An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FALLA LA CIUDAD DE LONDRESJUEVES 28/08/03 A LAS 18:20 IFOb280803.ppt 1/6

  2. FALLA EN LONDRES DEL JUEVES 28/08/03 A LAS 18:20DESCRIPCIÓN • 18:10 - EN UN TRANSFORMADOR DE 275 KV DE LA E.T. HURST, EN KENT,APARECIÓ UNA ALARMA • 18:20 EL TRANSFORMADOR FUE SACADO DE SERVICIO YA QUE EL FLUJO DE ENERGIA TENIA CAMINOS ALTERNATIVOS. • 18:20:07 - A LOS 7 SEGUNDOS SE PRODUJO UNA FALLA EN EL CABLE DE 275 KV NEW CROSS - WIMBLEDON . • COMO CONSECUENCIA QUEDO AFECTADO EL SUMINISTRO QUE PROVEEN LAS ESTACIONES DE 275 KV NEW CROSS, WIMBLEDON Y HURST QUE ALIMENTAN EL CENTRO DE LONDRES.

  3. E.T. HURST DONDE SE SACÓ DE SERVICIO EL TRAFO CABLE DE 275 KV QUE FALLO 7 SEG DESPUES ESQUEMA ELÉCTRICO DEL AREA AFECTADA

  4. ESQUEMA GEOGRÁFICO Y ELÉCTRICO GENERAL DE LONDRES. CABLE DE 275 KV QUE FALLO 7 SEG. DESPUES E.T. HURST DONDE SE SACÓ DE SERVICIO EL TRAFO

  5. FALLA EN LONDRES DEL 28/08/03. REPOSICION • A LOS QUINCE MINUTOS SE COMENZÓ LA REPOSICIÓN DEL SERVICIO, EL CUAL QUEDÓ MAYORITARIAMENTE REESTABLECIDO A LOS 30 MINUTOS. • LOS EQUIPOS AFECTADOS POR LA FALLA PERTENECEN A LA EMPRESA DE TRANSPORTE “NATIONAL GRID TRANSCO”. • LOS CLIENTES AFECTADOS PERTENECEN A LA DISTRIBUIDORA EDF ENERGY QUE ABASTECE A 5.000.000 DE CLIENTES DE GAS Y ELECTRICIDAD EN EL AREA DE LONDRES.

  6. FALLA EN LONDRES DEL JUEVES 28/08/03 A LAS 18:20CAUSAS • SEGÚN LA INFORMACION DE “NATIONAL GRID TRASNSCO” LAS FALLAS FUERON INDEPENDIENTES. • NO OBSTANTE EL CABLE QUE FALLÓ TUVO UNA MAYOR CARGA Y PUDO HABER FALLADO POR ESE MOTIVO • FUERON AFECTADAS ALREDEDOR DE 250.000 PERSONAS EN LONDRES, SOBRE UN TOTAL DE 7.000.000 QUE VIVEN Y TRABAJAN EN LA CAPITAL. • PRODUJO DETENCIONES DE 1000 FORMACIONES DE SUBTERRÁNEOS Y TRENES.