Data communications program
This presentation is the property of its rightful owner.
Sponsored Links
1 / 7

Data Communications Program PowerPoint PPT Presentation


  • 106 Views
  • Uploaded on
  • Presentation posted in: General

Data Communications Program. MEM/EWR ATCT DCL Trials PMR Update. To:Jesse Wijntjes , Program Mgr From: Gregg Anderson, Matt Maki, Pete Muraca Date: 03.11.2013. Agenda. MEM Trials Build 4.5 Limited Ops Summary MEM Schedule Milestones Build 6.0 Functional Testing Status

Download Presentation

Data Communications Program

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Data communications program

Data Communications Program

MEM/EWR ATCT DCL Trials

PMR Update

To:Jesse Wijntjes, Program Mgr

From: Gregg Anderson, Matt Maki, Pete Muraca

Date: 03.11.2013


Agenda

Agenda

  • MEM Trials Build 4.5 Limited Ops Summary

  • MEM Schedule Milestones

  • Build 6.0 Functional Testing Status

  • EWR Trials Schedule/Activities

  • Trials Timeline

  • Trials Budget


Build 4 5 limited ops trials complete

Build 4.5 Limited Ops Trials Complete


Mem schedule milestones

MEM Schedule Milestones

  • The Milestone Schedule Outlook:

    • Build 6 WJHTC Installation Complete: March 4

    • Build 6 WJHTC/MEM Functional/Pre-SAT Testing: March 4-20

    • MEM Limited Full Functionality Trials (3 Ops/day): March 26 – April 26

    • MEM Full FANS Fleet 24x7 Trials Start: April 30

    • 4pm Daily Build 6 Testing/PTR review telcon

  • Limited Full Functionality Trials on track for March 26:

    • Goal is 50 flight DCL operation shakeout

      • Minimum 35, 20 MD-11, 15 B777

  • DTAP Build 7 Formal Requirement Development Underway

    -Thales starting scope/cost development for FAA review


Ewr trials schedule activities

EWR Trials Schedule/Activities

  • EWR DTAP4 Hardware scheduled for pickup at Thales on March 15:

    • Will be driven to EWR ATCT

  • EWR DTAP4 equipment, cables and display installation at EWR ATCT confirmed for the week of March 18

  • Team met with UPS on March 6 in Louisville:

    • UPS confirmed EWR Trials participation

    • UPS to provide live aircraft for ramp FANS/DCL testing during Pre-SAT and SAT testing at both MEM and EWR

    • Initial MOU comments back from UPS