PROJECT : GTFS Reporting period : 1/8/13 – 30/8/13 - PowerPoint PPT Presentation


  • 102 Views
  • Uploaded on

PROJECT : GTFS Reporting period : 1/8/13 – 30/8/13. Project Brief/Summary RM3.5 billion allocation loan guarantee scheme from 2010 to 2015 with the objective to provide easier access to financing for producers and users of green technology . 60% government guarantee

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' PROJECT : GTFS Reporting period : 1/8/13 – 30/8/13' - velma


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Project gtfs reporting period 1 8 13 30 8 13
PROJECT: GTFSReporting period: 1/8/13 – 30/8/13

Project Brief/Summary

  • RM3.5 billion allocation loan guarantee scheme from 2010 to 2015 with the objective to provide easier access to financing for producers and users of green technology.

  • 60% government guarantee

  • Rebate 2% p.a. of interest/profit

    Objectives

  • To promote the utilisation of the Scheme to drive the development of green businesses.

  • To create awareness and increase in adoption of green technology to facilitate the growth of the industry enhancing its contribution to the national economy.

Project Fund : RM1,203,695

Duration : 1/1/2013 – 31/12/2013


Project gtfs reporting period 1 8 13 30 8 131
PROJECT: GTFSReporting period: 1/8/13 – 30/8/13

Activities Completed (During reporting period)

  • Business Review Presentation (22/8/13)

  • GTFS Enhancement Workshop (27/8/13)

    % completed: 31% based on 13 activities

    % funds utilised : 42% as of 31 July 2013

  • Activities Planned (For next reporting period)

  • GTC Meeting No.7 (12/9/13)

  • Training for FIs (23-27/9/13)


Project gtfs reporting period 1 8 13 30 8 132
PROJECT: GTFSREPORTING PERIOD : 1/8/13 – 30/8/13

Impacts of the Project

  • New investment realisedRM510.4 million.

  • A total of 178 green collar personnel.

  • 517,329 tCO2e GHG emission reduction.

  • Photos of activities for the period of reporting

  • GTFS Enhancement Workshop on 27/8/13