1 / 9

Cavity string assembly at KEK for S1-Global

Cavity string assembly at KEK for S1-Global. Eiji Kako (KEK, Japan). Cavity Assembly Team for S1-Global. FNAL Tug Arkan (Leader) Brian Smith Marco Battistoni DESY Axel Matheisen (Supervisor, not come) Manuela Schmoekel

Download Presentation

Cavity string assembly at KEK for S1-Global

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cavity string assembly at KEK for S1-Global Eiji Kako (KEK, Japan) S1-G Webex Meeting Global Design Effort

  2. Cavity Assembly Team for S1-Global FNAL Tug Arkan (Leader) Brian Smith Marco Battistoni DESY Axel Matheisen (Supervisor, not come) Manuela Schmoekel Patrick Schilling KEK Shuich Noguchi Eiji Kako S1-G Webex Meeting Global Design Effort

  3. Cavity Assembly Team for S1-Global FNALDESY Tug Arkan Manuela Schmoekel Brian Smith Patrick Schilling Marco Battistoni Arrival date in Japan ; FNAL 13th Jan. 2010 DESY 14th Jan. 2010 Departure date from Japan ; 24th Jan. 2010 Stay in Urban Hotel for 11 nights (FNAL) 10 nights (DESY) S1-G Webex Meeting Global Design Effort

  4. Present Status of Cavities Two DESY cavities (Z108 & Z109) arrived at KEK in 4th, December. ACC011 cavity arrived at Narita airport in Dec. 21th. AES004 cavity will depart at FNAL in Dec. 23th for KEK. Both cavities will delivered at KEK by the end of December ?? S1-G Webex Meeting Global Design Effort

  5. Schedule of Cavity String Assembly (1) 11 Mon; National Holiday 12 Tue; am. Check of tools and jigs for assembly pm. Rinsing of 9 support posts by car washer Setup of support posts in class-1000 13 Wed; am. Cleaning by wiping of 2 FNAL cavities Installation of 2 FNAL cav. on support in c-1000 pm.Cleaning by wiping of 2 DESY cavities Installation of 2 DESY cav. on support in c-1000 14 Thu; am. Rough alignment of 4 cavities in c-1000 am. Arrival of FNAL colleagues at KEK pm. Arrival of DESY colleagues at Hotel nightWelcome dinner with beer S1-G Webex Meeting Global Design Effort

  6. Schedule of Cavity String Assembly (2) 15 Fri ; am.Meeting for cavity string assembly planning pm. Start-up of assembly work at STF 16 Sat. ~ 21 Thu. ;(for 6 days) am./pm. String assembly of 4 cavities in c-10 22 Fri; am. Final leak check of string cavities Start-up of Ar slow leak in c-1000 nightFarewell dinner with beer 23 Sat; Spare day for safety margin 24 Sun; Departure of DESY & FNAL colleagues 25 Mon; am.Movement of string cavities to outside of clean room S1-G Webex Meeting Global Design Effort

  7. S1-Global Cryomodule Overview FNAL#1,#2 ACC011, AES004 DESY#1,#2 Z108, Z109 KEK#1,#2 MHI05, MHI06 KEK#3,#4 MHI07, MHI09 No connection No beam tube No gate-valve Closed by Blind Flange Pumping system Pumping system Gate-valve Gate-valve Down stream Up stream S1-G Webex Meeting Global Design Effort

  8. Clean Room at KEK-STF Clean room at STF Entrance HPR Air Shower Pass-box 5.4 m To cryomodule assembly area Water Shower 2.2 m Class 10 Class 1000 7 m 16.2 m He Leak Detector Pass-box Pumping System Pumping Line Between c-10 and c-1000 S1-G Webex Meeting Global Design Effort

  9. Request ....... Tug, Could you make your assembly plan in clean room at KEK from 15th (Fri.) to 21st (Thu.) for confirmation of our works ? S1-G Webex Meeting Global Design Effort