RSRDC. UNIT-IV, JAIPUR. ORGANISATION CHART OF RSRDC UNIT –IV, JAIPUR. Financial Work Load in Unit-IV, Jaipur. Rs. In Lacs. Important Works Completed during last 5 years. Corporate Bhawan, JAIPUR. Completion Cost – Rs. 10.00 Crs.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' RSRDC' - shae


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
rsrdc

RSRDC

UNIT-IV, JAIPUR

slide4

Important Works Completed during last 5 years

Corporate Bhawan, JAIPUR

Completion Cost – Rs. 10.00 Crs.

Inaugurated by Hon’ble Minister of Corporate Affairs on 22.02.09.

slide5

Important Works Completed during last 5 years

New Hospital Block,Chark Bhawan, JAIPUR

Completion Cost – Rs. 9.10 Crs.

Inaugurated by Hon’ble Chief Minister Rajasthan on 30.03.2008

slide6

Important Works Completed during last 5 years

Double storey Basement Parking, SMS hospital, JAIPUR

Completion Cost – Rs. 5.90 Crs.

Inaugurated by Hon’ble Chief Minister Rajasthan on 08.12.2007

slide7

Important Works Completed during last 5 years

12 nos LSQ at Shiprapath Thana, JAIPUR

Completion Cost – Rs. 70.24 lacs

slide8

POLICE HOUSING SCHEME

No. of Quarters : 112 Nos. LSQ

Total Cost : Rs. 654.00 lacs

Location : RPA Shastri Nagar

Date of Start : 01.03.08

Stipulated Date of Completion : 31.01.09

Expenditure till Date : 549.10 lacs

Likely Completion date : 15.12.09

Bottlenecks if any : Electric work & water supply from sousce to be connected

slide9

POLICE HOUSING SCHEME

No. of Quarters : 24 Nos. LSQ & 12 Nos USq

Total Cost : Rs. 288.76 lacs

Location : Banipark Thana campus, Jaipur

Date of Start : 19.09.08

Stipulated Date of Completion : 18.06.09

Expenditure till Date : 84.63 lacs

Likely Completion date : USQ will completed 31.12.09 12 nos LSQ 31.03.03

Bottlenecks if any : Land for 12 nos USQ allotted on 23.10.08 & order of 12 nos LSQ given on 03.06.09 and land for 12. LSQ still awaiting

slide10

POLICE HOUSING SCHEME

No. of Quarters : 196 Nos. LSQ

Total Cost : Rs.311.11 lacs

Location : Jail Building Karauli

Date of Start : 7.12.06

Stipulated Date of Completion : 06.11.07

Expenditure till Date : Rs. 247.79 lacs

Likely Completion date : 30.12.09

Bottlenecks if any : water supply line to be provided & water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli so revised estimate submitted for Rs. 428.00 lacs by PHED

slide11

POLICE HOUSING SCHEME

No. of Quarters : Adm Block, 100 men barracks, 4 nos LSQ & 2 nos USQ

Total Cost : Rs. 258.50 lacs

Location : Police line and Adm Block Karauli

Date of Start : 29.12.07

Stipulated Date of Completion : 28.11.08

Expenditure till Date : Rs. 158.50 lacs

Likely Completion date : 30.01.10

Bottlenecks if any : water supply shall be provided by PHED after laying 4.00 Km length pipe line from Karauli

slide12

POLICE HOUSING SCHEME

No. of Quarters : 12 nos USQ

Total Cost : Rs 119.57 lacs

Location : Mansarovar Thana, Jaipur

Date of Start : 07.07.08

Stipulated Date of Completion : 06.04.09

Expenditure till Date : Rs. 97.42 lacs

Likely Completion date : 15.12.09

Bottlenecks if any :

slide13

POLICE HOUSING SCHEME

No. of Quarters : 12 Nos. USQ

Total Cost : Rs. 120.58 lacs

Location : Pratapnagar Thana campus, Jaipur

Date of Start : 10.09.08

Stipulated Date of Completion : 09.06.09

Expenditure till Date : Rs. 103.51 lacs

Likely Completion date : 15.12.09

Bottlenecks if any :

name of work rob dausa
Name of Work : ROB Dausa

Total Cost : 10.00 Crores

Location : Dausa city

Date of Start : 2.09.08

Stipulated Date of Completion : 24.09.10

Expenditure till Date : 129.00 lacs

Likely Completion date : December -10

Bottlenecks if any : Estimate was Revised due to increasing number of viaduct as per demand of public representative. Revised estimate of Rs. 2020.00 lacs send to CE PWD vide Addl. Chief PWD Zone – I, Jaipur letter no 2330 dt 5.11.09

Note: Bar Chart for complete work shall be prepared after receiving of Revised A&F sanction

2 construction of rob gangapur
2. Construction of ROB Gangapur
  • Total Cost : 10.00 Crores
  • Location : Gangapur city
  • Date of Start : 1.04.08
  • Stipulated Date of Completion : 28.02.09
  • Expenditure till Date : 129.00 lacs
  • Likely Completion date : April -10
  • Bottlenecks if any : Estimate was Revised as bearing capacity is less to provide masonry retaining wall so RCC wall is proposed. Revised estimate of Rs. 1676.00 lacs send to CE PWD vide Addl. Chief PWD Zone – II, Jaipur letter no 2689 dt 27.10.09
  • Note: Bar Chart for complete work shall be prepared after receiving of Revised A&F sanction