NEPOOL Participant’s Meeting
This presentation is the property of its rightful owner.
Sponsored Links
1 / 43

NEPOOL Participant’s Meeting Boston, MA May 7, 2004 PowerPoint PPT Presentation


  • 76 Views
  • Uploaded on
  • Presentation posted in: General

NEPOOL Participant’s Meeting Boston, MA May 7, 2004. Stephen G. Whitley Senior Vice President & COO. Agenda. System Operations Market Operations Day-ahead Market – April 19, 2004 Electric and Gas Wholesale Initiative Summer Capacity Back-Up Detail. System Operations.

Download Presentation

NEPOOL Participant’s Meeting Boston, MA May 7, 2004

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Nepool participant s meeting boston ma may 7 2004

NEPOOL Participant’s Meeting

Boston, MA

May 7, 2004

Stephen G. Whitley

Senior Vice President & COO


Nepool participant s meeting boston ma may 7 2004

Agenda

  • System Operations

  • Market Operations

  • Day-ahead Market – April 19, 2004

  • Electric and Gas Wholesale Initiative

  • Summer Capacity

  • Back-Up Detail


Nepool participant s meeting boston ma may 7 2004

System Operations


Operations highlights

Operations Highlights

  • Boston & Hartford Weather Pattern:

    • April 2004 had normal to above normal temperatures. The precipitation was near record highs. Most areas doubled the amount of normal precipitation.

  • Peak load of 17,884 MW at 20:00 hours on April 1, 2004.

  • During April:

    • NPCC Shared Activation of Reserve Events:

      • April 6L/O Bruce [email protected] MW

      • April 11L/O Mystic [email protected] MW


Nepool participant s meeting boston ma may 7 2004

Market Operations


Day ahead real time prices iso hub

Day–Ahead & Real-Time Prices, ISO Hub:


Day ahead lmp average by zone hub

Day-Ahead–LMP Average by Zone & Hub:

April 1, 2004 to April 23, 2004

(1.27)

(0.52)

(-1.30)

(0.15)

(-2.61)

(-2.88)

(-1.86)

(-9.84)

NOTE: Corrected Day-Ahead LMPs for April 19 have been used.


Real time lmp average by zone hub

Real-Time-LMP Average by Zone & Hub:

April 1, 2004 to April 23, 2004

97.4%

(0.80)

(-2.00)

(0.08)

(-1.12)

(0.13)

(-1.63)

(-2.80)

(-6.66)

(0.60)

(0.88)

(0.10)

(-1.20)

(-2.41)

(-2.93)

(-1.95)

(-7.88)


Nepool participant s meeting boston ma may 7 2004

Day - Ahead Market vs. Forecast Load


Nepool participant s meeting boston ma may 7 2004

Day - Ahead LMP


Real time lmp

Real - Time LMP


Settlement data real time balancing market

Settlement Data – Real - Time & Balancing Market

Percentage of Real-Time Load Fully Hedged Through ISO-NE

Settlement System*


Nepool participant s meeting boston ma may 7 2004

Day-ahead Market – April 19, 2004


Summary of event

Summary of Event

  • The Day-Ahead (DA) Energy Market for Monday, April 19 incorrectly modeled two transmission outages in the VT/NH area leading to incorrect results affecting NH, VT and West Central MA.

  • The DA Market team detected unusual results and delayed the closing to investigate:

    • DA Market and System Operations outage scheduling personnel did not detect the problem in the allotted timeframe.

  • Data Problems were identified the following day:

    • Database included two specific outages modeled to occur

    • simultaneously due to delay in completing one of them: and,

    • Incorrect breaker numbers for scheduled outage at a substation.


Timeline of actions to correct errors

Timeline of Actions to Correct Errors

Advised Market Participants of ProblemApril 19 & 21

Advised State and Federal RegulatorsApril 20 & 21

Met with NEPOOL Markets CommitteeApril 22

Notice of Intent to Correct the ResultsApril 27

and Rule Changes Proposed

Teleconference Seeking Input toApril 29

Proposed Rule Changes

Filed an Explanation of Problem andApril 30

Proposed Rule Changes with FERC

Published Corrected ResultsMay 3


Summary of recommendations

Summary of Recommendations

  • Modify internal and external business processes to improve outage scheduler program.

  • Add on-site management/senior engineer coverage for the weekend.

  • Modify protocols to ensure more timely internal and external communications of potential problems.


Nepool participant s meeting boston ma may 7 2004

Electric and Gas Wholesale Initiative


Electric and gas wholesale initiative

Electric and Gas Wholesale Initiative

  • Timeline

    • Define problem & key issues- Complete

    • Publish Interim ISO-NE Cold Snap Report- May 7

    • Prioritize issues & brainstorm solution sets- May

    • Present range of solutions w/stakeholders- June

    • Finalize set of recommendations- June

    • 30 day public comment period- July

    • Publish final ISO-NE Cold Snap Report- August

    • FERC Filings- August

    • Implement changes- Fall 2004


Nepool participant s meeting boston ma may 7 2004

Summer Capacity


Summer 2004 capacity assessment

Summer 2004 Capacity Assessment


Summer 2004 capacity assessment1

Summer 2004 Capacity Assessment


Summer 2004 capacity assessment2

Summer 2004 Capacity Assessment


Summer 2004 capacity assessment3

Summer 2004 Capacity Assessment


Summer 2004 capacity assessment4

Summer 2004 Capacity Assessment


Summer 2004 capacity assessment5

Summer 2004 Capacity Assessment


Back up detail

Back-Up Detail


Nepool participant s meeting boston ma may 7 2004

CT/SWCT


Swct transmission

SWCT Transmission

  • Phase I

    • Received conditional approval from Connecticut Siting Council 2/11/04

  • Phase II

    • Town hearings completed

    • “Need” hearings completed

    • “Overhead” segments and “East Shore” – May

    • “Underground Technology” segments – June


Nepool participant s meeting boston ma may 7 2004

Demand Response


Demand response as of april 30 2004

Demand Response(as of April 30, 2004)


Demand response as of april 30 20041

Demand Response(as of April 30, 2004)

* SWCT assets are included in CT values and are not included in Total


Nepool participant s meeting boston ma may 7 2004

Northwest Vermont


Nwvt reliability project update

NWVT Reliability Project Update

  • State hearing process continues

    • Technical Hearings complete

    • Discovery on 115kV line relocations underway, hearings by mid-June

    • Rebuttal phase delayed until end of July

    • Decision expected by mid October


Nepool participant s meeting boston ma may 7 2004

New Generation


New generation update

New Generation Update


Nepool participant s meeting boston ma may 7 2004

RTEP


Rtep update

RTEP Update

  • TEAC21 held on Thursday, May 6, at the Sheraton Hotel in Springfield, MA

  • Discussion Topics

    • Load Response Program 2004

    • Load Response Penetration Study

    • SWCT RFP Results

    • Resource Adequacy Results

    • Interregional Planning Update

    • Economic Assessment

      • Review methodology

      • Results

  • TEAC22 tentatively scheduled for June 2

  • TEAC23 tentatively scheduled for June 25


Rtep projects update nema

RTEP Projects Update - NEMA


Rtep projects update swct

RTEP Projects Update - SWCT


Nepool participant s meeting boston ma may 7 2004

Compliance


Compliance update

Compliance Update

  • A4: Maintenance for Bulk Power System Protection

    • Required response to 2004 ISO-NE survey by 1/5/04

    • Level 2 sanctions will apply to 3 Participants for failure to respond on time.

    • 4 Participants that have not completed their 2003 required maintenance must become compliant by May 31, 2004.


Compliance update cont

Compliance Update (cont.)

  • A3: Generator Underfrequency Tripping

    • All Participants responded to the 2003 ISO-NE Survey by 12/1/03

      • 6 Participants are non-compliant

        • 2 are exempt

        • 2 have plans for compliance

        • 2 will require that ISO-NE enforce compliance

    • 2004 Surveys on UFLS and UF generator trip settings were sent out on March 15 and are due May 10, which includes a 10-day grace period.

      • Failure to comply will result in sanctions


Sanctions

Sanctions

  • Level 1 – Letter from Director SP to the relevant functional head (operations, planning) of the Industry Participant with copy to NCWG

  • Level 2 – Letter from COO to the Chief Executive of the Industry Participant with copy to the relevant functional head, other NEPOOL Participants (the NEPOOL Task Forces, RC, NPC) and NPCC

  • Level 3 – Letter from the CEO to the Board of Directors of the Industry Participant with copies to Level recipients. Post on the ISO-NE Compliance Website.

  • Level 4 – same as Level 3 with copies to the appropriate State/Provincial regulatory agencies, FERC, DOE, State Governor and Legislators.


  • Login