Proposal for TC88/PT12-4: Power performance verification of electricity producing wind turbines based on Numerical Site

Proposal for TC88/PT12-4: Power performance verification of electricity producing wind turbines based on Numerical Site Calibration. Akihiro SUZUKI, Wind Energy Institute of Tokyo, Inc. Makoto IIDA, The University of Tokyo. Problem statement.

trapper
Download Presentation

Proposal for TC88/PT12-4: Power performance verification of electricity producing wind turbines based on Numerical Site

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposal for TC88/PT12-4:Power performance verification of electricity producing wind turbines based on Numerical Site Calibration Akihiro SUZUKI, Wind Energy Institute of Tokyo, Inc. Makoto IIDA, The University of Tokyo

  2. Problem statement • The site calibration technique in IEC 61400-12-1 is NOT always applicable for power curve measurements. • The site may be in complex terrain without previous site calibration data. • Hub height wind measurement may be impractical at existing wind turbine site and/or very large wind turbines. • Numerically predicting the flow field, instead of executing field measurements for site calibration using sophisticated computer model (Computational Fluid Dynamics)

  3. Goal • Prepare a new document that describes the standardized technique for power curve measurements using computational fluid dynamics (CFD) models, called Numerical Site Calibration (NSC). • NSC is to be employed at the sites when the site calibration in IEC 61400-12-1 document is impractical. • The document should provide information on the uncertainty on numerically estimating the wind flow field for determining the power curve. • After 3 years of discussion within PT12-2, it proved difficult to achieve a consensus among experts to produce an International Standard (IS). • The convener for PT12-4 proposes to work towards a Technical Specification (TS), instead of an IS.

  4. Scope • The new document should describe the standardized techniques for flow field simulation procedure and field measurement methods tailored for numerical site calibration. • The new document should describe the validation procedure for flow field simulation (CFD) models. • The new document should provide information on the accuracy and uncertainty of the technique. • Working text in English

  5. Work Methods • Description of NSC Procedure • Flowcharts that clarify the standardized procedure • Document the procedure in the flowchart in details • More technical discussions in the PT • Validation of the Technique • To achieve consensus among team members • Clarify the technical issues that need to be defined and to be included in the new document • JP will supply a set of field test data (topographic data and field wind data). • More datafrom other members are appreciated

  6. Japanese Activity for Numerical Site Calibration Mast1 Flat Plane Mast2 Complex Terrain

  7. Project Team • The goal: Draft Technical Specification(DTS) in 20months, approximately by February2012. • The PT plans to meet 3 times per year, 6 times until the completion of a DTS. • Call for PT secretary

  8. Proposed –Time Schedule • June 2010 MTG1, location preferably somewhere in Europe • Presentations from experts • Recognition of Tasks and Issues • Setting up of subtaskteams • October 2010 MTG2 • Discussion on the result of investigation: Stage 1 • February 2011 MTG3 • Discussion on the result of investigation: Stage 2 • Complete the first working draft (WD) • May 2011MTG4 • Discussion on the first WD – Preparing a CD • October 2011MTG5 • Circulate the CD to TC88 • October 2011 TC88 • Report the progress. • February 2012 MTG6 • Drafting for a 2nd CD as a DTS • Circulate a DTS to TC88