TRD Electronics Flight Production

Loading in 2 Seconds...

play fullscreen
1 / 16

TRD Electronics Flight Production - PowerPoint PPT Presentation


  • 218 Views
  • Uploaded on

TRD Electronics Flight Production. Wim de Boer , Kai Gassmann, Florian Hauler, Andreas Sabellek , Mike Schmanau IEKP - Universität Karlsruhe (TH). Outline. TRD Electronics Overview Status of FM/FS TRD Electronics production at CSIST Results of Board-level acceptance testing Dec 06

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' TRD Electronics Flight Production' - tamah


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
trd electronics flight production

TRD ElectronicsFlight Production

Wim de Boer, Kai Gassmann, Florian Hauler, Andreas Sabellek, Mike Schmanau

IEKP - Universität Karlsruhe (TH)

outline
Outline
  • TRD Electronics Overview
  • Status of FM/FS TRD Electronics production at CSIST
  • Results of Board-level acceptance testing Dec 06
  • Report on replacement procedure of Actel FPGAs
  • Updated Time Schedule for FM U-Crates assembly and testing

TIM Jan07, JSC

trd u electronics overview
TRD(U)-Electronics Overview

V2

V2

UPSFE = TRD power supply for front end

UDR = TRD data reduction board

JINF = data concentrator and link to higher DAQ

UHVG = TRD high voltage generator

UFE = TRD front end

UTE = TRD tube end

UHVD = TRD high voltage distributor

U = Uebergangsstrahlung

UCrate = TRD electronics crate

UBP = TRD backplane

UPD = TRD power distribution box

TIM Jan07, JSC

qm2 upd and u crate
QM2 UPD and U-Crate
  • One set of fully qualified QM2 TRD Electronics Crates (two set of FM Crates needed for complete TRD readout)

Slow control connection to U-Crate

Power supply connectors for U-Crate and 28V

6 UHVG

JINF

3 UPSFE

6 UDR2

TIM Jan07, JSC

status of fm fs production at csist taiwan
Status of FM/FS Production at CSIST, Taiwan
  • DCDC Converter (S9056,S9048,S9053): FM/FS board production and test completed (May.06, presented on TIM Jul.06)
  • S9011AU Controller: FM/FS board production and acceptance test completed (Dec.06)
  • UBP: FM/FS production finished; Board assembly ongoing
  • UDR2: FM/FS board production and acceptance test completed (Sep/Dec.06, presented on TIM Oct.06)
  • UPSFE: FM/FS board production and acceptance test completed for 7/9 boards (Dec.06)
  • UHVG: reworked by VK; FM/FS production in progress, PCA delayed by components found out of specification (MIT)
  • JINF: FM/FS production ongoing (MIT)

U Power Distribution (UPD):

U DAQ Electronics (U-Crate):

TIM Jan07, JSC

s9011au controller fm fs test
S9011AU Controller FM/FS Test
  • Number of Boards tested: 4 (2 needed as FM)
  • Testprocedure (before/after Coating and ESS):
  • - Functional test via Lecroy communication
  • Signal and status lines tested with a DCDC converter (“needle” backplane used – no soldering on FM-boards necessary)
  • SSF test
  • Actel FPGAs with new Firmware are used
  • Some resistors mounted wrongly (unsoldered according to latest BOM)
  • 95001F: Short between two status lines on Actel pinout corrected (seen in functional test)

Summary of Test Results:

TIM Jan07, JSC

udr2 daq board fm fs test
UDR2 DAQ Board FM/FS Test
  • Number of Boards tested: 15 (12 needed as FM)
  • Testprocedure (before/after Coating and ESS in Dec.06):
  • - Functional test via AMSWire communication
  • Data acquisition with FM-Front-Ends
  • Current monitoring on Test-backplane
  • SSF test
  • No problems or errors seen

Test-backplane

Dec.06

TIM Jan07, JSC

upsfe fm fs test
UPSFE FM/FS Test
  • Number of Boards tested: 9 (6 needed as FM)
  • Testprocedure (before/after Coating and ESS):
  • - Functional test via Lecroy communication
  • Linear Regulator test (28 circuits/board) on a Fusetest-backplane
  • Signal and status lines tested
  • Current monitoring
  • SSF test
  • Actel replacement after Firmware modification done, but mounted pairwise into wrong position (see Report on replacement procedure)
  • Some resistors with wrong values exchanged
  • 95003F: FPGA off-signal failure; Actel problem in off-state, will be exchanged
  • 95005F: one LR SSF failed after ESS; part failure found, will be exchanged

UPSFE

board

14x2 LR test circuits

Fusetest Backplane

Off-signal LEDs

Status

Jumpers

Summary of Test Results:

TIM Jan07, JSC

actel replacement procedure 1 2
Actel Replacement Procedure 1/2

Vacuum

lifter

  • Solution to misplaced Actel FPGAs proposed and done by CSIST: desolder and swap same ICs to correct position
  • Thermal stress during desolder process is lower than in reflow soldering process of regular mounting

Hot air nozzle

Careful inspection necessary!

Bottom fan 100°C

FPGA pads have experienced 5 unavoidable de-/solder processes now

TIM Jan07, JSC

actel replacement procedure 2 2
Actel Replacement Procedure 2/2

Manual soldering

[email protected]°F

+

5sec slide/edge

Flux

TIM Jan07, JSC

fm upd assembly status
FM UPD Assembly Status
  • CSIST technicians will follow UPD Assembly document prepared by Mike Schmanau
  • Production of needed I-Frames for UPD boards was finished with priority in Dec 06
  • Cabling and soldering work on UPD boards is waiting for materials and tooling; most needed parts will arrive mid January

Assembly discussion at CSIST

TIM Jan07, JSC

fm u crate assembly status
FM U-Crate Assembly Status
  • JINF production and testing has to be finished
  • UHVG production and testing has to be finished; PCA now waiting for new part supply
  • CSIST accepted to produce three set of flight cables for us

- materials will be delivered mid January

- U Cabling document is being prepared (lenghts and procedure)

- final cable lengths already partly verified on wooden mockup (Andrey)

TIM Jan07, JSC

time schedule updated
Time Schedule (updated)
  • Delays: shipment of UPD assembly materials and tools to CSIST; late Chinese New Year holidays in February
  • Full TRD readout test with FM Electronics will be performed in Aachen

TIM Jan07, JSC

status summary
Status Summary
  • Board-level acceptance tests were completed for needed FM boards in December06 (excluding Uhvg and Jinf); two UPSFE boards still need part exchange
  • Assembly of two FM set of UPD and U-Crate will start as soon as materials arrive at CSIST

TIM Jan07, JSC

backup slides
Backup Slides

TIM Jan07, JSC

actel off signal failure
Actel off-signal Failure
  • Consequence: two UHVG boards cannot be switched to ON state
  • Lucky incident: after a replacement also observed on QM2 board with a new Actel

Actel0 (on) output:

high/low

opens/closes

transistor

UHVG input: Small current

(which is OFF state)

Actel1(off) output:

constant drop

0.6 V

TIM Jan07, JSC