Business Case 031 – Tunnels Refurbishment

Business Case 031 – Tunnels Refurbishment. Taxi Liaison Meeting. 10-Apr--14 Victoria Sutton (Landside Operations) Michael Cooper (Development Project Manager) 19341-XX-ME-400-000137. Project Overview. Refurbishment of Main & Cargo Tunnels Replacement or Introduction of 24 various systems

shiri
Download Presentation

Business Case 031 – Tunnels Refurbishment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Business Case 031 – Tunnels Refurbishment Taxi Liaison Meeting 10-Apr--14 Victoria Sutton (Landside Operations) Michael Cooper (Development Project Manager) 19341-XX-ME-400-000137

  2. Project Overview • Refurbishment of Main & Cargo Tunnels • Replacement or Introduction of 24 various systems • Structural Works, Life Safety Equipment, Architectural • Objectives • Reduce risk to life to As Low As Reasonably Practicable (ALARP) • Suitably reduce business continuity risk • Replace life expired assets • Minimise operational cost impacts • Improve passenger experience

  3. Architectural Treatment • “Living Garden” planting masques entrance to tunnel (similar to T5 Welcome Arch) • Improved lighting under business car-parking bridge to extend entrance to the tunnel • Improved internal treatment through simple lighting

  4. Traffic Management • Planned Closures • Various configurations of lane closures from 22:00-05:30 • Always one lane in and one lane out available • No day-time main bore closures • Side bores closed throughout duration of works • Extensive Modelling undertaken and numerous alternatives considered • Traffic Trials undertaken April 2013 • Cyclists • Will remain to use the side-bores during survey works • Will not be permitted to use the tunnels during these works

  5. Programme • Apr-14 Surveys Commence • 22:00-05:30 night time closures only • Side-bores remain open during the day • One side-bore to main open at night for cyclists (alternates) • Cladding to be removed • May-14 Surveys Conclude • May-14Main Works Start • 22:00-05:30 night time closures only • Both side bores closed 24/7 • Any extension of times will be proceeded by trial closures first • Dec-15Main Works Complete

More Related