1 / 26

PS 200 MHz RF Matrix and Control Application

PS 200 MHz RF Matrix and Control Application. as seen from the hardware side. H. Damerau Acknowledgments: A. Butterworth, D. Cotte, S. Hancock, C.-H. Sicard. 50. AB/OP Shutdown Courses 200 9. 16 March 2009.

taya
Download Presentation

PS 200 MHz RF Matrix and Control Application

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PS 200 MHz RF Matrix and Control Application as seen from the hardware side H. Damerau Acknowledgments: A. Butterworth, D. Cotte, S. Hancock, C.-H. Sicard 50 AB/OP Shutdown Courses 2009 16 March 2009

  2. The new application program • 2nd part by Denis Outline • Introduction • The 200 MHz RF system in the PS • Longitudinal blow-up • Control of the hardware of the 200 MHz system • Concept of re-start timings • Voltage program generation • The new application program • 2nd part by Denis • Summary

  3. Please interrupt for questions!

  4. 200 MHz RF system • The PS is equipped with six 200 MHz cavities • Originally foreseen for bunch-to-bucket transfer with the SPS, but never operational (~1978, instabilities) • Since 2006 run: number of cavities reduced from 8 to 6 • Therefore now used for - Longitudinal emittance control (a.k.a. blow-up) - 200 MHz rebunching before transfer of fixed target beam (SFTPRO/CNGS) • Cavities: - Short pill-box resonator - Reduced Q with strongly coupled load - 3 PIN diode switches/cavity to reduce residual impedance when not in use • PRF  25 kW/cavity → ~ 25 kV • C202/C203 equipped with fast loudspeaker-tuner

  5. 200 MHz RF system PS CB (353): generation of 200 MHz RF signals and voltage programs 6 × Vgap for voltage control North hall (151): amplification to 6 × 25 kW Tunnel (SS06): cavities • ~ 25 Racks of electronics

  6. Outline • Introduction • The 200 MHz RF system in the PS • Longitudinal blow-up • Control of the hardware of the 200 MHz system • Concept of re-start timings • Voltage program generation • The new application program • 2nd part by Denis • Summary

  7. Beam Cavity Longitudinal blow-up (beam for AD) 1. Low energy blow-up, h = 458 2. High energy blow-up, h = 420 gtr 0.94 eVs 1.3 eVs • 200 MHz system is operated in pulsed mode at various times during the cycle (all high-intensity beams) • Emittance blow-up is achieved by phase modulation

  8. fmod = 14 kHz, fmod = 180° (RMS) How does the blow-up work? • Modulate the phase of the 200 MHz voltage to shake the particle distribution • Modulation frequency must be well above synchrotron frequency to avoid resonant excitation AD Injection

  9. Modulation parameters Df = 3.141 rad fmod= 1 – 12 kHz VRF= 1 - 30 kV Harmonic number hb = 458, 433, 420 • Low energy: 458th beam harmonic steered to cavity resonance Need to lock the 200 MHz signal to frev • AD cycle with blow-up during first 20 ms after injection • Intensity: ~ 1.35 · 1013 ppp → 3.4 · 1012 ppb Set-up for operational blow-ups with 200 MHz Beam Cavity 199.95 MHz

  10. frev V ~ fRF High energy blow-up f Df 1 frev (digital) for h calculation hvar Injection f ~ 200 MHz AD fRF • Harmonic number changes automatically (h = 458 → 419) • The cavities can only be active at a fixed harmonic number! • One RF signal distributed to all six cavities RF signal for the 200 MHz RF system fRF Frequency multiplier fRF = h· frev 199.948 MHz

  11. Vgap 199.948 MHz fRF Reflected power • Blow-up during acceleration (e.g. HE blow-up of LHC beams only works in small time windows • Frequency used for blow-up sweeps through cavity resonance High energy blow-up on the fly (LHC) Blow-up cannot be applied anywhere in the cycle! • Need frequency window with constant harmonic number • Need h · frev sufficiently close to 199.948 MHz

  12. Outline • Introduction • The 200 MHz RF system in the PS • Longitudinal blow-up • Control of the hardware of the 200 MHz system • Concept of re-start timings • Voltage program generation • The new application program • 2nd part by Denis • Summary

  13. Control of the 200 MHz RF system Well known part… • Controls structure has been renovated to run the system without the ancient matrix hardware • How to control the hardware behind?

  14. How to control the hardware? • Each cavity needs: • An RF signal at ~ 200 MHz (including the modulation) • Voltage program • Timing signals to release PIN diodes • Timing signals to start and stop the voltage control loop (AVC) • < 2009: 200 MHz matrix in hardware • Built in 1984 • Sophisticated logics inside • Special chassis with custom made cards • Few spare components J. Evans, PS/RF/Note 84-5

  15. The old 200 MHz matrix hardware C201 Blow-up 1 … … MATRIX Control System Re-bunching 1 C206 • The control system generates per blow-up/re-bunching: • One voltage function • Three timings: warning, start, stop • The matrix converts these signals to the corresponding timings and voltage programs per cavity • Diagnostics: voltage program and detected per cavity on OASIS

  16. Remove matrix C201 … Control System C206 • Control system generates functions and timings directly per cavity • Old hardware matrix not needed anymore • How can a matrix like structure be implemented? • Which control structure reflects hardware structure?

  17. New controls structure: Timing trees • Construct a virtual matrix in rows • All the timing information of one row contained in an LKTIM timing tree • Timing trees per blow-up and re-bunching • The LKTIM trees contain start timings for each cavity • The new application program enables/disables timings

  18. New structure: Single voltage program • Due to the hardware structure of the 200 MHz system a single RF signal at a time is distributed to all cavities • All cavities always do the same function (blow-up/re-bunching) • Blow-ups or re-bunchings must never overlap • There is no use in sending different voltage programs to different cavities • A single voltage program (GSV200 like GSV10GLOBAL) function for all cavities is adequate Test signal RF signal to all cavities RF from SPS Modulated RF for blow-up

  19. Combine: Internal Stops • Combine timing trees and global voltage program function to coherent structure: • Global voltage program with internal stops • Sequence of voltage programs for blow-ups and re-bunchings in time order • Two sections per blow-up/re-bunching: Rising and falling edge of Vprog • Sequence voltage program excludes overlapping • Hardware wired structure (one RF for all) well reflected

  20. Closer look on a timing tree • Example: timing tree for blow-up 1 Information of a matrix row stored in timings To be handled by matrix application • New timing tree structure not very different from existing

  21. Interlock and diagnostics • Level2 interlock inputs of the old hardware matrix: • Disables all signals to a cavity, if not fully in ON state (level2) • The AVC loop modules are modified with an additional enable • Analogue signals to OASIS are derived from the voltage program per cavity at the output of the old matrix • A voltage program signal per cavity is important for a direct correspondence to the detected voltage • The AVC loop modules are modified with an additional switched voltage program output (simple)  OASIS signals Direct correspondence of program and detected signals remains

  22. Outline • Introduction • The 200 MHz RF system in the PS • Longitudinal blow-up • Control of the hardware of the 200 MHz system • Concept of re-start timings • Voltage program generation • The new application program • 2nd part by Denis • Summary

  23. New application software 2nd part by Denis

  24. • Newcontrol structure close to the structure of the hardware of the 200 MHz system • Direct correspondence of analogue signals Vprog and Vdet • New matrix has been operated at the end of last year’s run Summary • The 200 MHz RF system is essential for all high-intensity beams in the PS • Longitudinal blow-up is achieved by a phase modulated RF signal at a high harmonic (h = 420 – 458) • New control structure replaces ancient hardware: • Timing trees to handle matrix rows of cavity selections • Total voltage function with internal stops for all cavities together

  25. Thank you for your attention!

More Related