WG TDC2/TCC2 Lessons learned from BA1

Loading in 2 Seconds...

play fullscreen
1 / 8

WG TDC2/TCC2 Lessons learned from BA1 - PowerPoint PPT Presentation


  • 116 Views
  • Uploaded on

WG TDC2/TCC2 Lessons learned from BA1. 10-09-2013 JL- GRENARD EN-HE. Removal of SPS DUMP. Time for the operation as estimated -> ~20min Less radioactive element handle first Position of the operators well optimized-> behind the shielding of the tractor

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' WG TDC2/TCC2 Lessons learned from BA1' - shen


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
wg tdc2 tcc2 lessons learned from ba1

WG TDC2/TCC2Lessons learned from BA1

10-09-2013

JL- GRENARD EN-HE

removal of sps dump
Removal of SPS DUMP
  • Time for the operation as estimated -> ~20min
  • Less radioactive element handle first
  • Position of the operators well optimized-> behind the shielding of the tractor
  • Installation of marks for quicker positioning
removal of sps dump1
Removal of SPS DUMP
  • Installation of cameras for some checks
removal of sps dump2
Removal of SPS DUMP
  • Shielding of the Volk tractor
removal of sps dump3
Removal of SPS DUMP
  • Failure tests of the Loehr trailer
removal of sps dump4
Removal of SPS DUMP
  • All operations supervised with cameras-> follow up of operations by experts
to be still optimized
To be still optimized
  • Conical head for positioning the trailer underneath the element to be optimized
  • Additional marks to be installed on the trailer
removal of warm magnet
Removal of warm magnet
  • Same procedure as for the dump

-> training in a mock up

-> optimization of the tasks

-> additional tooling

Still some improvements to be done