Graduation Project (1) Strengthening of an existing reinforced concrete structure

United Arab Emirates University College of Engineering Civil and Environmental Department. Graduation Project (1) Strengthening of an existing reinforced concrete structure. Instructor: Dr. Ashraf Biddah. Student Name ID No. Nabil Raweh Qahtan 980410066

shayna
Download Presentation

Graduation Project (1) Strengthening of an existing reinforced concrete structure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. United Arab Emirates University College of Engineering Civil and Environmental Department Graduation Project (1)Strengthening of an existing reinforced concrete structure Instructor: Dr. Ashraf Biddah Student Name ID No. Nabil Raweh Qahtan 980410066 Mohammed Eisa Al-Harrasi 980710101 Hazem Bakri Al-Naser 199901443

  2. Introduction • Exclusive Summary • The general idea of the project. • Problems Facing reinforced concrete structures.

  3. Exclusive Summary The main achievements: • Studying the Strengthening Methods. • Selection of an exiting building. • Experimental Test. • Beginning of Structural Analysis.

  4. The general idea of the project • The owner of a residential building wanted to convert his building to a commercial building. • According to change in the use of existing structure, the structural system of the building will be modified to fit the new changes. • PROBLEM: The old building cannot carry the new loads that come from the changes. • DESIGN BRIEF : Design a strengthening system that can increase the capacity of the existing structural system to be able to carry the new loads that come from the changes.

  5. Problems Facing Reinforced Concrete Structures • Load increases. • Damage to structural parts. • Improvements in suitability for use. • Modification of structural system. • Errors in planning or construction.

  6. STRENGTHENING REINFORCED CONCRETE STRUCTURES BY BONDING STEEL PLATES: • Strengthening is the process of adding capacity to a member of structure. • Attachment of steel to concrete: • Adhesive connecting mechanism. • Bolting connecting mechanism.

  7. Explanatory Sketch Fig. 1 Techniques of plating reinforced concrete beams.

  8. STRENGTHENING REINFORCED CONCRETE STRUCTURES BY PRESTRESSING CABLES: • Post-tensioning is a technique used to prestress reinforced concrete after concrete is placed. • The tensioning provides the member with an immediate and active load-carrying capability.

  9. External Post-tensioned picture

  10. The advantages of External Prestressing • Ability to restress, destress and exchange any external prestressing cable. • Crack free members. • Reduce deflection. • High fatigue and impact resistance.

  11. The Disadvantages of External Prestressing • Usually requiring a greater section depth. • More exposed to environmental influences (fire, vandalism, aggressive chemicals etc.). • Handling of the tensioning devices may be more difficult. • High cost.

  12. Concrete Jackets(Section Enlargement)

  13. Concrete Jackets (Section Enlargement) • Enlargement is the placement of additional concrete and reinforcing steel on an existing structural member. • Beams, slabs, columns, and walls, if necessary, can be enlarged to add stiffness or load-carrying capacity.

  14. Concrete Jackets • In most cases, the enlargement must be bonded to the existing concrete to create a monolithic member for additional shear or flexural capacity.

  15. Column Compressive strengthening by Section Enlargement • Enlarging the cross section of an existing column will strengthen the column by increasing its load carrying capacity. • A column can be enlarged in various configurations. • The drying shrinkage effects in the concrete used to enlarge the column must be considered.

  16. Section EnlargementMethod A • In the illustration, Method A will accomplish efficient load transfer if the new portion is cast with a bond breaker between the new and old concrete. • After most of the drying shrinkage has occurred, the ties that link the old and new concrete can be installed.

  17. Section EnlargementMethod A • The gap between the new portion of the column and the existing member (to be partially supported by this column) can be filled with dry packing material. • This will allow the new material to share its portion of the load.

  18. Section EnlargementMethods B & C • When Methods B and C are used, extreme care should be exercised to select concrete mix designs with very low shrinkage rates. • Pre placed aggregate concrete generally offers the lowest drying shrinkage; it is, therefore, an excellent material for column enlargements.

  19. Disadvantages of the concrete jackets • Increasing the size of the element, which make its usage very limited. • Difficult to construct in some active buildings such as hospitals, schools because of the noise of equipments. • Needs shuttering, formworks, reinforced steel, concrete, concrete pumps, vibrators, …etc.

  20. Fiber Reinforced Polymer

  21. Fiber Reinforced Polymer (FRP) • FRP is a new class of composite material for the development and repair of new and deteriorating structures in Civil Engineering. • Search for alternatives to Steel and alloys to combat the high costs of repair and maintenance of structures damaged by corrosion and heavy use.

  22. FRP Laminate Structure • FRPs are organized in a laminate structure. • each lamina (flat layer) contains an arrangement of unidirectional fibers fabrics embedded within a thin layer of light polymer matrix material. • FRP consists of two main components: • Fibers. • Resin or Matrix.

  23. FRP Laminate Structure

  24. Types of FRP The three main types of fibers used are: • Carbon. • Glass. • Aramid.

  25. Suitability of FRP for Uses in Structural Engineering • FRP properties and advantages makes it ideal for wide spread applications in construction worldwide. • FRP has a few disadvantages.

  26. Advantages of FRP: • Corrosion Resistance. • Lightweight. • Ease of installation. • Less Finishing. • Less maintenance. • Ductility of FRP wrapped members improves dramatically. • They are ideal for external application.

  27. Advantages of FRP • They are extremely durable. • They are available in various forms:sheets, plates, fabric, etc. • They are available in long lengths that eliminates jointsandsplices. • They cure within 24 hours. • Versatility. • Anti-seismic behavior.

  28. Disadvantages of FRP • High cost, susceptibility to deformation under long-term loads • Temperature and moisture effects, lack of design codes, and most importantly, lack of awareness.

  29. Decision

  30. Introduction • M.S.Project gantt chart. • Lab tests on FRP material. • Cost estimation for G.P.1

  31. M.S. Project Gantt Chart

  32. M.S. Project Gantt Chart

  33. Experimental lab test on FRP material. • The main objective of this experiment was to study the effect of different environments on the behavior of FRP material.

  34. Beams Details • This experiment consists of 16 beams and 6 cubes. • Beams were divided to 4 groups, each group consists of 4 beams with four different reinforcements. • Beams dimensions were 10cm x 10cm x 50cm. • Minimum reinforcement of one bar with 6mm diameter (1Φ6) was used.

  35. Groups Environment Each group was exposed to four different environments as follows: Group 1: • Room temperature with 26oC. Group 2: • Hot water tank with 100 % humidity at 45oC. Group 3: • Oven (0% humidity) at 45oC. Group 4: • Outside exposed to sun radiation and the variation in temperature through the 24 hours.

  36. Equipments • Digital balance. • Molds of beams and cubes. • Mixer. • Vibrator. • Hot water tank. • Oven. • Cube test machine. • Beam test machine.

  37. Materials • Concrete mix: water, cement, sand, coarse and small aggregates. • Plastic sheet. • FRP strips. • Strain gages.

  38. Procedures • Steel reinforcements were prepared. • Strain gages were fixed on the steel reinforcement. • Concrete ingredients were calculated, weighted and mixed using a big mixer. • Concrete was poured in the molds of beams and cubes. • Concrete was vibrated and covered by plastic sheet.

  39. Procedures • 3 cubes were tested after 7 days. • Concrete beams and cubes were removed from molds and cured in potable water for 14 days. • Beams and cubes were exposed to air drying in laboratory.

  40. Procedures • FRP was applied with layer of epoxy. • Beams were exposed to the different environments for 1000 hours. • 3 cubes was tested after 28 days. • All beams was tested after 1000 hours.

  41. Experimental Result

  42. Experimental Results

  43. Experimental Results

  44. Experimental Observations • Effect of Fiber Reinforcement Polymer (FRP) on strengthening the beams: • One FRP strip increased the beam's capacity by about 100% for all environments. • Two strips of FRP increased the beam's capacity by about 200% for all environments. • All reinforced beams strengthen with FRP failed on de-bonding of the FRP at the end of strips due to the shear force at this location.

  45. Experimental Observations • Environmental effect on the beams: • The effect of environment on reinforced concrete beams with steel only is negligible. • Plain concrete with one strip of FRP (shear force) was affected in hot environments (humid and dry). Where the effect of outdoor and indoor environments was negligible.

  46. Experimental Observations • The reinforced concrete beams strengthen with FRP; (bond capacity between the FRP and the concrete)was affected in hot and humid environment. • Although the FRP in the outdoor environment was subjected to the Ultra Violet during the 1000 hrs exposure, no reduction in the beam capacity was noticed.

  47. Cost Estimation Total Cost = 1496 Dhs (within the budget)

  48. Analysis background • The most important and most difficult task faced by the structural designer is the accurate estimation of the loads that may be applied to the structure during its life. • The next problem is to decide the worst possible combinations of these loads that might occur at one time.

  49. Analysis background • The loads that will be used in this project are dead and live loads. • Dead loads are loads of constant magnitude that remain in one position. • Live loads are loads that can change in magnitude and position.

  50. Analysis background • ACI code (9.2) states that the required ultimate load carrying ability of the member U provided to resist the dead load D and the live load L must at least equal: U = 1.4D + 1.7L