P3K Team Meeting #15. Stephen Guiwits Dean Palmer Ernest Croner Team Meeting #15 -- 126 Cahill October 29, 2009. P3K Electronics Agenda. RTC Electronics (Computer Room) JPL Caltech Active Mirror Electronics (Cass Cage/AO Lab) Xinetics GenIII Integration and Test

Download Presentation

P3K Team Meeting #15

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


P3K Team Meeting #15

Stephen Guiwits

Dean Palmer

Ernest Croner

Team Meeting #15 -- 126 Cahill

October 29, 2009


P3K Electronics Agenda

  • RTC Electronics (Computer Room)

    • JPL

    • Caltech

  • Active Mirror Electronics (Cass Cage/AO Lab)

    • Xinetics GenIII Integration and Test

    • Driver  Electronics Interfaces

      • Active Mirror Cabling

      • Active Mirror Communications

  • The near future


RTC Electronics


RTC Electronics

  • PC 0 – 9 (Telemetry)

    • All components installed

    • Rack Mounted

    • Cabled (JPL Only)

    • Each machine kickstarted

      • Suse Enterprise Linux 10 (non real-time)

    • Actively using for software development (JPL Only)

  • Suse Kickstart DVD

    • JPL version completed

    • Custom RPMS built and tested

    • 2 disks architecture

      • Disk 1 = Base + patches

      • Disk 2 = custom scripts and RPM’s

    • Require two versions (JPL/Caltech)

    • Requires custom kernel patch to see both graphic cards


RTC Electronics

  • Optical Splitter tested. Able to get full frames to all GPU’s

  • Quadrics High Speed Network Switch

    • Installed and configured

    • Suse 10 Linux driver installed

    • Does not work with Real-Time Linux. Quadrics went out of business. We’re currently looking for solutions

  • RAID System

    • Configured for throughput optimization

      • RAID 0

      • Two partitions

        • High Speed data

        • All other data

  • Gigabit Private Ethernet Switch

    • Each PC is able to communicate over the private ethernet

    • Separate from the Quadrics High Speed Switch


RTC Electronics

  • KVM Switch

    • Convenience

    • Allows for graphical access to each machine while working on the racks

    • Helpful while debugging an issue with any one of the 10 machines located in the racks


RTC Electronics

Development Racks

Located at JPL Room: 306-130C

PC 0 – 8

RAID System

KVM Switch

Quadrics High Speed Switch

16 Port Gigabit Ethernet Switch

Optical Splitter

7


RTC Electronics

  • Production Racks (Caltech)

    • Located in Room 17b Cahill Center

    • Machines mounted in racks

    • 2 machines kickstarted for initial testing of Caltech Kickstart

      • JPL System Administrators are still working on the final version of the kickstart

8


RTC Electronics

9


DM Integration and Test


DM Driver Integration and Test

  • July 2009 :: Xinetics :: Devens, Massachusetts

  • Hardware required

    • Xinetics Gen III Mirror Electronics

      • (4U GenIII chassis + 1U fan tray) * 8

    • Perle IOLAN STS Terminal Server

      • 8 RJ-45  9 pin serial adapters

      • 8 RJ-45 cables

    • Custom PCB interface boards

      • Required to cable the mirror

    • Bud Industry 30U Rack (2)

    • Pulizzi IPC 3401 (2)

    • Dell Precision T7400 Computer

    • Associated cabling and interfaces required for integration and test


DM Driver Integration and Test

  • Hardware


DM Driver Integration and Test

  • Software

    • Initial non-high speed software written

    • Communicates via serial terminal server

      • PC  ethernet  terminal server  RJ-45  9 pin  driver

    • Successful command and control of all 8 driver

      • Command set

        • Power up

        • Power down

        • Put driver in proper mode (Normal or Test)

        • Clear faults on the drive (Xinetics feature)

        • Mute the drivers

        • Drive actuator values

        • Drive bias value

        • Read back voltage table (needs tweaking)

        • Read status table (needs tweaking)


DM Driver Integration and Test

  • Testing Results

    • Mirror had some issues. Jenny covered that during the optical bench presentation

    • PCB boards mapped incorrectly. Still able to move every actuator to bias levels

      • Able to re-wire some of the cables so we can continue to use the boards while a final design is being worked on

      • Cables already sent out and modified

    • Software worked upon arrival. Little changes were required to deal with undocumented behavior of the GenIII driver API

    • Optical results were covered in the optical bench presentation


Active Mirror Cabling


Active Mirror Cabling

  • 2 PCB Designs

    • Driver Interface Board (DIB) (x16)

      • 2 per chassis

      • Board routes all actuators, grounds, and bias from driver 50 pin connector to 260 pin connector

    • Mirror Interface Board (MIB) (x16)

      • Board routes actuators, bias, and ground signal from 260-pin connector to 62 and 44 pin connectors

      • 2 pin connectors are used to daisy chain bias and grounds to each PCB as needed


Active Mirror Cabling

High Level Block Diagram


Active Mirror Cabling

Hypertronics N Series Connectors


Active Mirror Cabling

Computer Rendering of the Mirror Interface Box


Active Mirror Cabling

  • Remaining costs to complete the cables and interface boards

    • Procurements

      • Hypertronics (34 plugs&sockets) $29,000DM

      • cables (17)                                    $70,100 ($3800 per cable +tx)

      • Driver interface boards (17)                $1300

      • Rack mounting panels (8)                   $800

      • Driver-rack interface ribbon cables      $1200

      • IDC Connectors for PCB                     $500

      • DSUB connectors for PCB                   $1050

      • DSUB mating connectors                       $1150

      • Back shells for DSUB connectors            $700

      • Mirror interface boards (17)                  $1300

      • Bench interface box (1)                         $1500 

        ---------------

        $108,600


Active Mirror Cabling

  • Remaining costs to complete the cables and interface boards

    • Labor (in days)

      • Mirror interface board design                  1 Weeks

      • Driver interface board design                  3 Weeks

      • Mirror interface cable design                   4 Weeks

      • Procurements                                        3 Days        

      • Rack panel mech. design                        1 Day

      • Bench box mech. design                         4 Days

      • Bench interface box wiring                      6 Weeks

        ------------------------

        15 Weeks 1 Day


Active Mirror Cabling

  • Near-term milestones

    • MIB and DIB designed finished by November 26, 2009

    • 17 custom cables ordered by November 26, 2009

      • Cables have a long lead time

      • Cables can be started without the final connectors available


Active Mirror Communications


Active Mirror Communications


DM High-Speed Data Link

Progress to date

  • Created a CMC Carrier Board hardware requirements specification

  • CMC Carrier Board Circuit design and schematic completed.

  • CMC Carrier Board PCB layout begun.

    • Component placement is almost complete.

    • Most of the individual circuit blocks are wired.

  • During the component placement, I found that we’re not able to fit all the connectors on a 6U VME card without greatly increasing the complexity of the PCB layout (blind vias, increase layer count, etc.).

    • Looked at a few mitigation options:

      • Separate board designs for LODM and HODM

      • Piggy-back board with connectors for HODM

      • Wires from board to enclosure boundary

    • Separate board designs is the best option for signal integrity and board complexity. Much will be shared between the two designs.

  • Selected a COTS cable/connector combination for the interface to the Xinetics chassis.

    • This requires a small adapter board at the Xinetics side

    • Adapter board design is nearly complete.


DM High-Speed Data Link FPGA

CMC Carrier Board FPGA Progress

  • Began initial FPGA development.

  • Simulated flow of data through the FPGA from the serial Front Panel Data Port input to the Xinetics SOR422-U outputs.

    • Still need to work out a minor bug.

    • Need to enhance the state machine for the data input.

    • Need to add inter-actuator checking algorithm.

    • Need to add support for LODM.

    • Need to add test mode.


DM High-Speed Data Link Completion Forecast

Forecast

  • November

    • Complete HODM Carrier Board PCB layout

    • Design review November 10, 2009

    • Receive assembled boards.

    • Complete preliminary FPGA design.

    • Begin board testing.

  • December

    • Create Carrier Board FPGA design specification.

    • Complete HODM Carrier Board testing.

    • Complete LODM Carrier Board PCB layout.


DM High-Speed Data Link Completion Forecast

Forecast (cont.)

  • January

    • Complete Carrier Board FPGA design.

    • Receive assembled LODM Carrier Cards.

    • Test LODM Carrier Cards


The near future

  • Build up RTC racks at Caltech

    • Complete work on Caltech Suse Kickstart

    • Incorporate new kernel findings into every verison of the kickstart

    • Work on Real-Time Linux with Quadrics

  • Build up DM racks at Caltech

  • Test the DM when it arrives from Xinetics

  • Measure power consumption of drivers to help determine proper cooling method

  • Move motion control and acquisition hardware from JPL to Caltech for development and testing

  • Move AO racks down from Palomar. They have been modified with cassegrain cage mounting hardware