NEPOOL Reliability Committee MPRP TCA Application Status CMP-09-TCA-01 March 17 th , 2009 Dave Conroy, Central Maine Power Company. MPRP CMP-09-TCA-01 Overview. CMP-09-TCA-01 Filed January 15, 2009 Total Project Estimated Costs: $1.55 B PTF: $1,510,365,000 Non-PTF: $39,635,000

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MPRP CMP-09-TCA-01 Overview' - semah


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
NEPOOL Reliability Committee MPRP TCA Application StatusCMP-09-TCA-01March 17th, 2009 Dave Conroy, Central Maine Power Company
mprp cmp 09 tca 01 overview
MPRPCMP-09-TCA-01 Overview
  • CMP-09-TCA-01 Filed January 15, 2009
  • Total Project Estimated Costs: $1.55 B
    • PTF: $1,510,365,000
    • Non-PTF: $39,635,000
  • Selection of Transmission Alternatives
    • N5: provides for more robust system performance and predicted load growth
    • S1: best performance/lowest cost
  • Underground Identified (≈ 6200’ of 115kV in Lewiston)
    • Replaces existing underground 34.5 kV transmission facilities in-kind in urban area
  • No Localized Costs in PTF
mprp presentations rc other meetings
MPRP PresentationsRC & Other Meetings
  • Planning Advisory Committee (PAC) Meetings:
    • Six meetings, 2007 & 2008(presentations posted at www.iso-ne.com/committees/comm_wkgrps/prtcpnts_comm/pac/mtrls/index.html)
  • ISO-TO System Planning Group Meetings:
    • Five meetings, 2007 & 2008
  • NEPOOL Reliability Committee Meetings:
    • MPRP PPAs CMP-08-T03 to T37 & X01, and NU-08-T08 to T10, June 17, 2008
    • MPRP Update, Upcoming PPA revisions and TCA, December 18, 2008
    • MPRP PPA Addendum Analyses & PPA revisions, January 26, 2009
    • MPRP TCA Application, January 26, 2009
  • TCA Stakeholder Meeting:
    • January 29, 2009
mprp stakeholder rc meeting iso information requests
MPRPStakeholder & RC Meeting & ISO Information Requests
  • ISO-NE Information Request:
    • Captured many comments from January RC & Stakeholder meetings
  • CMP Responses to questions:
    • Responses to ISO have been provided and posted (http://www.iso-ne.com/trans/pp_tca/req/mprp/index.html)
    • Requested N1/N5 presentation is being given today
  • Information Requests:
    • NSTAR & MMWEC responses have been provided to the RC and ISO
mprp cmp 09 tca 01 next steps
MPRPCMP-09-TCA-01 Next Steps
  • Awaiting ISO recommendation on construction of Section 254, Orrington-Coopers Mills (345 kV or 115 kV)
  • Seeking Reliability Committee recommendation vote at our next meeting, in April 2009