News from IceMOS. Alessandro Mapelli CERN PH-DT. frame. baseline. Schedule update December 3 rd. today. Done.. First wafers sent to CERN. Bulk Si vs SOI flows. Silicon Etching. Etch measurements from the first 9 bulk silicon wafers. Channels etch 70um +/- 7um.

Download Presentation

News from IceMOS

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


News from IceMOS

Alessandro Mapelli

CERN PH-DT

frame

baseline

GTK Collaboration meeting


Schedule update December 3rd

today

Done.. First wafers sent to CERN

GTK Collaboration meeting


Bulk Si vs SOI flows

GTK Collaboration meeting


Silicon Etching

  • Etch measurements from the first 9 bulk silicon wafers

Channels etch 70um +/- 7um

Manifolds etch – total depth 285um +/- 25um

IceMOS CONFIDENTIAL

GTK Collaboration meeting


Silicon Etching

IceMOS CONFIDENTIAL

GTK Collaboration meeting


First wafers have been shipped..

  • 3 bulk silicon wafers have been shipped on December 10th from IceMOS to CERN.

  • These wafers will be used to validate the last step of the fabrication process at EPFL with wafers from IceMOS.

  • It consists of the silicon etching with KOH to thin the acceptance area of the cooling plate.

GTK Collaboration meeting