IBL CO 2 cooling control system development status 10 .0 4 .2013

IBL CO 2 cooling control system development status 10 .0 4 .2013. Lukasz Zwalinski – PH/DT /DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC. Presentation overview. Control cabinets – progress Local box – progress Chilller control system V acuum system.

verna
Download Presentation

IBL CO 2 cooling control system development status 10 .0 4 .2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IBL CO2 coolingcontrol system development status10.04.2013 Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC

  2. Presentation overview Control cabinets – progress Localbox – progress Chilllercontrolsystem Vacuumsystem

  3. Control cabinets – status Control/electrical rack layout design completed Electrical schematics nearly completed by Florian 95% of control hardware components ordered and delivered Assembly by EN/CV in progress

  4. Localbox for maintenanceoperation Mechanicalassemblywelladvanced (PH/DT) Allcomponents are ordered Front panel to be graved with P&ID by NIKHEF Electricalassemblyalreadystarted

  5. Localbox for maintenanceoperation

  6. Chilllercontrol system We decided to bulidup the chillercontrol system by ourself Base on expirence from MARCO coolingsystem

  7. Chilllercontrol system WorksplitedbetweenPH/DT and EN/CV Electrical schematicby PH/DT Components integration in the cabinet byPH/DT Construction and cabling of the cabinet byEN/CV Purchaseof components: Frequency inverterandexpansion valves controllers by PH/DT Electrical components by PH/DT and EN/CV Electrical cupboards byEN/CV

  8. Vacuum system Contact with TE-CRG-CE (Controls and ElectricalSupport)

  9. ThankYou Controlsystem development status IBL CO2 cooling10thApril2013