Coordination of Right of Way on Design-Build Contracts

Coordination of Right of Way on Design-Build Contracts. By- Richard Bennett State Right of Way Director Virginia DOT. Overall VDOT Design-Build Process. Mostly use two-step process More defined smaller project uses one combined process P 3 projects are generally unsolicited.

tiger
Download Presentation

Coordination of Right of Way on Design-Build Contracts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Coordination of Right of Way on Design-Build Contracts By- Richard Bennett State Right of Way Director Virginia DOT

  2. OverallVDOT Design-Build Process • Mostly use two-step process • More defined smaller project uses one combined process • P3 projects are generally unsolicited

  3. Design-Build Procurement(2 Step) • Internal review to determine projects suitability for D-B and information available • VDOT issues request for Statement of Qualifications (SOQ) providing general project information • Selection Committee established • SOQ received from offerors (usually Contractors are Prime) • Selection Committee evaluates SOQ and shortlists 3 offerors

  4. Design-Build Procurement(2Step) (continued) • VDOT issues a Request for Proposal from short-listed offerors • RFP includes specific requirements including Right of Way acquisition methods and utility relocation coordination • RFP response is a separate detailed technical proposal and cost proposal • Selection Committee evaluates technical proposal (30% score) and then opens and evaluates cost proposals (70% score). May involve interview • Project awarded to offeror with highest total score

  5. Right of Way Involvement • Part of internal review is to determine ROW requirements • Can project be built in existing ROW • Is fee needed or only temporary construction easements • Potential for VDOT to acquire prior to award • ROW acquisition in D-B contract

  6. Right of Way in Design-Build Contract • Creation of ROW allowance for payment • Establishes qualification for ROW Team • Establishes general requirements of process • All consultant cost included in set bid price

  7. Right of Way Coordination • D-B contractor submits detailed ROW plan after award for DOT approval • D-B contractor submits detailed schedule to submit plans for approval and to acquire properties and relocate displacees • Work flow process is mapped and response timeframes are set (usually 15 to 21 days) • Often weekly or biweekly Over The Shoulder (OTS) reviews are included

  8. VDOT Right of WayReviews & Approvals • Completeness of plans for public participation meeting. • Plans adequate for approval to acquire ROW • Notice to commence acquisition (Project or Parcels) • Approval of appraisal and just compensation

  9. VDOT Right of WayReviews & Approvals (continued) • Review and comments on displacee interviews • Review and approval of RHP and Moving Costs • Review and approval of settlement above offer • Review and approval of eminent domain filings

  10. VDOT Right of WayReviews & Approvals (continued) • Certification of parcel/project clearance & notice to commence construction • Payment of landowner or displacee compensation

  11. Right of Way Certification • As parcels are cleared through Option or Eminent Domain a certificate and notice to commence construction is issued • Most projects involve certifying a group of parcels together (re-same block or construction feature)

  12. Design-BuildContractor Provides • Preliminary Title Report • Appraisal and Appraisal Reviews (separate subs) • Negotiations (30 days min.) • Relocation Assistance Services & computations • Settlement recommendations

  13. Design-BuildContractor Provides (continued) • Eminent Domain Documents for refusals • Option agreement and closing documents for voluntary conveyances • Closings, Recording and Title Insurance • Complete file

  14. Quality Control • Over the Shoulder reviews • Appraisal and Just Compensation Approval • Negotiation Report for Closing or Eminent Domain filing • Relocation activities and RHP calculations

  15. D-B vs. VDOT Issues • Timely resolution of design issues • Limits of right of way to be acquired • Limited Access issues • Appraisal quality and scope • Adequacy of negotiations • Pressure to complete parcel for construction access • Cost of design changes for ROW issues