Automated RGH Operational Sequence . Potential Gas in riser, Driller actuates MPO RGH system RGH automated sequence is initiated by Driller (pre or post well control operations depending upon TOI and Chevron policy);

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Automated RGH Operational Sequence ' - stacie


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Automated RGH Operational Sequence

  • Potential Gas in riser, Driller actuates MPO RGH system
  • RGH automated sequence is initiated by Driller (pre or post well control operations depending upon TOI and Chevron policy);
  • SCADA system automatically interrogates line up to ensure all required RGH flow spool and surface Buffer and RGH Manifold valves are correctly lined up to UMGS
  • Flow spool dual flow outlet valves open to dual return flow hoses and Buffer Manifold
  • PCVs on RGH Manifold full open
  • Upon confirmation the system is lined up correctly, the QCA closes in <3secs
  • Driller maintains circulation using riser booster pump injecting into LMRP, above closed SS BOP
  • RGH PCVs start to close/control to maintain 300psi ASBP on RGH Manifold while riser booster pump pressure stabilises.
  • Once riser booster pump pressure is stable, the RGH SCADA system starts to control the PCVs to maintain constant riser booster pump pressure
  • Gas is circulated out of the riser to the UMGS with the RGH system maintaining constant riser booster pump pressure
  • Riser is circulated to clear any gas
  • Riser secure