1 / 29

Run II Status and Prospects

Run II Status and Prospects. Jeff Spalding Fermilab June 14, 2004. Contents. Introduction Major elements of the Run II “campaign” Present performance Status of the upgrade projects Luminosity projection Summary. Run II goal: maximize integrated luminosity delivered to CDF & D0 ….

tiana
Download Presentation

Run II Status and Prospects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Run II Status and Prospects Jeff Spalding Fermilab June 14, 2004 Run II Status and Prospects - Spalding

  2. Contents • Introduction • Major elements of the Run II “campaign” • Present performance • Status of the upgrade projects • Luminosity projection • Summary Run II Status and Prospects - Spalding

  3. Run II goal: maximize integrated luminosity delivered to CDF & D0 … Run II Status and Prospects - Spalding

  4. … with a program of upgrades throughout the complex Recycler Ring Run II Status and Prospects - Spalding

  5. Basis for the Plan: What drives the luminosity • Peak Luminosity • Luminosity lifetime (tunes, beam-beam interactions) • Reliable Operation ep,epbar,form factor F, b* provide some gains But major improvements from bunch intensities • especially total number of pbars BNpbar, (B=36 bunches for Run II) • proton brightness (Np/ep) is constrained by beam-beam tune shift Run II Status and Prospects - Spalding

  6. Major Elements of the Run II Campaign Run II Status and Prospects - Spalding

  7. Operational improvements and upgrade projects Near Term (and ongoing) • Improved reliability and operating efficiency • Failure modes, abort system improvements… • Tevatron alignment • Improved instrumentation throughout the complex • Optimization of transfers, improved optics and helices in Tevatron Upgrade Projects • Increase pbar production • Slip stacking • Pbar acceptance upgrade • Stacking rate and stack size (stacktail, Recycler, e-cooling) • Upgrade Tevatron for higher bunch intensities • Helix • TEL: active beam-beam compensation Run II Status and Prospects - Spalding

  8. Reliability • The number of store hours per week is up 27% from FY03 - the TEV is a more reliable machine. • Typical store length 15 hrs last year  >24 hrs now • Due to: • Alignment of the TEV • Dipole un-rolls, Low Beta alignment, Smart bolt retrofit • Reliability strategy • Aggressively pursue equipment failures • Individual components and Systems (e.g. TEV abort system) • Operations strategy • With improved reliability  run long stores • More time to ensure large stack size • Minimize the effects of store turnaround time • Minimize impact of parasitic studies • Short focused dedicated studies • Configuration control Run II Status and Prospects - Spalding

  9. Upgrade Projects Dynamic plan – adjust the strategy when new information from operations and project R&D Major Elements • Increase number of protons on the pbar production target • Slip stacking (5E12  >8E12 protons on pbar target) • Upgrade the target itself to handle higher intensity • Increase antiproton collection • Increase the gradient of the antiproton collection lens • Increase the aperture of the antiproton collection transfer line (AP2) and the Debuncher ring. • Increase the antiproton stacking and storing capabilities • Increase the flux capability of the Accumulator stacktail stochastic cooling system. • Use the Recycler as a second antiproton storage ring, with both stochastic and electron cooling • Upgrade Tevatron to handle higher intensity bunches. • Improvements to helix separation and smoothness • Active compensation for beam-beam tune shift using the TEL Run II Status and Prospects - Spalding

  10. Status of Operations Run I Run II Status and Prospects - Spalding

  11. Status: Integrated Luminosity Compare the last 12 months to the year before Up 55% with 14% fewer scheduled running weeks Average integrated luminosity per week is up 80% Run II Status and Prospects - Spalding

  12. Status: Peak Luminosity Current best = 7.6E31 cm-2s-1 * Run II Status and Prospects - Spalding

  13. Summary of Current Operations • Booster running at record intensities • Major improvements in transfer efficiencies and emittances, TEV tunes, optics and helix • Improved reliability and operations allows longer stores  larger stacks  higher luminosity • However, stacking rate is ~75% of current goal – present focus of investigation and improvement for the stacktail and core cooling systems • Near term: introduce mixed-source operation (pbars loaded from both Accumulator and Recycler) – first [pilot] store 6/9/04 successful (6.7E31) • And slip-stacking by end of 04 ( already tested at 75% of design intensity) – awaits completion of RF upgrade Run II Status and Prospects - Spalding

  14. Status of the Upgrade Projects Run II Status and Prospects - Spalding

  15. Main Injector • Slip Stacking (goal x1.8ppp on pbar tgt) • Excellent progress • Tested @ 6 x 1012 and 1.5 nsec bunch length on pbar target • Reliable operation >8 x 1012 requires RF upgrade (beam-loading compensation) • On track for end of this year. Run II Status and Prospects - Spalding

  16. Pbar Source Pbar Acceptance (goal: x2) • Lithium Lens (goal x 1.1) • Prototype of new design (higher field gradient) bench test successful • AP2 and Debuncher aperture increase (goal x1.8) • Developed procedures for beam-based identification of limiting apertures, identified components to modify Stacktail cooling upgrade • Cooling system upgrade (extends the bandwith 2-4 2-6 GHz) • Requires the large stack to be in Recycler (with e-cool), and “rapid transfers” • Not [easily] reversible emphasize a phased approach • Interim upgrade (05) [NEW] • Reconfigure existing cooling tanks -quick and reversible • Simulated performance ~30E10 per hr • Full upgrade, with new cooling tanks (06) • Simulated performance ~40E10 per hr Run II Status and Prospects - Spalding

  17. Recycler • The Recycler has made excellent progress over the past year • Transverse emittance growth is no longer an issue (vacuum problems solved) • Met the performance specs needed for commissioning electron cooling • Ready to be integrated into operations (with stochastic cooling)  Provides possibility for interim operating phase [NEW] • Extract pbars from both Accumulator and Recycler: “mixed-source” • e.g. 24 bunches from the Accumulator + 12 bunches from the Recycler • A few (2-4) interim transfers from Accumulator to Recycler • Improves average stacking rate in the Accumulator • Reasons • Push Recycler commissioning progress by plunging it into operations • Potential luminosity enhancement – more pbars for smaller emittances • Break-even right now, potential for up to 20% gain in the next year • Flexibility in the Run II Upgrade schedule • Merge more naturally into commissioning electron cooling Run II Status and Prospects - Spalding

  18. Electron Cooling • R&D program on e-beam is complete, now moving the setup to the Recycler • R&D scheduled stretched by ~2 months  NOT BAD! • Operational test of the full system successful • All major components, diagnostics and controls developed and tested • Beam properties achieved close to spec (analysis ongoing) • Will add additional Pelletron section at Recycler  reliable operation at 4.3 MeV • Commission e-beam and then pbar cooling in Recycler, parasitic to HEP, then intro e-cooled stacks to HEP (05) • Still R&D (until pbar cooling demonstrated next year), but excellent progress Run II Status and Prospects - Spalding

  19. Tevatron Major improvements so far • Lifetime at 150 GeV • Larger aperture, alignment and dipole un-rolls • Emittance dilution reduced • De-coupling at TEV injection, optimization of injection optics • Helix improvements • CDF IP • Centered beam in low beta quads (4mm move at CDF), and re-aligned the quadrupoles • New Low Beta Optics • 20% increase in luminosity Upgrades • Further alignment improvements in shutdown 04 (and 05) • Add separators and polarity switches in shutdown 04 and 05  improved helices Run II Status and Prospects - Spalding

  20. Luminosity Projections Run II Status and Prospects - Spalding

  21. Luminosity Projection • Luminosity model incorporates • Performance parameters from simulation, parametric model and data • Long term operating experience • Sustained average store length was 15 hrs (now >24) • Sustained average 85 store hrs/week (operating weeks often >>100) • Scheduled shutdowns + turn on & recovery + learning slopes • Expect to do better on some parameters, worse on others • What’s new • The following plots are from Feb04 DOE review • Illustrate strategy • Updated projection will be similar in scale • We are in the process of updating the projections for: • e-cooling and stacktail schedules and strategy • Improved reliability (longer stores and stacking) • Mixed-source op - assume break even (conservative) Run II Status and Prospects - Spalding

  22. Design and Base Projections (Feb04 DOE Review) Integrated Luminosity • Design Projection • - No schedule contingency, maintains eng. design margin per subproject • Base Projection • - Assumes schedule slip for all subprojects and that all subprojects under perform Run II Status and Prospects - Spalding

  23. Design and Base Projections (Feb04 DOE Review) Integrated Luminosity per Week We are here Run II Status and Prospects - Spalding

  24. Risk Analysis / Strategy (Feb04 DOE Review) Our plan is to deliver the Design Projection but develop strategy for fallback scenarios: • Base Projection models schedule slip and under-performance for all upgrades • Can also ask: where would we be • without Recycler & e-cooling? • with e-cooling, but without stacktail upgrade? Run II Status and Prospects - Spalding

  25. Design Projection Electron Cooling Stacktail Upgrade Parameters in FY09 Debuncher & AP2 at 32p-mm-mrad Slip Stacking at 8x1012 ppp Av. Stk Rate = 39x1010/hr Stk in Accum = 20x1010 Stk in Rec’r = 570x1010 Base Projection As above with sched & param slip Parameters in FY09 Debuncher & AP2 at 25p Slip Stacking at 7x1012 ppp Av. Stk Rate = 24x1010/hr Stk in Accum = 24x1010 Stk in Rec’r = 360x1010 Risk Analysis / Strategy (Feb04 DOE Review) • BlackProjection • NO Electron Cooling • NO Stacktail Upgrade • Parameters in FY09 • Debuncher & AP2 at 21p • Slip Stacking at 7x1012 • Av. Stk Rate = 14x1010/hr • Stk in Accum = 205x1010 • Stk in Rec’r = 0x1010 • Purple Projection • Electron Cooling • NO Stacktail Upgrade • Parameters in FY09 • Debuncher & AP2 at 20p • Slip Stacking at 8x1012 • Av. Stk Rate = 23x1010/hr • Stk in Acum = 58x1010 • Stk in Rec’r = 337x1010 Run II Status and Prospects - Spalding

  26. Risk Analysis / Strategy (Feb04 DOE Review) with e-cooling, but w/o stacktail upgd without e-cooling & stacktail upgd Branch points from Design Projection Design Purple Black Assumes average store length 15 hrs Run II Status and Prospects - Spalding

  27. 50 40 30 Integrated Luminosity per Week (pb-1) 20 10 0 9/29/03 9/29/04 9/30/05 10/1/06 10/2/07 10/2/08 10/3/09 Start of Fiscal Year Strategy Changes WARNING: curves not yet updated changes in green to be implemented Design e-cooling and interim stacktail upgrade will be delayed to fall 2005, full upgrade in 06 interim Stacktail upgrade Purple Black mixed-source operation longer stores Run II Status and Prospects - Spalding

  28. Risk Analysis / Strategy (Feb04 DOE Review) Design Purple Black Base Run II Status and Prospects - Spalding

  29. Summary • Current performance is above the design projection • 80% higher weekly luminosity than a year ago • Major achievements in the last year (Tevatron perf, Recycler…) • There is a complex-wide plan for the Run II campaign • Plan is dynamic: schedule/scope adjustments, mixed-source, capitalize on improved reliability • The upgrade projects are making good technical progress • The plan and progress are formally reviewed by DOE • With the updated plan, expect the design projection to be close to the previous 8.5 fb-1 2009, with fall-back scenarios >4.5 fb-1 Run II Status and Prospects - Spalding

More Related