1 / 21

CSC Limit Calculation & Posting

This document provides a detailed roadmap of how ERCOT performs daily CSC limit calculations and identifies the posting location. It also allows for variations in the processes for special circumstances.

srieke
Download Presentation

CSC Limit Calculation & Posting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CSC Limit Calculation & Posting John Adams jadams@ercot.com Operations Support 5/11/2004

  2. Course Roadmap • Review of How ERCOT performs Daily CSC Limit Calculations • Identification of Posting Location • Note – Variation in these processes by the professional performing the calculation is allowed for special circumstances

  3. Farmersville – Royse Switch North • Farmersville – Royse Switch South Houston • Graham-Parker • Graham-Benbrook North Northeast • Jewett – T.H. Wharton • Gibbons Creek – Obrien • Jewett – Tomball • Roans Prairie - Kuykendahl CRE • Sandow-Temple 1 • Sandow-Temple 2 West • STP Dow 18 • STP Dow 27 • STP WAP 39 CRE South CSC Monitoring • CSC Limits are defined through detailed planning and engineering studies

  4. Create a Power Flow Base Case • Continuously during the week TDSP’s provide updates to the ERCOT network model. • Once/week: Typically Tuesday, a database load is performed • Once/Week: Normally the following day, a new study base case is created.

  5. Create a Daily Base Case • Operations Engineer uses the power flow base case, and overlays the load forecast, the generation plan, and the outages scheduled for peak hour (typically) • Operations engineer reads the outage notes, looking for outages with significant impact on CSC’s. • Solve Power flow case, execute contingency analysis. Save case as daily base case.

  6. Calculate South-North limit • Examine post-contingency overloads to see if violations on CSC, CRE or associated elements already exist. • If not, increase load in North Central load Zone [wxznrthc]. Decrease load in South Central load zone and Southern Zone. • Run Contingency analysis and examine results for post-contingency overloading on CSC’s and associated elements until post contingency overload detected.

  7. Calculate South-North limit • When post-contingency overload detected, open contingency line in base case and scale load in North Central/South & South Central until post-contingency overload 100% of emergency rating.{15 minute rating may be used if an RAP exists for this element} • Observe the flow on Sandow-Temple double circuit and record as the S-N limit.

  8. Calculate South-North limit • Examine Outage notes to determine if an outage is affecting the limit during the day. If so; repeat limit calculation process for period after restoration of the outage.

  9. Calculate North-Houston limit • Retrieve daily save case. • Examine post-contingency overloads to see if violations on CSC, CRE or associated elements already exist for North-Houston • If not, increase load in Coast load Zone [wxzcoast]. Decrease load in East load zone and North Central Zone. • Run Contingency analysis and examine results for post-contingency overloading on CSC’s and associated elements [or under voltage] until post contingency overload detected.

  10. Calculate North-Houston limit • When a post-contingency overload is detected, open the contingency line in the power flow case and scale load in until post-contingency overload is 100% of emergency rating.{15 minute rating may be used if an RAP exists for this element} • Observe the flow on Gibbons Creek-O'Brien + Jewet-THW + Jewet-Tomball + Roans Prairie-Kuykendahl-King and record as the N-H limit.

  11. Calculate North-Houston limit • Examine Outage notes to determine if an outage is affecting the limit during the day. If so; repeat limit calculation process for period after restoration of the outage.

  12. Calculate South-Houston limit • Similar to North-Houston & South –North; but scale up load in Coast load zone, and down in South load zone. • Sum STP-DOW double circuit + STP-WAP for limit.

  13. Calculate Northeast-North limit • Examine post-contingency overloads to see if violations on CSC, CRE or associated elements already exist. • If not, increase generation at NORTHEAST zone generation stations • Run Contingency analysis and examine results for post-contingency overloading on CSC’s and associated elements until post contingency overload detected.

  14. Calculate Northeast-North limit • When post-contingency overload detected, open contingency line in base case and scale generation in Northeast until post-contingency overload is 100% of emergency rating.{15 minute rating may be used if an RAP exists for this element} • Observe the flow on Farmersville-Royce double circuit and record as the NE-N limit.

  15. Calculate West-North limit • Similar to Northeast-North CSC calculation but Sum Graham-Parker and Graham-Benbrook for the CSC limit.

  16. Posting of CSC limits • https://tcr.ercot.com/default.cfm?func=tcrpostings

More Related