Generation Interconnection at SPP

Generation Interconnection at SPP. Generation Interconnection Queue As of 9/30/2010. 116 Active Interconnection Requests under study for 20,180MW 103 of the Active Interconnection Requests are for wind for a total of 19,256MW Interconnection Agreements Pending - 42

sorley
Download Presentation

Generation Interconnection at SPP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Generation Interconnection at SPP

  2. Generation Interconnection QueueAs of 9/30/2010 • 116 Active Interconnection Requests under study for 20,180MW • 103 of the Active Interconnection Requests are for wind for a total of 19,256MW • Interconnection Agreements Pending - 42 • Transition Cluster – 21 GIA for 4,799 MW • DISIS-2009-001 – 21 GIA for 2,773 MW • Wind Requests currently with Interconnection Agreements • 66 GIA for 10,144 MW • Approximately 3,400MW of this is in service with the remainder on suspension or otherwise not built out the full capacity of the GIA.

  3. Generation Interconnection Queue as of 9/30/2010

  4. Queue Reform • Generation Queuing Task Force (GQTF) formed in March, 2008 • Queue Reform Filing made in June, 2009 (ER09-1254) • Queue Reform Filing Approved by FERC in July, 2009

  5. Before Queue Reform • Status (on April 1, 2009) • 278 Active Requests totaling 61,128 MW • 228 for Wind totaling 50,868 MW • 50 for Fossil or Other totaling 10,260 MW • A sequential queue • Once problem areas identified; queue would bog down as upgrade costs increased • 136 new interconnection requests in 2008 brought the issue to a head.

  6. Before Queue Reform • Interconnection Customers allowed to sign Interconnection Agreement and then “suspend” the agreement for 3 years. • Suspended Interconnection Agreements pose problems in that Interconnection Customer are “holding” capacity but not using that capacity. • Subsequent (lower queued) customers may be liable for costly upgrades that would not be necessary if the suspended customers were to outright relinquish their queue position.

  7. Queue Reform Measures • Site Control – Tighten requirements for site control. Site Control required to enter the queue for an Impact Study • Stricter Milestones for Advancement in process • Different Queues for Feasibility Study and Impact Study. Customers that meet stricter milestones can advance ahead of Customers that cannot.

  8. Queue Reform Measures • Cluster Studies • intended to study multiple requests simultaneously and allocate costs of network upgrades that are beneficial to the group. • All interconnection requests in each queue that are received in a 180 day open season period are studied together. • Allows for all interconnection requests in the queue to commence study process within six months and greatly lessens the queue backlog burden

  9. Queue Reform Measures • Cluster Studies (continued) • A set of upgrades that is necessary for the interconnection of the entire cluster of interconnection requests is determined. • The upgrade set’s costs are shared by the entire cluster of interconnection request based on a MW usage basis of each interconnection request. • Upgrades that are required for the interconnection of the cluster (i.e. shared upgrades) cannot be suspended.

  10. Queue Reform Measures • Increased Study Deposits • Stricter Suspension Requirements • Reduced from 3 years • 6 months – no cost • 6-18 months – Requires payment of allocated costs of network upgrades or minimum payment of $1M - $5M depending on project size. • Shared Network Upgrades cannot be suspended.

  11. Wind in the Queue before and after Queue Reform (Queue Reform effective Q2 2009)

  12. What’s Next for GI • ITP – Developed in part to ease the pressure on the GI queue • AGCTF – Task Force formed to determine optimum methods of connecting generation including wind farm collector systems • LUPTF – Task Force formed to optimize land use amongst SPP member utilities, non-SPP utilities, generator developers

  13. Juliano Freitas