Reconstruction: Planning Board considering new zoning req’s based on revised elevation guidelines from FEMA (issued last week)

  • Streamline permit process

  • Planning Board working with Borough: Resolution being drafted allowing: PODs, RVs, Boats, etc.


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy

  • UTILITIES (Current Status):

  • Sanitary Sewer

  • Over 15,000 lf (3 miles) of sewer main cleaned and inspected

  • Force main pressurized and discharging clean water to OCUA

  • Water

  • 90% of main restoration complete

  • Pressure testing and water quality testing for 8” main on Rt. 35

  • Gas

  • 70% of main restoration complete

  • Portion of Barnegat Lane and Lagoon/Channel not pressurized

  • Electric

  • 85% of distribution grid energized

  • Areas around Barnegat Lane and Herbert St breach not energized

7


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy

  • UTILITIES (Short Term Planning):

  • Sanitary Sewer

  • Complete the remainder of sewer main CCTV inspection/cleaning

  • Install temporary pump system at Herbert Street

  • Water

  • Repair damaged fire hydrants

  • Install new services for properties off of new 8” main in Rt 35

  • Gas

  • Pressurize and perform full assessment of Lagoon/Channel area

  • Replace 2” main on Barnegat Lane

  • Electric

  • Complete the replacement of overhead distribution

  • Ensure safety policies remain in place throughout restoration work


Mantoloking super storm sandy

Mantoloking & Super Storm Sandy – Happy Holidays