MRP 及 CRP 的使用 在本课中 , 您将学习如何 :

next. MRP 及 CRP 的使用 在本课中 , 您将学习如何 :. 在 MFG/PRO eB 中设置 MRP 及 CRP 之前所应明确掌握的关键业务流程 在 MFG/PRO eB 中设置 MRP 及 CRP Use MRP and CRP in MFG/PRO eB. 在 MFG/PRO eB 中使用 MRP 及 CRP. 浏览执行提示信息. next. 批准计划工单. 浏览 MRP 信息. 计算产能计划. MRP 流程. 核对低层代码. 计算需求. 核对低层代码. 计算需求. 浏览执行提示信息. next. 批准计划工单.

Download Presentation

MRP 及 CRP 的使用 在本课中 , 您将学习如何 :

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. next MRP及CRP的使用在本课中,您将学习如何: • 在MFG/PRO eB中设置MRP 及CRP之前所应明确掌握的关键业务流程 • 在MFG/PRO eB中设置MRP及CRP • Use MRP and CRP in MFG/PRO eB • 在MFG/PRO eB中使用MRP及CRP eB-MRP-PR-010

  2. 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 核对低层代码 计算需求 eB-MRP-PR-020

  3. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 低层代码更新 23.22 eB-MRP-PR-030

  4. next 23.22 – 低层代码更新 eB-MRP-PR-040

  5. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 计算需求 eB-MRP-PR-050

  6. Net Change Update 核对低层代码 计算需求 浏览执行提示信息 next 再生式物料需求计划 批准计划工单 浏览MRP信息 计算产能计划 选择式物料计划 计算需求 净改变式物料计划 23.1 计算需求 eB-MRP-PR-060

  7. next 23.1 – 净改变式物料计划 eB-MRP-PR-070

  8. 净改变式物料计划 核对低层代码 计算需求 浏览执行提示信息 next 重新产生计划 批准计划工单 浏览MRP信息 计算产能计划 选择式物料计划 计算需求 计算需求 再生式物料计划 23.2 eB-MRP-PR-080

  9. next 23.2 –再生式物料计划 eB-MRP-PR-090

  10. 净改变式物料计划 核对低层代码 计算需求 浏览执行提示信息 next 再生式计划 批准计划工单 浏览MRP信息 计算产能计划 选择式物料计划 计算需求 计算需求 选择式物料计划 23.3 eB-MRP-PR-100

  11. next 23.3 – 选择式物料计划 eB-MRP-PR-110

  12. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 执行提示信息更新 23.5 eB-MRP-PR-120

  13. next 23.5 – 执行信息检查/更新 eB-MRP-PR-130

  14. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 批准计划工单一 eB-MRP-PR-140

  15. Work Orders 核对低层代码 计算需求 浏览执行提示信息 next 采购单 批准计划工单 浏览MRP信息 计算产能计划 批准计划工单 计划加工单 23.10 批准计划工单 eB-MRP-PR-150

  16. next 23.10 – 计划工单批核:第1屏 eB-MRP-PR-160

  17. next 输入相应的项次工单号码 23.10 –计划工单批核:第2屏 eB-MRP-PR-170

  18. 工单 核对低层代码 计算需求 浏览执行提示信息 next Purchase Orders 批准计划工单 浏览MRP信息 计算产能计划 已批核的计划工单 批准计划工单 采购单 23.11 eB-MRP-PR-180

  19. next 23.11 – 计划采购单批准: 第1屏 eB-MRP-PR-190

  20. next 23.11 –计划采购单批准: 第2屏 输入相应的项次号码 eB-MRP-PR-200

  21. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 浏览MRP信息 eB-MRP-PR-210

  22. MRP Summary 核对低层代码 计算需求 浏览执行提示信息 next MRP明细 批准计划工单 浏览MRP信息 计算产能计划 过期到货 浏览MRP信息 MRP汇总 23.13 浏览MRP信息 eB-MRP-PR-220

  23. next 23.13 – 物料需求计划汇总查询 eB-MRP-PR-230

  24. next 23.14 –物料需求计划汇总报表 eB-MRP-PR-240

  25. next 23.14 –物料需求计划汇总报表: 范例 eB-MRP-PR-250

  26. MRP汇总 核对低层代码 计算需求 浏览执行提示信息 next MRP Details 批准计划工单 浏览MRP信息 计算产能计划 过期到货 浏览MRP信息 MRP 明细 23.16 浏览MRP信息 eB-MRP-PR-260

  27. next 23.16 –物料需求计划明细查询 Item Number: 10-10000 Qty On Hand: 0.0 Site: 10000 OASIS(TM) COOLING SYSTEM HOME/INDUST MODEL UM: EA Pur/Mfg: C Buyer/Planner: Ord Pol: POQ Min Ord: 0 Mfg LT: 1 Master Sched: yes Ord Period: 7 Max Ord: 0 Pur LT: 0 MRP Required: no Time Fence: 0 Ord Mult: 0 Ins LT: 0 Plan Orders: yes Safety Time: 0 Order Qty: 0 Inspect: no Issue Policy: yes Safety Stk: 0 Yield%: 100.00% Cum LT: 8 Due Date Gross Reqs Sched Rcpt Proj QOH Plan Ords Details -------- ---------- ---------- ---------- ---------- ------------------------- 0 Beginning Available 03/03/94 100 -100 S/O: SO10025 Line: 1 03/03/94 125 -225 S/O: SO10026 Line: 1 03/03/94 50 -275 S/O: SO10027 Line: 1 03/03/94 50 -325 S/O: SO10028 Line: 1 03/03/94 -225 100 PLANNED F/A ORDER S/O: SO10025 Line: 1 Release Date 03/02/94 eB-MRP-PR-270

  28. MRP汇总 核对低层代码 计算需求 浏览执行提示信息 next MRP 明细 批准计划工单 浏览MRP信息 计算产能计划 Past Due Receipts 浏览MRP信息 浏览MRP信息 过期到货 23.19 eB-MRP-PR-280

  29. next 23.19 – 过期到货查询 Item Number: 10-10000 Buyer/Planner: Site: 10000 OASIS(TM) COOLING SYSTEM HOME/INDUST MODEL Due Date Release Qty UM Details -------- -------- ------------ -- ---------------------------------------- 03/10/94 03/10/94 1,180.0 EA Work Order past due W/O: 03030038 ID: 401507 03/14/94 03/03/94 100.0 EA Work Order past due W/O: 03030004 ID: 401499 03/21/94 03/03/94 100.0 EA Work Order past due W/O: 03030005 ID: 401500 03/03/94 03/02/94 50.0 EA PLANNED F/A ORDER past due S/O: SO10027 Line: 1 03/03/94 03/02/94 50.0 EA PLANNED F/A ORDER past due S/O: SO10028 Line: 1 03/03/94 03/02/94 100.0 EA PLANNED F/A ORDER past due S/O: SO10025 Line: 1 03/03/94 03/02/94 125.0 EA PLANNED F/A ORDER past due eB-MRP-PR-290

  30. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP 流程 CRP 处理流程 计算产能计划 24.1 eB-MRP-PR-300

  31. 24.1 – 重新计算生产能力计划 next 产能需求计划重计算包括系统中所有的工单. eB-MRP-PR-310

  32. 无限产能计划将不考虑产能 next 产能 有限产能计划永远不会超过产能 产能 无限及有限产能计划 eB-MRP-PR-320

  33. next 车间产能为部门人工产能及工作中心工时 部门及工作中心产能 eB-MRP-PR-330

  34. next 24.4 – 投入/产出查询 eB-MRP-PR-340

  35. next 24.5 – 投入/产出报表 sfiorp.p 24.5 输入/输出报表 日期: 10/28/02 页号: 1 MFG/PRO Training DB - V90 时间: 15:58:22 工作中心: 4010 WELD 设备/工序: 1 设备: 30 排队时间: 1.0 设备/中心: 1.000 部门: 40 Fabrication 等待时间: 0.0 操作人数: 1.000 过去 10/28/02 11/04/02 11/11/02 11/18/02 11/25/02 12/02/02 12/09/02 12/16/02 12/23/02 12/30/02 01/06/03 01/13/03 10/27/02 11/03/02 11/10/02 11/17/02 11/24/02 12/01/02 12/08/02 12/15/02 12/22/02 12/29/02 01/05/03 01/12/03 01/19/03 -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- 计划投入 126 0 0 0 0 0 0 0 0 0 0 0 0 实际投入 48 0 0 0 0 0 0 0 0 0 0 0 0 累计投入差异 -78 -78 -78 -78 -78 -78 -78 -78 -78 -78 -78 -78 -78 eB-MRP-PR-350

  36. 部门 工作中心 next 负荷汇总/明细查询/报表 eB-MRP-PR-360

  37. next 24.13 – 工作工心负荷量汇总查询 eB-MRP-PR-370

  38. next 24.14 – 工作中心负量荷汇总报表 eB-MRP-PR-380

  39. next 24.16 – 工作负荷量明细查询 eB-MRP-PR-390

  40. next 24.17 – 工作中心负荷量明细报表 eB-MRP-PR-400

  41. next 24.19 – 部门负荷量汇总查询 eB-MRP-PR-410

  42. next 24.20 –部门负荷量汇总报表 eB-MRP-PR-420

  43. next 24.22 –部门负荷量明细查询 eB-MRP-PR-430

  44. next 24.23 –部门负荷量明细报表 工单 标志 工序 说明 工作中心 机器 开始日期 备时间 运行时间 负荷时间 未结数量 态 ------------------ -------- ------ ------------------------ -------- -------- -------- -------- -------- -------- -------- -- 1030 1097 10 1010 02/15/02 0.0 300.0 300.0 300 零件: dddd AAAAA 1188 10 PENCIL ASSEMBLY 1010 05/30/02 0.0 20.0 20.0 20,000 Q 零件: AAAAA 部门: 20 Packaging eB-MRP-PR-440

  45. 核对低层代码 计算需求 浏览执行提示信息 next 批准计划工单 浏览MRP信息 计算产能计划 MRP/CRP 流程汇总 eB-MRP-PR-450

  46. Exercises 处理练习 eB-MRP-PR-460

  47. next B C D E 子件需求 A 库存余量: 0 每数量: 2 每数量: 1 库存余量: 30 库存余量: 60 每数量: 1 每数量: 2 库存余量: 20 库存余量: 0 eB-MRP-PR-470

  48. 周期 1 2 3 4 5 6 7 8 9 10 需求 25 30 20 35 25 30 25 35 30 25 next LFL FOQ=35 POQ 2 Periods POQ - 2 Periods Min Qty=60 POQ - 2 Periods Multi Qty=25 订货原则及修改标志 eB-MRP-PR-480

  49. A C B (1) (2) next D B (1) (2) 提前期=1周 多笔=250 提前期=2周 多笔=50 周期 B 周期 C 1 2 3 4 5 1 2 3 4 5 毛需求 毛需求 计划收货 计划收货 现有量 30 现有量 60 计划工单收货 计划工单收货 计划工单发放 计划工单发放 每一个周期 = 1 周 (7天) 订单计算 提前期=1周 多笔=200 周期 A 1 2 3 4 5 毛需求 计划收货 0 现有量 计划工单收货 计划工单发放 eB-MRP-PR-490

  50. 层数 0 A (1) (2) (2) 层数 1 B C D next (2) (3) 层数 2 C E 层数 0 F (1) (2) (2) 层数 1 B D E (2) (3) 层数 2 C E 订单计算 eB-MRP-PR-500