An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Global Supplier Quality ManualPPAP Requirements

  2. What is PPAP? • Production Part Approval Process (PPAP) • The purpose of PPAP is to determine if all customer engineering design record and specification requirements are properly understood by the Suppliers and that the manufacturing process has the capability to produce product consistently meeting these requirements during an actual production run at the quoted production rates.

  3. Global Supplier Quality Manual: PPAP Requirements

  4. AIAG PPAP Oshkosh Corporation – PPAP P500 Oshkosh PPAP Level Definitions • Level 1 PPAP: • One page document that “warrants” the part meets the design intent, know as a Part Submission Warrant. • Level 2 PPAP: • Level 1 Warrant • Dimensional reports • Material certifications • Performance test reports • Welding Standards • Surface Finish test reports • Incoming Inspection usually approves Level 2 PPAP’s • Level 3 PPAP • Includes Level 2 PPAP with additional process control documentation. • Process Flow Diagrams • PFMEA • Control Plans • Capability Studies • Supplier Quality Engineer Approves • Incoming Inspector still verifies all initial sample parts. Long Term Benefit FMTV - REQUIREMENT

  5. Defense Website - Example of PPAP Workbook http://osn.oshkoshcorp.com/ Click on: Production Part Approval Process (PPAP)

  6. PPAP Workbook – “Excel workbook”

  7. PPAP Workbook – Level 2 Requirements • Intro: • Type in Part / Supplier Information, this will be transferred throughout the workbook. • PSW Requirements: • This outlines the PPAP submission requirements. (Informational only) • Labeling: • This is the label to be used to Identify the PPAP sample part when shipped to OSK • PSW: • This documents the warrant that the Part Meets the design Intent • This will be used to communicate back to the supplier the acceptance or rejection of the PPAP • Dimensional: • This is used in conjunction with a “bubble print” to document the actual dimensions of the PPAP part. • Print Notes: • This is used to document all the remaining notes on print (Material Certs, Surface Finish, Performance Testing, Labeling, etc…) • Print Notes – Paint: • This is optional depending if there are Print Notes specifying paint / coating requirements. • Print Notes – Welding: • This is optional depending if there are Print Notes / Welding requirements specified.

  8. Intro “TAB” – PPAP Workbook 1. Part Information 2. Supplier Information Note: This information will Be transferred to all “like” fields In this PPAP Workbook. 1 2

  9. PPAP Submission Requirements 1 2 • Level 2 Submission is the • Default PPAP level. • 2. This is the list of what is • Required per submission level • (Level 1, 2, or 3)

  10. PPAP Parts Labeling Requirements 1 • All PPAP sample parts must • Be tagged with this label on the • Part and / or on the box. • 2. Document all the appropriate • Part / Supplier / PO information • On the label. 2

  11. PSW – Part Submission Warrant

  12. ISIR – Initial Sample Inspection Report 1 2 3 4 5 6 • Numbering Matches Drawing • “bubble print”. • 2. Specification and Tolerances • 3. Gage Used to measure item • 4. How many measured • 5. Actual Results • 6. Good or Bad • 7. Supplier sign off All dimensions on the print must be verified by the Supplier! 7

  13. EXAMPLE: ISIR – Initial Sample Inspection Report Example of ISIR Filled out.

  14. EXAMPLE: Bubble Print Bubble Print to Match Dimensional Layout (ISIR) Includes Notes! Material type surface finish performance part I.D.

  15. Print Notes (Material Certs, Performance Tests & Part Identification) 1 2 3 4 5 6 1. Numbering Matches Drawing “bubble print”. 2. Specification and Tolerances 3. Gage Used to measure item 4. How many measured 5. Actual Results 6. Good or Bad 7. Supplier sign off Note: This sheet to be used to document all Print Note requirements via the “bubble print” and reference any applicable Test report numbers in the PPAP Package. 7

  16. EXAMPLE: Print Notes (Material Certification) • Print Requirement • ASTM Chemical Requirement • ASTM Mechanical Requirement • PPAP document to outline • Requirement and actuals per the • Print and Industry standard (ASTM) 1 2 3 4

  17. EXAMPLE: Print Notes (Material Certification) • Use Chemical Weighted % from material cert. and transfer to print notes PPAP Page. • Mechanical Results to be transferred to print notes PPAP Page. • Signature on Cert. approving material 1 2 3

  18. Print Notes – Paint Testing 1. Verification Prime Coat: permeability, Adhesion, thickness Salt Spray, Ambient Cure Time & Oven Cure Time 2. Verification Prime Coat: permeability, Adhesion, thickness Salt Spray, Ambient Cure Time & Oven Cure Time 3. Document what print standard Industry Standard the part has been Painted to. 4. Supplier Sign Off 1 2 3 4

  19. Example: Print Notes – Paint Testing 1. Print Note Paint Note Requirement 2. Prime Coat Verification 3. Top Coat Verification 4. Document what print standard or Industry Standard the part has been Painted to. 2 3 1 4

  20. Welding specification 3 1 2 1. Document the Welding Specification / Weld Symbol From “bubble print”. 2. Document WPS / PQR (if not prequalified) 3. Document visual verification of weld size, Weld length, Weld Quantity. 4. Supplier Sign Off Note: WPS’s and PQR’s may be requested and must be provided upon request. 4

  21. Example: Welding specification 1. Document the Welding Specification / Weld Symbol From “bubble print”. 2. Document the Welding Specification /Weld Symbol from “bubble print”. 3. Document WPS / PQR (if not prequalified) 4. Document visual verification of weld size, Weld length, Weld Quantity. 5. Supplier Sign Off Note: WPS’s and PQR’s must be provided upon request. 4 2 3 1

  22. PPAP Workbook – Level 3 Requirements LEVEL 2 - PPAP • Same Requirements as Level 2 with the following additional requirements: • DFMEA • Design Failure Mode Effects Analysis is required if the Supplier is design responsibly • FLOW DIAGRAM • Process Flow diagram is required to outline and standardize the production process that is being approved. This should outline the entire process that is being used to manufacture the component & assembly. • PFMEA • Process failure Mode Effects Analysis is required to be conducted to understand all the potential failure modes and mitigate know failure modes. • CONTROL PLAN • The control plan is to be used to document and be used on the shop floor to monitor and control the standardized manufacturing process being approved. • TOOLING • This sheet is used to visually document any Oshkosh owned tooling. • CAPABILITY STUDY • This sheet is to be used to show evidence the production process is capable to meet the design intent. This is required when Critical Characteristics are identified on the print or other wise specified by Oshkosh Corporation. • Gage R&R • This sheet is to be used to show evidence that the measuring method used for the capability studies is repeatable and reproducible. . LEVEL 3 - PPAP

  23. DFMEA 1. Design Failure Mode Effects Analysis is required if the Supplier is design responsible Note: Utilize AIAG manuals as required. www.aiag.org

  24. Process Flow Diagram 1. Process Flow diagram is required to outline and standardize the production process that is being approved. This should outline the entire process that is being used to manufacture the component / assembly. Note: Utilize AIAG manuals as required. www.aiag.org

  25. PFMEA 1. Process failure Mode Effects Analysis is required to be conducted to understand all the potential failure modes and mitigate any know failure modes. Note: Utilize AIAG manuals as required. www.aiag.org

  26. Control Plan 1. The control plan is to be used to document and be used on the shop floor to monitor and control the standardized manufacturing process being approved. Note: Utilize AIAG manuals as required. www.aiag.org

  27. Tooling – Oshkosh Owned • This sheet is used to visually document any Oshkosh owned tooling. It is required to attach a picture of tooling as well as the tooling identification method.

  28. Capability Studies 1. This sheet is to be used to show evidence the production process is capable to meet the design intent. This is required when Critical Characteristics are identified on the print or other wise specified by Oshkosh Corporation. Note: Utilize AIAG Manuals as required. www.aiag.org

  29. Gage R&R 1. This sheet is to be used to show evidence that the measuring method used for the capability studies is repeatable and reproducible. Note: Utilize AIAG manuals as required. www.aiag.org

  30. PPAP Process Flow

  31. Defense: PPAP Submission / Notification Process Oshkosh Purchasing FTP Site Homepage Upload all PPAP’s to the FTP Site https://ftp.oshkoshcorp.com/thinclient/ Email Notification of Documents on FTP site Email Level 2 PPAP’s Notification to: PPAP@defense.oshkoshcorp.com Email Level 3 PPAP’s Notification to SQE’s email: Note: Do not email the PPAP’s load them to FTP Site due to ITAR regulations. 31 8/22/2014

  32. Defense: FTP Site Oshkosh Purchasing FTP Site Homepage: https://ftp.oshkoshcorp.com/thinclient/ 32 8/22/2014

  33. Defense: FTP Site – APQP Folder Supplier should load PPAP’s into APQP folder. Open APQP folder. 33 8/22/2014

  34. F&E: PPAP Submission / Notification Email PPAP Documents to: PPAP@piercemfg.com 34 8/22/2014

  35. Commercial: PPAP Submission / Notification Email PPAP Documents to: PPAP@McNeilusco.com 35 8/22/2014

  36. JLG: PPAP Submission / Notification Email PPAP Documents to: PPAP@jlg.com 36 8/22/2014