1 / 14

A Flood as Big As Rhode Island!

A Flood as Big As Rhode Island!. Background-Flood Timeline. Flood was a two-stage event March 12-15, 2010 First event- 4-6” of rain/hurricane force winds Pawtuxet River crests at 14.98 feet, 5 feet above flood stage and a historic record March 28-April 1, 2010 Second event-8”-12” of rain

ula
Download Presentation

A Flood as Big As Rhode Island!

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A Flood as Big As Rhode Island!

  2. Background-Flood Timeline • Flood was a two-stage event • March 12-15, 2010 • First event- 4-6” of rain/hurricane force winds • Pawtuxet River crests at 14.98 feet, 5 feet above flood stage and a historic record • March 28-April 1, 2010 • Second event-8”-12” of rain • Pawtuxet River crests at 20.79 feet

  3. Pawtuxet River in RI

  4. Scope of DEM Involvement • Overall Unified Command/ICS • Dam Safety • Wastewater Treatment Plant Inundation • Oil and Petroleum Releases • Debris Management • Sediment Characterization & Management • TSDF Impacts • UST Impacts

  5. Overall Unified Command/ICS • Emergency Operations Center activated at State Emergency Management Agency • Web EOC activated for needs/assignments • Emergency Support Functions: • Oil and Haz Mat Response • Public Works- Dam Safety • Debris Management • DEM Agency Desk • Wastewater Recovery TF under Operations

  6. Dam Safety • 42 Inspections at 33 dams • 4 dam breaches • Laurel Avenue-”Signature Site of Crisis” • Staff supplemented by Army Corps of Engineers

  7. Wastewaster Treatment • 2 major plants inundated • Several pump stations impacted • Major downstream risk- water contaminated with sewage • Electronics destroyed • Recovery linked to energy efficiency

  8. Oil and Haz Mat Releases • 170 locations • Lots of loose containers and tanks • Gas cylinders • Many releases inside structures

  9. Debris Management • Extended Landfill and Transfer Station Hours • Household Hazardous Waste Advisories • Segregation of “Green” vegetative wastes • Marine debris

  10. Sediment • Downstream outlet of Pawtuxet River- 18,000 cubic yards of sediment deposited in cove • Concerns about entrainment/deposition of historical contamination • Advisory on treatment with lime- sewage contamination • Strategies for response • Check all known sites for releases/impacts • Respond to all releases discovered • 29 recreation fields underwater- 111 acres • Municipal sampling • Providence-Dioxin (upstream NPL site) • PCB, TPH, Metals, PAH • Street sweepings advisory

  11. Impacted TSDF • Safety Kleen • Activated contingency plan • Relocated drums/wastes • Submerged: • Lab • Records • No releases

  12. USTs • 55 impacted facilities • All inspected post-flood • No major issues • No critical damage • No releases

  13. Lessons Learned • Communications-Getting the word out • Supplemental staffing- back ups for programs expected for response • Planning- Hurricane exercises were very valuable • Working with federal agencies- regular partnerships vs. Stafford Act protocols • Issues with FEMA pre-approvals • Community Expectations of FEMA- can impact all operations.

  14. Questions?