180 likes | 563 Views
Topics for Discussion. The PGBT Segment IV Success StoryThe DNT Extension Phase 3 Success StoryAggressive Project Incentive UsePros/Cons of Design-Bid-BuildSummaryQuestions. Dallas North Tollway System. President George Bush Turnpike. . . Segment VFully Opened 2001. . Segment IVFully Opened 2005.
E N D
2. Topics for Discussion The PGBT Segment IV Success Story
The DNT Extension Phase 3 Success Story
Aggressive Project Incentive Use
Pros/Cons of Design-Bid-Build
Summary
Questions
5. The PGBT Segment IV Success Story Funding includes $135 ISTEA Loan
Full NEPA EIS
Significant environmental challenges
Design at risk during the environmental process
Schematics, ROD and 404 permit approvals obtained in same month
6. Right-of-way acquisition and utility relocations started immediately
First project bid 4 months after environmental ROD
Successful opening in September 2005, 5 months ahead of schedule
Negotiated acceleration on each contract
Negotiated additional open to traffic incentives The PGBT Segment IV Success Story
8. The DNT Extension Phase 3Success Story Primary ROW was donated before design began
ILAs in-place and executed before design began
Incorporated city water & wastewater relocation into PS&E package
Leveraged franchise utility agreements for relocations
9. The DNT Extension Phase 3Success Story Combined 2 design packagesinto 1 to balance earthworkand ensure better unit cost
First project design deliveredin 16 months, $83M inconstruction cost
No slippage for design consultants, liquidated damages
Created corridor-widemasterplans for ITS, signing & illumination
Created System Wide Design Guidelines for entire corridor
12. Aggressive Project Incentive Use DNT MLP 2 & 3 express lane reconstruction
Contract allowed 17 days of lane closure
13. Aggressive Project Incentive Use Aggressive incentives resulted in:
14. Analyzing the Process Compare to stockbroker model:
Full Service Broker – rewards may be greater by hiring the professional, but loss of control may be costly
Discount Broker – owner manages the process to maximize reward
Owner should be informed and develop strengths to self manage portfolio
15. Pros to Design-Bid-Build A traditional process
Process is flexible
Offers ability to manage time and cost
Potential of retaining the risk premium sought by the Design-Builder
Utilizes similar Value Engineering savings as Design-Build
Competitive bidding results in lowest cost
Relative ease of ensuring Quality Control
16. Cons to Design-Bid-Build Contractors focus on exploiting error in Specifications & Estimate
Increases in construction cost risk to owner
Standardize design for market wide application
Does not leverage individual contractor strengths
Prescriptive contracts reduce design innovation opportunities
17. Optimizing Design-Bid-Build Put greater responsibility on designer to prepare a complete package – PS&E
Incorporate Value Engineering in design
Constructability reviews
Expediting letting process
Design at risk in advance of environmental clearance or bond sale
Managing risk
Incentives/damages
18. Summary NTTA has had great success on PGBT Segment IV and DNT Extension Phase 3.
The expedited design-bid-build process has allowed the NTTA team to:
19. Questions?Contact:Mark Bouma, P.E.mbouma@ntta.org214-461-2058