An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 10 things you need to know aboutCAPITAL

  2. 1. AASB 116 – Property, Plant & Equipment Objective: • Prescribe the accounting treatment for property, plant and equipment (PP&E). • Allow users of the financial statements to discern information about an entity’s investment in its PP&E, and the changes in such investment.

  3. AASB 116 (Cont’d). Recognition of an Asset The cost of an item of PP&E shall be recognised as an asset if, and only if: • (a) it is probable that future economic benefits associated with the item will flow to the entity; and • (b) the cost of the item can be measured reliably. (Source: AASB 116: Property, Plant and Equipment)

  4. 2. C-Funds and Z-Codes • ANU generally uses C-Funds to record capital projects. • Each project is allocated a Z-project code (e.g. Z105) • Benefits: • Allows for whole-of-life reporting on the project • ESP Financials Reports on Z-codes return any transaction that used that project, regardless of Fund, Department or Natural Account combination. • Allows for control on invoice processing and approvals. • Disadvantage: • See above ‘Benefits’

  5. 3. ANU Property ‘Property’ is broadly defined by the University as: • land; • buildings; • site works and services including; • roads • bridges • footpaths • Carparks • Computer Networks, • capital improvements to previously capitalised assets. (Source: ANU Website, F&BS)

  6. ANU Plant & Equipment ‘Plant & Equipment’ is broadly defined by the University as: • Office Equipment, • Research Equipment, • Teaching Equipment, • Computer Equipment, • Motor Vehicles, • Musical Instruments, • Works of Art, and • the Rare Library Collection. (Source: ANU Website, F&BS)

  7. 4. ANU Capitalisation Principles (TBC) New buildings • Costs include: • Feasibility studies and design • Demolition of existing building on the site allocated • Construction • Fit-out • Not included in cost: • GST (residential accommodation may be excepted) • Furniture • Lunches • Tuxedo hire for Building Award Ceremony

  8. ANU Capitalisation Principles (Cont’d) Existing buildings • The nature (with regards to capitalisation) of refurbishment, fitout, update, etc, taking place assists in determining whether costs are to be capitalised or expensed. • Where work is predominantly of a ‘capital’ nature, then relevant ‘expense’ work in the project will alsobe capitalised, • Where work is predominantly of ‘expense’ nature, however some items (which are clearly measurable), are of ‘capital’ nature, a split will be done to treat those costs according to their nature.

  9. ANU Capitalisation Principles (Cont’d) • Determining the nature of a project (with regard to capital or expense) is assisted by examining the existence of the following factors (non-exhaustive): • Work that is probable to increase the future economic benefit to the ANU or the useful life of the asset • Fitout / works to change of use/purpose of the space – Capital • Changes to partitions & walls - imply improve of space use – Capital • Work that enables higher number staff to occupy the space – Capital • Improving functionality of the area – Capital • Plant & Equipment purchased/installed as a ‘set’ with value exceeding the $5,000 threshold will be capitalised.

  10. Examples: • Refurbishment work included new carpets, paint and new air-conditioning, where evaporative cooling was used before: • Expense: Carpets, painting • Capitalise: Air-conditioning (improvement, measurable) • Lecture theatre converted to Laboratory – Capitalise • Fitout configuration was altered by changing partitions – Capitalise • Also capitalise carpet, painting and other expenses. • Projector was purchased for lecture room, including components suc as screen, receiver, speakers, other peripherals. This is considered a ‘set’. • If complete ‘set’ cost >$5,000 – Capitalise.

  11. 5. Capital Works Funding • ANU uses several funding sources, some are regular, while others are non-recurring: - Non-Recurring • Federal Government Grants, e.g.: • EIF – Education Investment Fund – 2009 - $90m, Colleges of Science • BURF – Better Universities Renewal Fund – 2008 - $23.973m –Refurb of libraries, labs, lecture theatres, accommodation, etc. • ACT Government Grants, e.g.: • Fenner School Building - $2.5m • Bonds issued to the Market • Funds multiple Capital projects

  12. Capital Works Funding (Cont’d) • Recurring: • ISF – International Student Fee – Capital Component - Funds BIF (below) Note: ISF Cannot be used to pay directly for Capital Works costs. It only a reimbursement source for other GLC’s which incur these costs. • BIF – Building Infrastructure Fund (a new Fund), funding • Capital Works, • Maintenance, and • Backlog Maintenance. • CMP II Loans • Funding from ANU for capital projects in the form of a loan • Application is required, including a business case, • Approval by VC. • Usual terms are: • Principle + Interest (10-year Commonwealth Government Bond rate) • Term – 15 years, quarterly repayment • No individual CMP II loan to exceed $25 million

  13. 6. Project’s Life • Demand (Master Plan, user groups, etc), • Feasibility Study undertaken (for major projects), • Approval by OVC, including funding sources, • Authorities Approval, • Selection of Project Manager (PM), • Tender & selection • Construction • Certificate of Occupancy => Capitalisation • Insurance, • Commence use, and • Maintenance & Depreciation.

  14. 7. Important External Parties • Project Manager (PM) • Overall responsibility to achieve desired outcome on time and on budget. • Oversees tendering, sub-contractor’s work, payments, liaison with authorities, etc • Receives a fee for service. • Quantity Surveyor (QS) • Employed by the ANU to act on it’s behalf to certify that: • Work is performed according to the contract, Building regulation and Standards, etc • Progress Claims made by PM are corrects.

  15. 8. Retentions • Retentions are agreed sums of money withheld from the sub-contractor invoice/claim while they are performing their work. • Retentions are used as a form of guarantee that the sub-contractor will complete their work, and do so to a satisfactory level. • The project’s GLC is grossed up by the retention. • Once ANU is satisfied with the work performed, the retention funds are released back to the sub-contractor. • Retentions are not held in the project code, but centrally, in a special GLC. They also get paid out from that GLC on completion. Therefore, a release does not ‘reduce’ the project total cost.

  16. 9. (Some of the..) Current Projects • Colleges of Science • Total Budget - $240,000,000 • 4 years duration • 8 new buildings • Multiple sub-projects – Carparking, Equipment Storage, ground infrastructure, numerous staff relocations. • Highest monthly claim – November 2010 - $8.6 million excl GST

  17. Current Projects (Cont’d) • Student Accommodation – Stage #4 (SA4) • Total Budget - $106.5 million • Expected Completion – January 2012 • Number of Apartments: 485 • Number of Beds - 558 (not necessarily equate to number of persons in the beds) • Highest monthly claim – August 2011 - $9.4 million excl GST • Flythrough

  18. 10. Capital Works Accounting – Move to F&S • As of the First week on November 2011, the Capital Works Accounting function has been moved back to F&S Division • The function will operate as part of the general Finance area of the Division. • Main responsibility – Cost side of projects. • Funding responsibility – F&BS Division.

  19. Questions.