MS Project Concepts. Dr. Greg Neal CIS 480 Systems Analysis and Design. Pert Network. Gantt Chart. 1,2 & 3 all start at beginning. Task List. Late Start. Slack Difference Early-Late. Early Start. Critical Path. Calculation of EarlyStart,LateStart,Slack. Task Three (3 days)

sileas
Download Presentation

MS Project Concepts

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MS Project Concepts Dr. Greg Neal CIS 480 Systems Analysis and Design Dr. Neal CIS 480

  2. Pert Network Dr. Neal CIS 480

  3. Gantt Chart 1,2 & 3 all start at beginning Dr. Neal CIS 480

  4. Task List Late Start Slack Difference Early-Late Early Start Critical Path Dr. Neal CIS 480

  5. Calculation of EarlyStart,LateStart,Slack • Task Three (3 days) • EarlyStart (Project Start on 6/1/06) • LateStart = Task 7 LateStart – Task 3 duration: 6/2/06 • Task Seven (6 days) • Task 7 StartFinish predecessor of Task 3 • EarlyStart =Task 3 Finish 6/5/06 + 1 day: 6/6/06 • LateStart = Task 9 LateStart – Task 7 duration: 6/7/06 • Task Nine (3 days) • Task 9 StartFinish predecessor of Task 7 • EarlyStart = Task 7 Finish 6/13/06 + 1 day: 6/14/06 • LateStart = Task 10 Start – 3 days: 6/15/06 Forward Calculation Slack 1 day Backward Calculation Dr. Neal CIS 480

  6. Task Dependencies • Finish-to-Start (FS) • Task B cannot start until task A finishes • Start-to-Start (SS) • Task B cannot start until task A starts (both start the same time) • Finish-to-Finish (FF) • Task B cannot finish until task A finishes (both finish at the same time) • Start-to-Finish (SF) • Task B cannot finish until task A starts Dr. Neal CIS 480

  7. Dependency Gantt Examples FinishStart(FS) StartStart(SS) StartFinish(SF) FinishFinish(FF) Dr. Neal CIS 480

  8. Lead and Lag Dependencies 1 day Lag 1 day Lead Dr. Neal CIS 480