Cdma network wireless telephone directorate
Download
1 / 16

CDMA Network Wireless Telephone Directorate - PowerPoint PPT Presentation


  • 122 Views
  • Uploaded on

CDMA Network Wireless Telephone Directorate. Presented by: Chetan Ratna Kansakar Manager, DWT. Content. Objective & Plan Current Status Progress and Capacity Service Future Plan Problems encountered Conclusion. Objective & Plan.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' CDMA Network Wireless Telephone Directorate' - tavon


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Cdma network wireless telephone directorate

CDMA NetworkWireless Telephone Directorate

Presented by:

Chetan Ratna Kansakar

Manager, DWT


Content

  • Objective & Plan

  • Current Status

    • Progress and Capacity

    • Service

  • Future Plan

  • Problems encountered

  • Conclusion


Objective plan
Objective & Plan

  • The CDMA Project objective was to facilitate telecommunication services in 75 District Head Quarters and 3,915 VDCs of Nepal.

  • To meet the above objective, NT Procured the CDMA system with following capacity in Five Phases under contract with ZTE which was signed on 18th October 2004:

    • MSC- one million lines

    • BSC- one million lines

    • BTS- Around 450K lines

  • Install 100 CDMA BTS each year.

  • To facilitate Trunk requirement of Nepal Telecom.

    • NG SDH East-West optical link with bandwidth of STM-64.

    • Various Microwave spur link. (100 stations)

    • Alcatel Valley SDH link.(4 sites)


Current status
Current Status

  • Progress and Capacity

  • Service status



CDMA Network

  • Soft launch of CDMA-2062, Asar

  • System put into commercial use- 2062, Magh 23

  • Installed capacity to date

    • MSC-1 million lines

    • BSC-1 million lines

    • BTS-399K lines (Installed BTS-258)

  • Capacity to be installed

    • BTS-151K lines

    • BTS-100K Lines Upgradation (additional Purchase)

Note:- Five phases frame contract has been merged in three Phases


Transmission
Transmission

  • NG SDH

    • STM-64 Tx. Equipments installed in 16 sites along East-West high-way, 5 STM-64 equipment will be installed in up coming month of fiscal year 2064/65.

  • Valley SDH

    • STM-4 and STM-1 Tx. equipment installed in 4 sites

  • Microwave Radio

    • Microwave radio installed in 42 stations





  • Service status
    Service status

    • CDMA line distribution

      • Fixed telephone Post paid 43,427

      • Fixed telephone Prepaid 116,730

      • Sky phone 198,227

      • Sky Data 1103

      • Total Data user 19,120

    • CDMA Coverage

      • Zone-14

      • District-71

      • Municipality-58

      • VDC-2120

        Note:- Humla, Mugu, Dolpa and Manag yet to be connected


    Future plan
    Future plan

    • After completion of revised phase IV CDMA network will have one million lines capacity in MSC and BSC whereas the BTS capacity Will be only 550K lines.

      • L/C has already been open for procurement of additional BTS equipment to upgrade 53 1C3S BTS to 2C3S and 41 1C1O BTS to 2C1O which will add 100K lines to BTS capacity.

      • The BTS capacity will be 650K lines after up-gradation. Remaining 350K Lines BTS capacity to be procured for ultimate capacity of One Million Lines which will cover around 3360 VDCs (out of 3915 VDCs) in all 75 Districts. Negotiation is under way to procure additional 190 BTS and 220 BTS upgradation equipment.


    Future plan cont
    Future Plan cont.

    • Additional 2 million line with around 400 BTS are required for carpet coverage through out the country and to cater the demand.

    • By the end of fiscal year 2064/65 150K lines fixed and 200K RUIMs shall be distributed throughout the Kingdom. For the next five year, DWT has planned to distribute 500K lines each year.

    • By the end of fiscal year 2064/65 DWT has planned to cover all 75 districts and cover around 2500 distinct VDCs throughout the country.


    Problems encountered
    Problems encountered

    • Outrageous situation

      • Transportation of Equipment

      • Movement of technical manpower

    • Preparing Infrastructure

      • Acquiring Land

      • Building

      • 3 phase electricity supply

      • Tower

    • Migration of Subscribers


    Conclusion
    Conclusion

    • Expansion of CDMA networks specially in rural sector of the country to cater the growing demand of telephones.

    • Establishment of East West High bandwidth (STM-64) optical transmission link.