An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Photon Systems Update John Arthur SLAC 1

  2. Photon Systems Includes LCLS x-ray and laser groups • X-ray Transport, Optics and Diagnostics (XTOD) • managed by LLNL (Richard Bionta) • X-ray Endstation Systems (XES) • managed by SLAC (Stefan Moeller) • Laser Systems • managed by SLAC (Bill White)

  3. X-Ray Systems Status • FY2006 was a design and replan year • Scope changes were accommodated • XTOD designs have been undergoing reviews • XES designs will start reviews imminently • FY 2007 is a build year • Ready for installation starting November 2007 • Ready for first light in Spring 2008

  4. Recent Events • FAC April 2006 Recommendations • Make x-ray mirror design the top priority • Include a full suite of non-destructive diagnostics • Consider bringing white beam to FEH • Define critical path for commissioning + experiments • LCLS actions • X-ray mirror specs are now in hand, engineering soon • Including robust diagnostics for commissioning and operations • White beam option preserved, not first choice • Commissioning schedule in preparation

  5. XTOD progress • Updated work plan, new ETC • Designs moving through review stage FEE West Wall Gas Detector Gas and Solid Attenuator Cable Trays X-Ray Slit and Fixed Mask First x-ray optics

  6. XTOD progress • Transport design nearly finished • Optics design advanced • Most devices have passed preliminary design review • Mirrors about to have concept review • Diagnostics design underway • At concept review stage

  7. XES progress • Updated work plan, new ETC • 2d x-ray detector development program on schedule, with good reviews so far • Working closely with LCLS Controls Group and LUSI

  8. Preliminary design for AMO experiment layout (showing future LUSI station as well) Laser tables Expt chambers NEH Hutch 2

  9. Efficient Experiment Layout 4 XPCS 5 XCI 6 HED Beam can be switched without moving experiments

  10. BCR changes in FY2006 • XES • Delete some detectors and computers (Feb) • Add K-measurement (May) • Delete streak camera (June) • Revise AMO (June) • Delete laser amp and K-measurement (Aug) • Net: Decrease of ~$1500k, nearly all TEC • XTOD • Revise plan (Oct) • Delete flipper mirrors and side beamlines, revise plan (Jan) • Replan, add K-measurement (Aug) • Net: Decrease of ~$1800k TEC, increase of ~$900k OPC

  11. Summary • X-ray groups in design phase; going well • Net scope reduction has been accommodated • Project scope and beamline design have crystallized • Working hard on critical instrumentation