The alignment of the LHC during the shut-down 2008-2009. D. Missiaen. Outline. Repair of sector 34 Maintenance alignment Roll angle measurements Vertical smoothing of the LHC Horizontal smoothing of the LSS Case of the LSS with experiments Conclusions. Repair of sector 34.

Download Presentation

The alignment of the LHC during the shut-down 2008-2009

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


The alignment of the lhc during the shut down 2008 2009

The alignment of the LHC during the shut-down 2008-2009

D. Missiaen


Outline

Outline

  • Repair of sector 34

  • Maintenance alignment

    • Roll angle measurements

    • Vertical smoothing of the LHC

    • Horizontal smoothing of the LSS

    • Case of the LSS withexperiments

  • Conclusions

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Repair of sector 34

Repair of sector 34

A measurement of the position « after incident » wasdone

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Repair of sector 341

Repair of sector 34

  • A zone of 700 m of 39 dipoles and 14 quads

    • Fiducialisation

    • Alignment of BPM in quads

    • Beamscreen and Tubes positioning on both types

    • Main difficultywas to re-start an activitystoppedtwoyearsbefore

      • « Fiducialisation » benchesweredismantled

      • Motorized system without maintenance

      • Software not running

      • Interface to databasehad to beupdated

    • After a re-learningcurve, whole job done in 3-4 months

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Repair of sector 34 2

Repair of sector 34 (2)

  • Initial alignmentdonewith respect to the geodetic network

    • NOT the normal procedure

    • BUT geodetic network wasstill consistent withmagnets

    • Accuracyobtained 0.3 mm at 1s.

  • Local smoothingdonedirectly on fiducials on areas of 100m. => OK to the interconnection team

    • Offsets to a stretchedwire – Digital levels

    • Accuracyobtained 0.15 mm at 1 s.

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Vertical smoothing of sector 34

Vertical Smoothing of sector 34

  • 49 magnetsrealigned (22%)

  • No more in the damaged area thanelsewhere

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Horizontal smoothing of sector 34

Horizontal smoothing of sector 34

  • 41 magnetsrealigned

  • MB.B29L4.E:1.5 mm

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Alignment maintenance

Alignment Maintenance

SU alwaysclaimedthatitwilltaketwo to threeshut-downs to have the « best smoothed» position of the magnets

This was an opportunity to startwith the improvementcampaigns

All magnetswereunder cold conditions

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Roll angle measurements

Roll angle measurements

  • Mvtsbetween 2008 and 2009

  • For eachsector :

    • Avgis close to 0

    • Stdevisbetween 0.06 and 0.09 mrad

    • 55 magnetsrealigned

    • S34 : stdev = 13mrad, 100 magnetsrealigned

  • S67: q8r6 moved due to concreteslabproblem

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Vertical smoothing

Vertical smoothing

  • Absolute vertical shape

  • Closure +2.4 mm

  • Not fixed on the deepreferences

  • Pb withconcreteslab in LSS6

  • Hole of S78

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Sector 78

Sector 78

  • The wellknown « LEP hole » of 2mm per yearre-appeared in 2009

  • Weshould have leftitlikethatbecauseitissmooth but finallyitwasdecided to realigned to the theoretical position

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Vertical smoothing1

offset

Length of the window

Vertical smoothing

  • The relative position of the magnetsis more important for the beamthan the absolute one

  • The deviationsw.r.t a smoothcurve, much more significant, werecalculatedwith PLANE

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Horizontal survey of lsss

Horizontal survey of LSSs

  • Straight lines of 500 m on each part of the IP from Q8Ln to Q8Rn

  • 4 of them are equipedwith permanent monitoring systemsbecause of the obstacle of the Experiment and of the low beta quadrupoles

  • The aimwas to link

    • the standard arc with the LSS

    • The LSS to the low beta quads

      Beforethese areas become radioactive

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Horizontal survey of lsss1

Horizontal survey of LSSs

  • Methodology

    • Long stretchedwire of 160 m with an overlap of almost 100m

    • Measurementsissuedfrom permanent sensors values

  • Calculations

    • Q2Ln considered as fixed point, Q2Rn orientation point

    • Radial corridors of 1 mm at the vicinity of the Q8s in order NOT to make a stepat the junction

    • Add relative position of « standard » and « permanent monitoring » fiducials

    • Residualswerebetterthan 0.1mm. Someinconsistenciesbetweenmeasurements of different types and accuracies

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Horizontal survey of lsss1 2 5 and 8

Horizontal survey of LSSs1, 2, 5 and 8

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Conclusions

CONCLUSIONS

  • Leveling and roll angles allowed the detection of unstable areas (sector 78, LSS6R, etc)

  • The vertical smoothing of all LHC sectorsimproved the relative accuracy to betterthan 0.1 mm at 1 s

  • Horizontal smoothingwith long stretchedwireswas a success

  • Horizontal position of the low beta quads wasimproved

  • A huge effort to measure and to realign but itisworthit

  • LHC willrununtil the end of 2011, then a hugeshut-down in 2012 and part of 2013. A rythm of a shut-down everythreeyearswillbeadopted

IWAA2010, 13-17 Sep. 2010, DESY Hamburg


Conclusions1