An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Industrial Wastewater Permits 2014 Environmental Trade Fair Karen Holligan

  2. Overview • Processing the permit application • Filling out the permit application – help us to help you

  3. Permitting Process • Administrative review • Technical review • Public notice / (public comments) • (EPA review / objections) • (Public meeting / contested case hearing) • Agency decision – issued / denied

  4. Processing Time Frames • Newapplication – 330 days • Major amendment • Major facilities – 330 days • Minor facilities – 300 days • Renewal • Major facilities – 330 days • Minor facilities – 300 days

  5. Processing Time Frames • Timeframes may be extended if: • EPA issues objections to the draft permit • TCEQ receives request(s) for public meeting or contested case hearing

  6. Administrative Review • Administrative report • Applicant and site information • Notice information • Landowner information • Respond promptly to any requests for additional information. Delaying your response delays your permit.

  7. Administrative Review • Notice of Receipt of Application and Intent to Obtain a Water Quality Permit (NORI) – “first notice” • Publish promptly and return documentation to the Chief Clerk’s Office (CCO) • Draft permit cannot be filed with the CCO if NORI process is incomplete – this may delay your permit Notice # 1

  8. Technical Review • Water Quality Standards • Uses and criteria • Antidegradation • Endangered species • Critical Conditions • Critical flows or mixing conditions • Mixing zone definition

  9. Technical Review • Dissolved Oxygen (DO) Modeling • Impact of discharge(s) on DO • Water body impairments • Completed total maximum daily loads (TMDLs) • Biomonitoring • Whole effluent toxicity (WET) testing or limits • Species, frequency, dilutions

  10. Technical Review cont. • Agronomy (disposal by irrigation) • Crops • Soil testing • Hydrogeology • Pond-lining requirements • Buffer zones • Groundwater monitoring • Industrial Permits

  11. Industrial Permits - Development • Data completeness review • Compliance history • Self-reported effluent data • Technology-based effluent limits • Water quality-based effluent limits • Final effluent limits – most stringent of tech-based, water quality-based, and existing permit limits

  12. Industrial Permits - Review • Team leader • Applicant • (Legal) • (Other technical staff)

  13. Industrial Permits - Review • Public – Notice of Application and Preliminary Decision (NAPD) – “second notice” • Again, publish promptly and return documentation to the CCO. • If comments are received, permit writer and Legal prepare a response to comments document • If public meeting is held, comment period typically extended to end of meeting. Notice # 2

  14. Industrial Permits - Review • (EPA review – approve or issue objections – respond to EPA objections) • (Request(s) for contested case hearing – granted or denied) • Permit issued or denied

  15. Filling out the Application • If an item is not applicable, enter “N/A”. Do not leave the item blank. • If you’re not sure how to fill out part of the application: • Read the instructions (!) • Call the Water Quality Division (512-239-4671) and ask to speak with an industrial permit writer. • Provide complete information each time, even for renewals.

  16. Technical Report - Tips • Item 1 • Describe all processes that generate wastewater. • Include legible facility maps. • Item 2 • Describe treatment systems, if any. Err on the side of too much detail. • Include flow schematic with water balance. • Item 3 • Impoundments – Provide all information such as liner type, storage volume, and surface area.

  17. Technical Report – Tips cont. • Item 4 - Outfall information • List all contributing waste streams. • Include volumes of all waste streams, even if they are very small. • Include % of total flow volume of each waste stream. • Be sure that the sum of all waste percentages equals 100%. • Be sure information in table is consistent with flow schematic/water balance.

  18. Technical Report – Tips cont. • Items 12-14 • Amendments/modification requests – try to include all changes up front. • Not including all changes up front may cause significant delay in processing the permit application.

  19. Technical Report – Worksheet 1.0 EPA Effluent Categorical Guidelines • Item 1 - Include all parts and subparts of Title 40 Code of Federal Regulations (CFR) that apply. • Item 2 – Include all production data (in appropriate units) for each category and subcategory. • Item 3 – Provide breakdown of process vs. non-process wastewater. • Item 4 – Provide complete information on processes, 40 CFR Parts and Subparts, and start dates so that permit writer can determine whether New Source Performance Standards apply.

  20. Technical Report – Worksheet 2.0 Pollutant Analyses • Plan ahead • Begin sampling and analyzing effluent so that all required data can be submitted with the application. • Effluent data is required for renewal applications. • Applications are no longer processed without analytical data. Exceptions: • new facilities • facilities with no discharges due to drought or other circumstances • Analytical labs must be NELAC-certified.

  21. Technical Report – Worksheet 2.0 Pollutant Analyses • Minimum analytical levels (MALs) in the June 2010 Implementation Procedures were approved by EPA on July 12, 2013. • Many have been lowered, e.g.: • Total copper: 10 µg/L 2 µg/L • Total lead: 5 µg/L 0.5 µg/L • Permit application forms are being updated and are scheduled to be available on July 14, 2014.

  22. Technical Report – Worksheet 3.0Texas Land Application Permits - TLAPs • Complete all applicable information (irrigation, evaporation, or both). • Provide cropping plan if irrigating.

  23. Technical Report – Worksheet 3.0Texas Land Application Permits - TLAPs • Provide pollutant analysis. • Analytical labs must be NELAC-certified (signature required on page 17). • Fill out all required pollutant analysis tables. • In Table 7, include data for all parameters regulated in the permit. • In Table 8, include data for all parameters not regulated in the permit.

  24. Technical Report – Worksheet 3.1TLAPs Water balance • Needed to calculate allowable land application rates and storage volumes (when storage is required). • Information needed includes: • Curve number (CN) • Effluent conductivity (Ce) • Maximum allowable conductivity of soil solution (CL) • Irrigation efficiency (K)

  25. Forms and Instructions Application forms and instructions, plus additional information, are available at the following TCEQ web site: http://www.tceq.texas.gov/permitting/wastewater/industrial/TPDES_industrial_wastewater_steps.html This page also includes a link to Spanish language notice templates.

  26. For More Information: Phone: 512-239-4671 Water Quality Division Industrial Permits Team Questions ?