The planning p rocess
This presentation is the property of its rightful owner.
Sponsored Links
1 / 10

The planning p rocess PowerPoint PPT Presentation


  • 60 Views
  • Uploaded on
  • Presentation posted in: General

The planning p rocess. Martin Andersson Mathias Högberg Konrad Wladyko. Stages. Introduction Work breakdown structure - WBS Lead times Levels of planning Pre-contract planning Contract planning Planning a project References and further reading. Introduction.

Download Presentation

The planning p rocess

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


The planning p rocess

The planning process

Martin Andersson

Mathias Högberg

Konrad Wladyko


Stages

Stages

  • Introduction

  • Work breakdown structure - WBS

  • Lead times

  • Levels of planning

  • Pre-contract planning

  • Contract planning

  • Planning a project

  • References and further reading


Introduction

Introduction

  • To set a realistic time framework for the project

  • To establish realistic standards and avoid ”wishful thinking”

  • To aid control during the project

  • To monitor performance in terms of output, time and money

  • To review progress and take action when necessary to correct the situation


Work breakdown structure

Workbreakdownstructure

  • Key tool

  • Subdivide the project

  • Hierarchy


Lead times

Leadtimes


Levels of planning

Levelsof planning

  • Project planning

  • Pre-tender planning

  • Pre-contract planning

  • Contract planning


Pre contract planning

Pre-contract planning

  • Period between contract award and commencement of work on site

  • Target programme

    • Internal contractor programme

    • Compressed version of the master programme

    • Time bars

  • Procurement programme

    • For each subcontractor

    • Positive and negative time


Contract planning

Contract planning

  • During the contract stage

    • Stage programme

    • Series of short-term programmes

  • Is done by the main contractor

  • Revised programme


Planning a project

Planning a project

  • Requires a logical approach including:

    • Getting a feel for the project

    • Establishing key project dates

    • Establishing key activities/events

    • Assessing how long the activities will take

    • Establishing the sequence

    • Deciding which programming technique to use


Preferences and further reading

Preferences and furtherreading

  • BrianCooke, Peter Williams, 2010. Construction Planning, Programming and control, third edition.


  • Login