An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Management - Instrument, ICC - Otto H. Bauer MPE Garching Management

  2. Important Events • Quarterly Progress Meeting, 15/17 July 03, Cannes • Decision to provide ILT EGSE for warm functional test of FPU delays delivery to Project: • AVM/CQM now mid May 04 • FM now end June 05 • HP-PI-PM Meeting, 22 Oct 03, ESTEC • ILT period of 6 months no longer at risk • Solve instrument problems first Management

  3. Critical Areas • Management • Liaison Project/Alcatel/Astrium/Instrument Teams still with a lot of friction  Quarterly PI-PM meetings with Project  Monthly telecons in between PACS Interface Meetings • Traceability of CR´s and RFW´s (RFD´s ?) still problematic  Alcatel will install accessible data base Management

  4. Critical Areas (II) • Spacecraft Interfaces still not frozen • Thermal Models (orbit, EQM IMT, FM IMT) not stable yet • Influence of straylight in EQM cryostat on IMT conditions • Straylight Model (PACS comments not taken into account)  Very risky situation, as AVM/CQM is nearly ready for ILT • SVM (also PACS input still not complete) Management

  5. Critical Areas (III) • PACS • Monthly reporting still to be improved  More “Team Spirit” necessary ! • PA/QA activities not satisfactory • FMECA, HSIA, .. (contractual or funding reasons) • Incoming inspection: Mirrors, Chopper  Improve procedure • Documentation • Science Requirements, Instrument Requirements, Instrument Description  Minor updates for AVM/CQM EIDP • FMECA, ...  Major updates when reports are available (WE QM´s and FM) • AIV, Test Plan  Updates foreseen for mid Jan 04, we started with lower level doc´s: PCD, ... Management

  6. Critical Items • PACS DPU (IFSI) • 1553/1355 problems still not solved  At present we have no working warm electronics • FPU Grating Launch Lock: Possible single point failure for Spectrometer part • PhFPU Cooler: Evaporator L0 interface: Possible single point failure for Bolometer part Management

  7. Funding • MPE • Funding gap 2.8 M€ , ESA covers 2.0 M€, 0.8 M€ still open, DLR/ESA have to find solution before end of 2003 • IFSI • No funding received since 2001, personnel secure until end Dec, no travel money left • Funding for QM and FM manufacture not approved yet  DPU FM delivery to MPE: Oct 04  Now end Nov 04 • IAC • Funding for QM and FM manufacture not fully approved yet  SPU FM delivery to MPE: June 2004 or later • UVIE • Funding problem solved, but not much travel money Management

  8. Personnel • Instrument • CEA: O. Boulade started working on Bolometer data • MPIA: K. Eberle left, she was working on Ge:Ga detector data • KUL: P. Royer is overseeing the CRE/FEE activities at IMEC and the integration of FEE´s at ASTEQ. He is also managing the interfaces with ASTEQ • ICC • MPIA: R.Vavrek will leave spring 04  PACS calibration scientist at HSC • MPIA: J. Schreiber will start 01 Jan 04 • IAC: S. Grothe started beginning of July, she will be member of the Calibration and IA WG • KUL: J. Vanautgaerden is replacing P. Royer • OT/OP: G. Rodighiero is replacing P. Panuzzo ( SPIRE) Management