NCSX Engineers at IPP Department Device Assembly

NCSX Engineers at IPP Department Device Assembly. First I will introduce my self: Name: K-H. Oelgemöller, Dipl.-Ing. Age: 48 Years

sage
Download Presentation

NCSX Engineers at IPP Department Device Assembly

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NCSX Engineers at IPP Department Device Assembly NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  2. First I will introduce my self: Name: K-H. Oelgemöller, Dipl.-Ing. Age: 48 Years Position: Head Device Assembly Experience: Planning, Engineering and Assembly Parts of Refinery-, Power- and Steel-Plants In Project W7-X: since June 2004 NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  3. All projects are limited to the same borderlines: 1. Time 2. Money 3. Quality To ensure the finishing the Project W7-X within the approved limits we have installed the following Structure in “Device Assembly” NCSX Engineers in IPP, 2007.10.11

  4. Process-/ Work- planning • 1.1 Every Monday we discuss the up-dated 4-week-time-schedule with all involved people. We present the milestones for the required parts or actions, 4-weeks in future. The responsible officers has to confirm the delivery date of their parts or actions. NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  5. 1.2 Out of the confirmed 4-week-time-schedule we generate every Thursday the detailed Week-Planning (Manpower and Equipment) for the next week. NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  6. Assembly • On base of the Process-/ Work- planning and the “QAAP” ( Quality Assurance Assembly Plan, (detailed work break down structure)) the responsible crew is doing and controlling the work packages. NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  7. For your overview this slide shows the Organisation diagram of Assembly with their Sub-divisions. One of them “Device Assembly” ASSEMBLY L. Wegener with its groups. Secretary H. Nothnagel ONE-SITE CO-ORDINATION S. Gojdka DEVICE ASSEMBLY K.H. Oelgemöller * PERIPHERY R. Krampitz ASSEMBLY TECHNOLOGY F. Hurd* Process planning, Scheduling Recource planning, Documentation Hübschmann, Pasyutina, Schwarzkopf, Wiegand Storage/Magazine Consumables Bormann*, Steffen* Procurements Pasyutina Metrology Bräuer, Endler, Hillmann*, E. Lorenz, Junge, J. Müller, Poncet*, Radau, Siche Welding ControlHolluba*; Lahr Shift Manager Modrow Mounting stand leader Domscheit, Domscheit, Jassmann Management of component preparation Bau*, Günther, Höchel, Ihrke*, Jung, Neuner*, Raatz*, Reinke, Schinkel Service Nankemann Assembly Anders*, Bertram*, Bulgrin*, Goericke*, Jacobs*, Klagge*, Kullok, Kuse*, Langer*, Spreeberg*, Stolpe*, Terkowski, Wulf*, Ziemann* Vacuum Technology Ahmels, Braun, Dutz, Grote, Kuck, Rademann, W. Schneider, Schweitzer, Volzke Further external not named manpower *person assigned from other divisions or External NCSX Engineers in IPP 11.10.2007 – 12.10.2007

  8. In answering the question, “What is my Job in the Assembly Wendelstein W7-X”? Equal a soccer-team: I’m the “trainer” NCSX Engineers in IPP, 2007.10.11

  9. Thank you! NCSX Engineers in IPP, 2007.10.11

  10. 1.7 Work packages: 1. Component preparation 1.1. Coils, 80 days additional work out of changes and Collisions 1.2 Plasma Vessel, Instrumentation, Cooling- pipe work, Multi-Layer isolation 1.3. Support-Structure, 20 days additional work out of changes and Collisions Instrumentation. 2. Mounting Stand 2.1 MST IA / IB Half-Modul-Assembly 2.2 MST II Modul-Assembly 2.3 MST III-IVa-IV Final Modul Assembly 2.4 MST V Port Assembly In all Mounting Stands will be worked in a 2 shift system (06:00 am to 02:25 pm; 02:00 pm to 10:25 pm). The overlap is to discuss the work packages are done and must be done. Also problems. At the overlap always a member of the Planning department is involved. NCSX Engineers in IPP, 2007.10.11

  11. Shift organization: NCSX Engineers in IPP, 2007.10.11