Edmonton s rdf facility concept to implementation
This presentation is the property of its rightful owner.
Sponsored Links
1 / 12

Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION PowerPoint PPT Presentation


  • 119 Views
  • Uploaded on
  • Presentation posted in: General

Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION. SWANA Northern Lights Conference, Edmonton, AB – June 20, 2013 Lena Aitken, Project Engineer, City of Edmonton Uwe Eschenhorst, Project Manager, Vecoplan LLC. Outline. History of Edmonton’s journey to Refuse Derived Fuel (RDF) production.

Download Presentation

Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Edmonton s rdf facility concept to implementation

Edmonton’s RDF Facility – CONCEPT to IMPLEMENTATION

SWANA Northern Lights Conference, Edmonton, AB – June 20, 2013

Lena Aitken, Project Engineer, City of Edmonton

Uwe Eschenhorst, Project Manager, Vecoplan LLC


Outline

Outline

  • History of Edmonton’s journey to Refuse Derived Fuel (RDF) production.

  • RDF – what is it?

  • RDF Project – from concept to final design

  • Welcome Vecoplan!

    • Major Equipment Supplier

    • Design Build Construction Management Services


History

History

  • Cloverbar Landfill is getting full!

    • 2009 was estimated closure date

    • Starting premise – there IS a better solution to landfilling

  • City already had very established recycling and composting programs, currently diverting 60% of the waste

    • Looking to process the remaining 75,000 tonnes/yr of Composting residuals and 5,000 tonnes/yr of MRF residuals.

  • Specific targets include:

    • Increase Edmonton’s landfill diversion rate from 60% to 90%

    • Reduce Edmonton’s need for landfilling, without going to traditional combustion systems.


15 years of development

2010

15 years of development

1995


Rdf what is it

IPTF

Biofuels Facility

RDF – What is it?

  • RDF is the feedstock for the future biofuels facility


Iptf functions and phasing

March 2010

Pre-Processing Area

Transfer Station

August 2009

IPTF Functions and Phasing

November 2012

Phase 2

Phase 3

RDF Facility

Phase 1


Rdf what is it1

Transfer Station

MSW

Organics to ECF

RDF to Biofuels

RDF Facility

Pre-process

Area

- MRF Residuals

- ECF Residuals

- Wood Waste

RDF – What is it?

  • Produced in the 3rd Phase of the Integrated Process and Transfer Facility (IPTF)

    • Sort out the most suitable material from the trash and residuals.

    • Process it to achieve homogenous, quality, and uniform material.


Rdf project concept to design

RDF Project – Concept to Design

Considerations along the way….

  • Low speed shreddervs. High speed shredder

    • Separate explosion proof building required to house the high speed shredders.

  • Equipment Supply & Design Build Construction Management vs. Design–Bid–Build

    • Equipment manufacturing firm designs and supplies equipment systems with demonstrated performance.

    • Performance guarantee for the production of RDF.


Rdf concept in the beginning

RDF Concept in the Beginning

In-Feed

Primary

Shredding

Screening

Heavies

Removal

Fines Bunker

Heavies Bunker

Ferrous

Removal

Non-Ferrous

Removal

‘RDF Block Diagram’ that was used in the Request For Proposal

Ferrous Bunker

Non-Ferrous

Bunker

Secondary

Shredding

RDF

Conveying


Rdf project milestones

RDF Project Milestones


Final rdf design

Final RDF Design


Welcome vecoplan

Welcome Vecoplan!

  • Major Equipment Supplier

  • Design Build Construction Management Services for the IPTF Phase 3 (RDF) Project

  • Project Manager: Uwe Eschenhorst


  • Login