An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. July 01, 2013 All Experimenters’Meeting

  2. Shutdown 2012 - 2013 Machine Status: • NTF Treatments and Dosimetry as scheduled • Proton Source Commissioning and Studies • RFQ Injector Line (RIL) • Linac • Booster • Main Injector • Power Supply studies on weekends TeV & Muon Rings – Partially available for tours with approval and appropriate training

  3. MSS Bypass Project

  4. MSS Bypass Project – Impact Areas • Project Completion Date • July 17th – July 25th • A0 Parking Lot Work • TeV road closure at A1 (Tuesday, July 2nd and Wednesday, July 3rd from 0700-1530) • TeV road reduction at A1 (Thursday, June 20th for about 3 weeks during cable terminations) • Power off to A1, A2, & A3 (Daily for ~ 3weeks) • Pave parking lot on Tuesday, July 2nd

  5. MSS Bypass Project – Impact Areas Cont. • CHL • ~5 day outage/reduction (only house power available) • Monday, June 24ththrough Friday, June 28th • Two 5 minute power outages needed • Monday, June 24th @ 0730 – 0735 (Completed) • Friday, June 28th @ 0700 – 0705 (Completed) • Cable pulls and splices in PMH 210 • Meson • Two 15 minute outages one week apart • Monday, June 17th @ 0700 – 0715 (Completed) • Monday, June 24th@ 0700 – 0715 (Completed) • Monday, June 24th @ 0815-1215 (Bonus MCC-2 outage @ MS3) • Cable pulls and splices in PMH 110 • Impacts MCC, Holometer, MW9, all enclosures, systems, and buildings

  6. Kautz Road SubStation • Status • MI backfed from Master SubStation • Using Feeder 45 for MI conventional power which is normally T85 on KRS • We ordered 6+ new surge arrestors (4.7k each) from Hubbell and wait for delivery in 8-9 weeks • Schedule a ~1-2 day KRS outage (not really an outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87 • There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed

  7. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html