Measurement and Verification of Refrigeration Measures in 4 Grocery Stores in Pacific County

Measurement and Verification of Refrigeration Measures in 4 Grocery Stores in Pacific County. Presented to the Regional Technical Forum August 8 th , 2006. Introduction. Review Work to Date with NRM Present Results of M&V for 4 stores in Pacific County

Download Presentation

Measurement and Verification of Refrigeration Measures in 4 Grocery Stores in Pacific County

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Measurement and Verification of Refrigeration Measures in 4 Grocery Stores in Pacific County Presented to the Regional Technical Forum August 8th, 2006

  2. Introduction • Review Work to Date with NRM • Present Results of M&V for 4 stores in Pacific County • Present recommendations for future grocery store M&V.

  3. February 7th 2005 • RTF reviewed and approved NRM measures and calculation methodology on a pilot basis: • Require 3rd-party M&V on first 10 projects. • Revise credit as indicated after completion of first 10 projects.

  4. March 2005 • BPA developed M&V plan for pilot. By BPA • Two week pre/post installation electrical power metering. • Pre/post installation review of equipment and operation. By NRM • Detailed pre-installation audit and post installation data collection.

  5. June 2005 – Pacific County Incentive Offer

  6. July–November 2005 - BPA Baseline Metering • 5 stores • 10 site visits over 5 months • Average 32 man-hours per store in combined travel and in-store time. • Labor Intensive • Adds months of time

  7. RESULTS

  8. Baseline Compressor-Condenser Unit Duty Cycle & Run-Time kW Load Observed NRM* Cooler 52% 53% Freezer 68% 53% Cooler kW 4.3 4.3 Freezer kW 4.6 4.3 * NRM assumes 55% Duty Cycle for units during non-winter months (OSA temp > 35 degrees F), otherwise 35%.

  9. Post-Install Compressor – Condenser Unit Duty Cycle Observed NRM* Cooler 33% ~42% Freezer 64% ~42% * NRM assumes 55% Duty Cycle for units during non-winter months (OSA temp > 35 degrees F), otherwise 35%. NRM estimates 3% reduction in compressor-condenser unit duty cycle thru direct digital temp controls. Further reductions in duty cycle estimated by reduced refrigeration load due to ECM motor installations, but not directly specified in % basis.

  10. Reduced Compressor Duty Cycle Observed NRM* Cooler 19% ~11% Freezer 3% ~11% * NRM estimates reduction in compressor-condenser unitduty cycles due to combination of measures – direct digital control, evaporator fan cycling, and ECM motor installations. Due to ECM motor installations only in coolers, not freezers, NRM estimated % reductions should be slightly higher for cooler compressor-condenser units compared to freezers [NRM calculations do not directly specify % duty cycle reductions for specific measures, only kWh per year.]

  11. Compressor-Condenser Units per Stores Coolers & Freezers • See Spreadsheet • Note large variance in run-time kW, from low of 1.6 to high of 10.3.

  12. Baseline Door Heater Duty Cycle & Average Connected Load (kW) Observed NRM* Cooler X 100% Freezer X 100% Cooler Door (kW) 87 95 Freezer Door (kW) 170 195 * NRM assumes 100% duty cycle pre-installation. Site visits did not conflict with this assumption, but note difficulty in metering (CT sizes, access, etc.), as well as a difference in temperature felt and measured at several doors.

  13. Post-Installation Average Door Heater Duty Cycle & Annual kWh per Door Savings Observed NRM* Cooler 4% 21% Freezer 54% 59% Cooler Door 826 644 (kWh/yr Savings) Freezer Door 822 744 (kWh/yr Savings)

  14. Door Heater Control Results per Stores, Coolers & Freezers • See Spreadsheet • Cooler Door Heater Control with average B/C ratio = 2.57 • Freezer Door Heater Control with average B/C ratio = 1.40

  15. Sampling of Baseline Evaporator Fan Connected Load (kW) – Metered to NRM Estimates Observed (kW)NRM (kW) Bev. Cooler (10) 1.25 1.173 Produce Cooler (4) 0.36 0.704 Bev. Cooler (10) 1.65 1.955 Meat Cooler (3) 0.61 0.528 Misc. Freezer (4) 0.37 0.938 Meat Freezer (2) 0.27 0.352 Misc. Freezer (3) 0.91 0.587

  16. Post-Installation Average Evaporator Fan Duty Cycling Observed NRM* Cooler 59% 68.78% Freezer 63% 68.78%

  17. Post-Installation Evaporator Fan % Savings and Fan kWh per Year Savings from Control Measure Observed NRM* Cooler 41% 31.22% Freezer 37% 31.22% Cooler Fan 583 444 (kWh Savings per Year) Freezer Fan 575 485 (kWh Savings per Year)

  18. Evaporator Fan Control Measure Results per Store, Coolers and Freezers • Cooler Units with Average B/C Ratio = 2.74 • Freezer Units with Average B/C Ratio = 1.40 • See Spreadsheet

  19. New Evaporator Fan ECM Motors Connected Load (kW) – Metered to NRM Estimates Observed (kW)NRM (kW)* Produce Cooler (4) 0.17 0.4224 Bev. Cooler (10) 0.93 1.197 * NRM assumes a 40% reduction in motor load.

  20. Vendor Beverage CoolersObserved Percent kWh Savings

  21. Vendor Beverage CoolersSummary Observed NRM* % Savings 35% 36%

  22. Store Total Results

  23. Recommendations • Extend as pilot for 1-year • Continue approval of NRM package of measures. • Continue approval of NRM savings calculation methodology.