Flood fighting and planning us army corps of engineers omaha district l.jpg
This presentation is the property of its rightful owner.
Sponsored Links
1 / 25

Flood Fighting and Planning US Army Corps of Engineers Omaha District PowerPoint PPT Presentation


  • 108 Views
  • Uploaded on
  • Presentation posted in: General

Flood Fighting and Planning US Army Corps of Engineers Omaha District . Joel Ames Tribal Liaison.

Download Presentation

Flood Fighting and Planning US Army Corps of Engineers Omaha District

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Flood fighting and planning us army corps of engineers omaha district l.jpg

Flood Fighting and PlanningUS Army Corps of Engineers Omaha District

Joel Ames

Tribal Liaison


Slide2 l.jpg

Our Mission: Emergency Management provides engineering services to respond to national and natural disasters to minimize damages and help in recovery efforts. Public Law 84-99 enables the Corps to assist Tribes, state, and local authorities in flood fight activities and cost share in the repair of flood protection structures. Public Law 93-288 authorizes the Federal Emergency Management Agency (FEMA) to task the Corps with disaster recovery missions under the Federal Response Framework.

POC: Omaha District Readiness Branch24/7 Number: 402-995-2448


Slide3 l.jpg

2010 Flooding – the normal


Slide4 l.jpg

The new fight


Slide11 l.jpg

Safety Training


Lessons learned l.jpg

Lessons Learned

  • Tribes did not know how/when to contact the Corps

  • Tribes were unaware of the Corps capabilities to assist and assets we can bring to the table

  • Tribes did not understand the limits of authority under PL-84-99


2011 initial actions l.jpg

2011 Initial actions

  • Letters and informational packages sent to each Tribal Leader and Emergency Planner (Jan)

  • Follow-up Calls to each Tribe (Jan)

  • Begin site visits (7-11 Feb)

  • Pine Ridge Flood Response 15 – 19 Feb

  • Tech Assist Ponca Tribe 17 Feb

  • MoRAST Briefing (8 Mar)

  • Additional Tribal visits (13-19 Mar)


Slide14 l.jpg

Road Trip

Road Trip

Road Trip

Road Tri[p

Tribal visit

Flood Fight

State EOC Visit and exercise

State EOC visit

Tribal Visit

Road Trip

State EOC Visit

Tribal Visit

Road Trip

Tech Assist

Tribal Visit

Flood Fight

Tech Assist

Road Trip

State EOC visit


Current situation l.jpg

Current Situation

  • Standing Rock – Waters Receded

  • Pine Ridge - Waters Receded

  • Flandreau – Monitoring Big Sioux

  • Ft Belknap - Ring Levee Constructed, Monitoring

  • Blackfeet Nation – Monitoring

  • Ft Peck – Monitoring

  • Yankton Sioux - Monitoring


Slide17 l.jpg

PURPOSE: This fact sheet explains in general the assistance that can be provided from the U.S.

Army Corps of Engineers (USACE) under Public Law 84-99(PL 84-99) and the correct process

that must be followed to request Federal Assistance.

BACKGROUND: USACE emergency assistance under PL 84-99 during flood events will be of a temporary nature to meet the immediate threat and will be undertaken only to supplement State and Local efforts. State, tribal, and local interests must commit all available resources, i.e. work force, supplies, equipment, funds, National Guard assets, etc., as a general condition of USACE assistance. USACE emergency efforts are not intended to provide permanent solutions to flood problems and are provided strictly for the protection of public facilities and infrastructure. In order to best serve our stakeholders, and by law of PL 84-99, requests for assistance to USACE may be received from the State Emergency Management Agency or tribes only. In the past, several communities have come directly to USACE for assistance; In these instances, USACE will be directing those communities to follow the process, outlined below, to request resources. The proper procedure is to request assistance through the local, county, and then State emergency management offices. The tribes may come directly to USACE. The request must include a detailed assessment of the resources committed, the current actions of the locals/County/State,

what type of assistance is requested, point of contact and specific details on exactly what the community is looking for in assistance.


Slide18 l.jpg

PL 84-99 ADVANCED MEASURES – TECHNICAL ASSISTANCE (Class 520):

Overview: USACE is authorized to provide supplemental technical assistance prior to the event for Communities threatened with imminent flooding potential. Assistance is provided to protect life and protection of public facilities/infrastructure. Assistance requires HQUSACE approval.

-State Emergency Management Agency/Tribal letter requesting assistance

required

-Evaluate flood threat to area

-Supplement data collection efforts

-Inspect existing Flood Control Works and identify problems

-Provide engineering technical services

-Provide information for local contingency/flood fight plans


Slide19 l.jpg

PL 84-99 ADVANCED MEASURES – DIRECT ASSISTANCE (Class 510):

Overview: USACE is authorized to provide supplemental direct assistance prior to the event for Communities threatened with imminent flooding potential. Assistance is provided to protect life and protection of public facilities/infrastructure. Assistance requires HQUSACE approval.

-Governor/Tribal letter requesting assistance required

-State, County, and Local Emergency Declarations have been made.

-Supplemental to State and Local efforts

-Conduct field investigations/data collection

-Provide emergency construction of protective measures i.e. temporary levees

-Project Information Report approved by HQUSACE

-Project economically feasible and constructible before flood

-Imminent threat of unusual flooding – forecasted by National Weather Service

-Benefit-cost ratio greater than 1.0

-Project Cooperation Agreement (PCA) required

-Locals are physically and fiscally responsible for removal of all temporary flood

protection features at the end of the event

-Applicants must furnish all borrow, lands, rights, easements, and right-of-ways


Slide20 l.jpg

-Applicants must make necessary relocations

-Hold harmless the U.S. Federal Government free from damages.

-Applicants must provide traffic control during construction

-Applicants must provide monitoring for levees and pumping operations.


Slide21 l.jpg

PL 84-99 EMERGENCY OPS FLOOD FIGHTING – TECHNICAL ASSISTANCE (Class 210):

Overview: This authority is initiated during a flood event and rivers are either forecasted,

at, or above flood stage. Technical assistance consists of providing review and

recommendations in support of State and Local efforts, and helping determine feasible

solutions to uncommon situations.

-Guidance on flood fight techniques and emergency construction methods from

experienced personnel

-Provide experienced personnel to inspect existing flood protection projects to

identify problem areas and recommend corrective measures

-Provide hydraulic or hydrologic analysis, geotechnical evaluations, and

stream data, maps, and historic flood or storm information.


Slide22 l.jpg

PL 84-99 EMERGENCY OPS FLOOD FIGHTING – DIRECT ASSISTANCE (Class 210):

Overview: This authority is initiated during a flood event, when river are forecasted, at, or

above flood stage as predicted by the National Weather Service.

-Assist or direct flood fight efforts

-Conduct field investigations/data collection

-Provide emergency flood fight supplies

-Initiate emergency contracting for construction of protective measures i.e.

temporary levees

Requirements:

-Supplemental to state/tribal/local government flood fight efforts

-Impacts to urban areas or critical public infrastructure only

-Temporary in nature and directed to the immediate threat

-Request from local/counties must be made to the State Emergency

Management Office for their review and processing

-USACE must receive request from the State/Tribe to provide assistance

-Loaned supplies and equipment(Pumps, sandbags, and Innovative flood

barriers) must be returned in the same condition as it was when lent, replaced in

kind, or reimbursement made to USACE.

-Project economically feasible, reasonable, prudent and constructible before

flood


Slide23 l.jpg

-Project Cooperation Agreement (PCA) required

-Applicants/Locals are physically and fiscally responsible for removal of all

temporary flood protection features at the end of the event

-Applicants must furnish all borrow, lands, rights, easements, and right-of-ways

-Applicants must make necessary relocations

-Hold harmless the U.S. Federal Government free from damages.

-Applicants must provide traffic control during construction

-Applicants must provide monitoring for levees and pumping operations.


Slide24 l.jpg

USACE – Omaha District Flood Update Webpage

http://www.nwo.usace.army.mil/html/op-e/flood.html