An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 17 Activity-Based Costing and Analysis

  2. Assigning Overhead Costs C1 Direct Materials Indirect FactoryOverhead Goods in Process FinishedGoods Allocate Indirect Cost of GoodsSold Direct Labor 17-2

  3. Single plant-wide rate Departmental overhead rates Activity-based costing Assigning Overhead Costs C1 Overhead can be assigned to production in one of three ways: 17-3

  4. $4,800,000 100,000 DLH = $48/DLH Plant Wide Overhead Rate Method Illustration P1 Plantwide overhead rate = 17-4

  5. Machining Department Overhead Rate $4,200,000 70,000 MH = = $60/MH $600,000 30,000 DLH Assembly Department Overhead Rate $20/DLH = = Departmental Overhead Rate Method: Second Stage P2 17-5

  6. Step Three: Determine Activity Rate P3 17-6

  7. Plantwide Overhead Rate Method Advantages and Disadvantages A1 Advantages • Information is readily available • Easy to implement • Often sufficient to meet external financial reporting needs Disadvantages • Overhead costs may not bear any relationship with direct labor hours • All products may not use overhead costs in the same proportion 17-7

  8. Indirect Costs Single Plant-Wide Overhead Rate Cost Allocation Base Cost Objects Product 1 Product 2 Product 3 Plant Wide Overhead Rate Method P1 Overhead Cost 17-8

  9. Total budgeted overhead costs Total budgeted DLH Plant Wide Overhead Rate Method Illustration P1 Plantwide overhead rate = 17-9

  10. Plant Wide Overhead Rate Method Illustration P1 17-10

  11. $4,800,000 100,000 DLH = $48/DLH Plant Wide Overhead Rate Method Illustration P1 Plantwide overhead rate = 17-11

  12. Plant Wide Overhead Rate Method Illustration P1 17-12

  13. Advantages and Disadvantages of Departmental Overhead Rate Method A1 • Disadvantages • Can distort product costs • Assumes that products are similar in volume, complexity, batch size • Assumes that departmental overhead costs are proportional to the allocation base • Advantages • More accurate overhead allocations • More refined than the plantwide overhead rate method 17-13

  14. Total departmental overhead costs Total unit number in departmental allocation base Departmental Overhead Rate Method: Second Stage P2 Departmental Overhead Rate = 17-14

  15. Departmental Overhead Rate Method: First Stage P2 Overhead Cost $4,800,000 First Stage Machining Dept. $4,200,000 Assembly Dept. $600,000 17-15

  16. Departmental Overhead Rate Method: Second Stage P2 17-16

  17. Machining Department Overhead Rate $4,200,000 70,000 MH = = $60/MH $600,000 30,000 DLH Assembly Department Overhead Rate $20/DLH = = Departmental Overhead Rate Method: Second Stage P2 17-17

  18. Departmental Overhead Rate Method: Second Stage P2 17-18

  19. Advantages and Disadvantages of Activity-Based Costing A3 • Advantages (Continued) • Can assist in distin-guishing value added activities • Advantages: • More accurate overhead cost allocation • More effective overhead cost control • Focus on relevant factors • Better management of activities • Disadvantages: • Costs to implement and maintain • Uncertainty with decisions still remains 17-19

  20. Cost Flows Under Activity-Based Costing Method C2 Indirect Costs Overhead Cost First Stage Activity Cost Pool X Activity Cost Pool Y Activity Cost Pool Z Cost Objects Second Stage Activity Overhead rate Activity Overhead rate Cost Allocation Base Activity Overhead rate Cost Objects Product 1 Product 2 Product 3 17-20

  21. Applying Activity-Based Costing P3 4 steps: • Identify activities and the costs they cause. • Group similar activities into activity pools. • Determine an activity rate for each activity cost pool. • Allocate overhead costs to products using those activity rates. 17-21

  22. Unit level Batch level Product level Facility level Four types of activities that cause overhead costs C3 17-22

  23. Unit level Levels of activities C3 Unit level activities are performed on each product unit. Example: 1) Cutting parts driver: machine hours/labor hrs 2) Printing checks driver: number of checks 17-23

  24. Batch level Levels of Activities` C3 Batch level activities are performed only on each batch or group of units. Example: 1) Machine Setups (readying machine) driver: number of setups 2) Receiving shipments driver: number of orders 17-24

  25. Product level Levels of Activities C3 Product level activities are performed on each product line and are not affected by either numbers of units or batches. Examples: 1) Design modifications driver: Change requests 2) Organizing Production driver: Engineering Hours 17-25

  26. Facility level Facility Level Activities C3 Facility level activities are performed to sustain facility capacity as a whole and are not caused by any specific product. Example: 1) Cleaning work space 2) Providing electricity Driver: 1) Square feet of floors 2) Kilowatt Hours 17-26

  27. Step Two: Trace Overhead Costs to Cost Pools P3 Overhead Cost Activity Cost Pool X Activity Cost Pool Y Activity Cost Pool Z 17-27

  28. Step Two: Trace Overhead Costs to Cost Pools P3 17-28

  29. Step Two: Assigning Overhead to Activity Cost Pools P3 17-29

  30. Step Three: Determine Activity Rate P3 Total cost in activity pool Measure of the activity Activity rate For example: Set-up cost pool activity rate = $2,000,000 / 200 batches = $10,000 per batch Craftsmanship cost pool activity rate = $600,000/30,000 DLH = $20 per DLH = 17-30

  31. Step Three: Determine Activity Rate P3 17-31

  32. Step Four: Assign Overhead Costs to Cost Objects P3 Step 4 is to assign overhead costs in each activity cost pool to final cost objects using activity rates. Activity Overhead rate Activity Overhead rate Activity Overhead rate Product 1 Product 2 Product 3 17-32

  33. Step Four: Assign Overhead Costs to Cost Objects P3 • To illustrate, the overhead costs in the craftsmanship pool are allocated to standard go-karts as follows: Overhead allocated to standard go-kart = Activities consumed X Activity rate= 25,000 DLH x $20 / DLH = $500,000 17-33

  34. Step Four: Assign Overhead Costs to Cost Objects P3 17-34

  35. Step Four: Assign Overhead Costs to Cost Objects P3 17-35

  36. Comparison of Overhead Allocations by Method C1 17-36