Bulk Water Supply in Limpopo. Integrating Infrastructure Delivery towards 2030 Summit Peter Mokaba Stadium 5 and 6 October 2010 A.M. Matukane. Contents. Growth Points Water Resources - Dams, Transfers, Ground water ORWRDP, MCWAP, GLEWAP, LRGWS

sara-glenn
Download Presentation

Bulk Water Supply in Limpopo

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bulk Water Supply in Limpopo Integrating Infrastructure Delivery towards 2030 Summit Peter Mokaba Stadium 5 and 6 October 2010 A.M. Matukane

  2. Contents • Growth Points • Water Resources - Dams, Transfers, Ground water • ORWRDP, MCWAP, GLEWAP, LRGWS - Description, Purpose, Map, Schedule, Risks and Mitigation • Regional Bulk Infrastructure Grant (RBIG) • Funding • Challenges

  3. Growth Points Polokwane Elias Motswaledi Makhado Lephalale Greater Tubatse Greater Tzaneen Growth Points Phalaborwa Thabazimbi Mogalakwena Marble Hall Musina Lepelle Nkumpi Bulk Water Supply in Limpopo

  4. Bulk Water Supply in Limpopo • The growth points in red are, apart from existing supplies, currently not addressed by either Implementation Ready Studies (IRS) or by constructing of a water resource/services project. • The other growth points are covered with an IRS or a phase of a regional bulk water project is under construction to alleviate the water problem • The water resources and transfer schemes are to support the development of the different growth points in the province.

  5. Bulk Water Supply in Limpopo All Growth Points must have water supply schemes: • A water resource – surface and/or groundwater • A water treatment plant • Pump stations • Regional Bulk – from source to and including bulk reservoir • Internal Bulk– from bulk reservoir outlet to reticulation connection • Reticulation– from internal bulk end to household meter

  6. Bulk Water Supply in Limpopo DWA has constructed many major dams in Limpopo in the past which supply water to people and other users, namely: • Nzhelele, Vondo, Damani, Lupepe-Nwanedi in Vhembe • Middle Letaba, Ebenezer, Tzaneen, Thabina, Tours, Blydepoort in Mopani • Mokolo, Doorndraai, Glen Alpine in Waterberg • Houtrivier, Chuene, Molepo in Capricorn • Vergelegen, Nkadimeng, Piet Gouws, Flag Boshielo in Sekhukhune

  7. Bulk Water Supply in Limpopo DWA is developing the major dams in Limpopo: • Inyaka (now in Mpumalanga) • Nandoni in Vhembe District • Flag Boshielo Raising, and • De Hoop in Sekhukhune District- construction 50% completed • Nwamitwa in Mopani District in planning • Possible dam in Olifants river under investigation

  8. Bulk Water Supply in Limpopo DWA is planning and developing major water transfer schemes in Limpopo from: • Inyaka (now in Mpumalanga) to Acornhoek • Nandoni in Vhembe District to Makhado, Matoks, Giyani, etc • Flag Boshielo to Pruissen at Mokopane • De Hoop in Sekhukhune District to Burgersfort, Tubatse, Lebowakgomo and Polokwane (ORWRDP) • Crocodile river to Lephalale (MCWAP) • Groblersdal to Moutse West

  9. Major Schemes • Olifants River Water Resources Development Project (ORWRDP) • Mokolo & Crocodile Water Augmentation Project (MCWAP) • Groot Letaba Water Augmentation Project (GLeWAP) • Luvuvhu River Government Water Scheme (LRGWS) – Nandoni Distribution Scheme • Water Services Bulk Water Supply in Limpopo

  10. 88m high De Hoop Dam (R3 075 million) on Steelpoort River– Implementation by DWA • Extensive bulk distribution systems (pump stations, balancing dams and pipelines) from De Hoop and Flag Boshielo Dams (R12 981 million) • Implementation by TCTA • Primary water supply in Middle Olifants River catchment area – Regional Bulk and Reticulation (R6 812 million) • Industrial water for mining on eastern limb of Bushveld Igneouscomplex 1. ORWRDP PHASE 2: DESCRIPTION & PURPOSE

  11. 1. ORWRDP (DE HOOP)REGIONAL BULK AND PRIMARY RETICULATION TO HOUSEHOLDFEASIBILITY STUDIES

  12. 1. ORWRDP PHASE 2: SCHEDULE (Subject to availability of funding) • 2A: June 2007 – Mar 2013 • 2B: Jul 2011 – Dec 2013 • 2C: Jul 2011 – June 2013 (Steel Bridge: July 2012) • 2D: Jul 2011 – June 2013 • 2E: April 2012 – March 2014 • 2F: April 2012 – March 2014 • 2G: April 2012 – March 2014 • 2H: Incorporated by March 2013

  13. 1. ORWRDP PHASE 2: PROJECT RISKS & MITIGATION • Level of commitment by mines and municipalities due to effects of ongoing global recession • High social demands • Affordability • High cost of scheme • Reliance on electricity for pumping • Alignment of completion of water resources & services infrastructure • Implement GWW with government funding • Implement WC & DM • Government funding • Step wise implementation within funding constraints • Align with Eskom’s developments • Aligned planning and water supply agreements

  14. Augmented water supply in the Lephalale area to meet the water requirements of the Medupi Power Station, and the future water requirements related to the expected growth in the Lephalale Municipality • Industrial water for possible CTL plant by Sasol • Phase 1 (R2 059 million) includes a new pump station at Mokolo Dam and pipeline to Medupi and Matimba Power Station, Exxaro mine and Lephalale town • Sub-phase 2A (R13 455 million): Abstraction works at Vlieëpoort and BDS to Steenbokpan and Lephalale areas • Sub-phase 2B (R1 590 million): Duplication of BDS • Social/Commercial portion on/off-budget • TCTA implementing agent • Regional Bulk and Reticulation (R 330 million) 2. MCWAP: DESCRIPTION & PURPOSE

  15. 2. MCWAP: SCHEDULE (Subject to environmental authorisation and Integrated Resource Plan (IRP) for electricity) • MCWAP-1: July 2011 – July 2013 • MCWAP-2A: Jan 2013 – Dec 2016 • MCWAP-2B and further phases: Depends on IRP and investment decisions by the private sector and other stakeholders

  16. 2. MCWAP-1 AND 2A: PROJECT RISKS & MITIGATION • Likelihood of appeals against environmental authorisation high • Very tight construction programme • Affordability of water by social users • Delayed IRP for electricity • High dependence on single resource, i.e. Mokolo Dam • Concerted efforts to deal swiftly with possible appeals • Efficient implementation strategies and contract management • Government funding • Co-operative governance • Investigate and implement additional and alternatives sources

  17. 3. GLeWAP: DESCRIPTION & PURPOSE • 36m high Nwamitwa Dam (R1 262 million) on Groot Letaba River – Implementation by DWA • 3m raising of Tzaneen Dam (R84 million) • Regional Bulk Water supply (R410 million) • Provide primary water requirements in Mopani District • To implement the preliminary Reserve in compliance with the National Water Act • To stabilise the assurance of supply to the existing irrigation farming • To improve water availability for the establishment of resource-poor irrigation farmers

  18. 3. GLeWAP: SCHEDULE (Subject to environmental authorisation and funding) • Tzaneen Dam Raising: 2013/14 • Nwamitwa Dam: 2016/17 • Regional Bulk: 2015/2016

  19. 3. GLeWAP: PROJECT RISKS & MITIGATION

  20. 4. LRGWS – Nandoni Distribution Scheme: Description & Purpose • The Nandoni Dam and Distribution scheme forms part of the larger Luvhuvhu River Government Water Scheme (LGWS) which also includes the Xikundu scheme • The project was initiated to provide potable water to the area between Thohoyandou and Makhado after the completion of the Nandoni Dam • The Nandoni Distribution projects were started in 2005 in conjunction with the Nandoni WTW after completion of the Nandoni Dam and includes: • 3 bulk pipelines takes water from Nandoni WTW to various reservoirs • NR6 and NN20B pipelines takes water in a northerly direction • 3 bulk pipelines takes water from Nandoni WTW to various reservoirs • NR5 pipeline takes water in a southern and western direction • Estimated cost for the completion Nandoni Distribution Scheme is R701 million

  21. 4. LRGWS: SCHEDULE • DWA approved the accelerated plan to complete the Nandoni Distribution Scheme’s bulk water pipelines up to the Valdezia Reservoir • Tender for PSPs to redesign the bulk water pipelines did close • Water delivery dates are as follows: • Thohoyandou CBD (via NR6 Reservoir and Rising Main) by October 2011 • Mavambe to Gumbani and Mudabula (via Mavambe to Gumbani Rising Main, Gumbani Reservoir and Pump Station). Water was already being delivered as from 17 June 2010 Greater Vuwani Area(Vuwani (NR7) Reservoir and Rising Main) by August 2012 • Valdezia Area (Valdezia Reservoir and Rising Main) by November 2012 • Mushiri, Mahagala and Lambani (Lambani Gravity Main) by October 2011 • Peri-urban areas east of Thohoyandou (NN20B Reservoir and Rising Main) by October 2011 • The water from the bulk distribution systems will feed into the existing local reticulation systems

  22. 4. LRGWS: PROJECT RISKS & MITIGATION

  23. Bulk Water Supply in Limpopo - RBIG

  24. Bulk Water Supply in Limpopo - RBIG

  25. Bulk Water Supply in Limpopo - RBIG • In addition to the projects being implemented, Table 2 illustrates projects at feasibility, or implementation ready study stage that were funded through the RBIG.

  26. Bulk Water Supply in Limpopo - RBIG

  27. Bulk Water Supply in Limpopo - RBIG

  28. Bulk Water Supply in Limpopo FUNDING • The dams are funded by National Treasury • Funds not so easily available for RBIG and Reticulation through MIG Example: • De Hoop is funded at R3 billion by National Treasury. • Bulk Distribution and reticulation to Households require R20 billion. • R1.2 billion is available from 2007 to 2013 through RBIG and MIG. • Shortfall of R18.8 billion is needed to serve 2 million people and mining. • Mines and Municipalities not in a position to sign off take agreements with DWA.

  29. Bulk Water Supply in Limpopo Example: • RBIG is funding a pipe line from Steelbridge to Jane Furse – 70% completed • Sekhukhune DM with MIG is on tender for WTW at Steelbridge and 10 Megaliter reservoir at Jane Furse for completion July 2012. • DWA has to do Phase 2C pipe from De Hoop Dam to Steelbridge for completion July 2012 depending on funding from National Treasury.

  30. Life cycle planningCost of the Business Planning Design Procure Construct Operate Maintain Refurb. Typical % of Total Cost over the Life of Water Supply Infrastructure 0,2% 2% 17% 44% 37% Financing Cost Based on actual local government case study (Paul le Roux)

  31. Limpopo Picture

  32. NeedsClassification/Definition – Water Services Water services Programme O&M needs Infrastructure needs Resource needs Upgrade Management Refurbishment Demand management Extension Community with no water services at all Local source development Bulk Infrastructure Illegal settlement Housing Programme Regional Bulk Interim Formal rural Housing Program Water resource development Backyard dwelling Internal Bulk Shared services Sewerage works Purification plants Permanent

  33. NeedsClassification/Definition - Sanitation Sanitation services programme O&M needs Infrastructure needs Existing Services that needs to be replaced Basic but not appropriate Management Refurbishment RDP – Pit/less than VIP Buckets Households with no sanitation services at all Other Other Programmes Illegal settlement Housing Programme Other Programmes Interim Formal rural Housing Program Health Sanitation needs Water resource development Backyard dwelling Schools Sanitation needs Shared services Permanent

  34. Backlog on Water: Households Priority (Infrastructure Status) Priority Adequate 0 No Water Services 1 Inadequate Infrastructure: Need Extensions 2 Inadequate Infrastructure: Need Upgrade 3 Inadequate Resources 4 Inadequate Management: O & M 5 Inadequate Management: Refurbishment 6 Inadequate Housing: Interim 7 Inadequate Housing: Permanent 8

  35. LIMPOPO WATER CHALLENGES EQUITABLE SHARES Currently R5 / kiloliter (1000 liters) ORWRDP at Nebo estimated R25 / kiloliter (1000 liters) 85% indigents to get 6 kiloliter free 200 000 households (4 people / hh) x 6kl x 12months x R20 = R288 mil per year

  36. STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND CHALLENGES • Total Water Business – Industry, Agriculture, Tourism and People • Single Purpose Dams • Water Services Provider – Cross Border Issues • WSDP requirements – Water Resource Planning & Internal Strategic Perspective • Priorities of backlogs • Eradicate per priority • Water Resource shortfall (De Hoop) • Funding shortfall – RBIG, MIG, ACIP • Water Services Reference Framework - MIG Projects outstanding • Redesign EQUITTABLE SHARE formula

  37. STRATEGIC TARGETS / BACKLOG ERADICATION PROGRESS AND CHALLENGES Cont….. • Materials availability • Manpower • Inexperienced PSPs and Contractors • Supply Chain • Not enough resources to support Population Growth • Population development require higher water needs

  38. THANK YOU • Bernie Badenhorst • badenhb@dwaf.gov.za • Tel 015-2901218 • Cell 083 627 5912 • c\:My Documents\Dept Premier\Premier’s Intergovernmental Forum 2010-10-06