Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11. PowerPoint PPT Presentation


  • 142 Views
  • Uploaded on
  • Presentation posted in: General

ON GOING PROJECTS. Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11. DOUBLING. Items Announced in Budget 10-11. Item No. 116 ( XXIX) of Budget Speech Durg – Rajnandgaon 3 rd line ( 30.889 Km) STATUS Cost of project - ` 147.06 Crores.

Download Presentation

Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11.

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Slide1 l.jpg

ON GOING PROJECTS

  • Items Announced in Budget 10-11

  • Gauge Conversion in NGP Divn.

  • Targeted works 2010-11.


Doubling l.jpg

DOUBLING

Items Announced in Budget 10-11

  • Item No. 116 ( XXIX) of Budget Speech

  • Durg – Rajnandgaon 3rd line ( 30.889 Km)

    STATUS

  • Cost of project - `147.06 Crores.

  • Budget Grant - `10.00 Crores. for 2010-11

  • Detailed estimate sanctioned in Oct. 10.

Contd…


New gauge conversion works l.jpg

New Gauge Conversion works

  • Item No 115 (i) Budget speech

  • Chhindwara -Nainpur – Mandla Fort (182.25 Km)

    STATUS

  • Cost of project - ` 556.54 Crores.

  • Budget Grant for 10 - 11: ` 1.00 Crores.

  • Detailed part estimate of NIR - MFR for ` 145.8 Cr. Prepared.

Contd…


Completed gauge conversion project l.jpg

Completed Gauge Conversion Project

  • Item No 113 (x) of Budget speech

    • Gondia - Balaghat including MOIL siding (42+7 Km) section commissioned in year 2005

    • Balaghat - Katangi [46.8] - Section completed & commissioned on 7.05.2010

Contd…


New line project l.jpg

New line Project

  • Item No 111 of Budget speech

  • Mandir Hasaud - Naya Raipur (20.00 Km) sanctioned as material modification to Raipur – Titlagarh doubling of East Coast Railway

  • Cost of project - ` 77.32 Crores.

  • Budget Grant for 2010-11 – Nil

  • Part estimate for ` 28 Lakhs. for preliminary activities sanctioned by GM/SECR.

Contd…


Updating of socially desirable rail connectivity proposals l.jpg

Updating of Socially Desirable Rail Connectivity Proposals

  • Item No 102 of Budget speech (Sr. No.10)

  • Barwadih- Chirimiri / Ambikapur[182km]

  • RET Survey report submitted on 17.05.03 for ` 406.86 Crs. with ROR (-) 4.85%. Updating done on 16.2.09. with ROR (-) 9.05%. Board again desired for updating. Updated estimate under finance vetting..

Contd…


Updating of proposals lohardaga korba 326 km via dharmjaygarh pathalgaon l.jpg

Updating of proposalsLohardaga-Korba (326 Km.)(via Dharmjaygarh & Pathalgaon)

  • Item No 102 of Budget speech (Sl No. 63)

  • Report Submitted to Rly. Board in 2003.

  • Cost ` 621.67 crores & ROR (+) 07.25 %.

  • Updated estimate under calculation of ROR.

Contd…


Updating of proposals pendra road korba gevra rd 121 7 km via pasan sundargarh deepika l.jpg

Updating of proposalsPendra Road –Korba/Gevra Rd. (121.7 Km.)(via Pasan, Sundargarh & Deepika)

  • Item No 102 of Budget speech (Sl. No. 82)

  • PET survey sanctioned in 1996-97.

  • Report submitted to Board in 2003.

  • Cost ` 344.43 Crores & ROR (+)15.23%.

  • Updated estimate under finance vetting.

Contd…


Updating of proposals raigarh mand colliery to bhupdeopur 63 km with fly over l.jpg

Updating of proposalsRaigarh - Mand Colliery to Bhupdeopur(63 Km. with Fly over)

  • Item No 102 of Budget speech (Sl. No. 88)

  • PET survey sanctioned in 2008-09.

  • Report submitted to Railway Board in July -2009 at the cost of ` 310.64 Crores & ROR (+) 29.58%

  • Updated report submitted to Board in Aug. -10 at the cost of ` 344.20 crores and ROR (+) 26.33%

Contd…


Updating of proposals raipur jharsuguda 310 km via kharotapalan baloda bazar bhatgaon sarangarh l.jpg

Updating of proposalsRaipur – Jharsuguda (310 Km.)(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.)

  • Item No 102 of Budget speech (Sl. No. 89)

  • RET survey sanctioned in 1999-2000

  • Report submitted to Railway Board in Feb-2003.

  • Cost ` 971.96 crores & ROR (-) 20%.

  • Updating of abstract estimate is being done.

Contd…


Updating of proposals ramtek gotegaon 275 km via khawasa sioni dhuma l.jpg

Updating of proposals Ramtek – Gotegaon(275 Km.)(via Khawasa, Sioni & Dhuma)

  • Item No 102 of Budget speech (Sl. No. 92)

  • RET survey sanctioned in 1995.

  • Report submitted to Railway Board in April 1999.

  • Cost `. 528.21 crores & ROR (-) 11.50%

  • Updating in progress.

Contd…


Updating of proposals l.jpg

Updating of proposals

  • Item No 118 (i) of Budget speech

  • Wadsa - Desaiganj - Gadchiroli - 49.5 Km(Cost sharing)

  • RET survey sanctioned in Aug -1995.

  • Initial report submitted in July - 1998.

  • Updated report submitted in Aug - 2010.

  • Cost ` 232.40 crores & ROR without sharing (-) 3.88% & with 50% cost sharing by State Govt. ROR (-) 0.40%


Gauge conversion in ngp division l.jpg

Gauge conversion in NGP division


Slide14 l.jpg

Planning of N.G. conversion in NGP Divn.


Slide15 l.jpg

Contd.


Progress of major items jabalpur nainpur balaghat l.jpg

Progress of Major ItemsJabalpur – Nainpur - Balaghat


Progress of major items jabalpur sukarimangla l.jpg

Contd.

Progress of Major ItemsJabalpur - Sukarimangla


Progress of major items nagpur chhindwara l.jpg

Contd.

Progress of Major ItemsNagpur - Chhindwara


Slide19 l.jpg

Contd.


Targeted works 2010 11 l.jpg

Targeted works 2010-11


Slide21 l.jpg

Contd…


Slide22 l.jpg

Contd…


Slide23 l.jpg

Contd…


Slide24 l.jpg

Contd…


Slide25 l.jpg

PROGRESS OF QUARTERS


Slide26 l.jpg

Contd.


Slide27 l.jpg

THANK YOU


Slide34 l.jpg

WORKS COMPLETED IN

2009 -10 & 2010 -11 (PB)


Slide35 l.jpg

Contd.


Slide36 l.jpg

STATUS OF LAW BOOK WORKS


Slide37 l.jpg

Contd.


Slide38 l.jpg

Contd.


Slide39 l.jpg

WORK IN PROGRESS

In. Crs.

Remarks

ESP & IP approved. Slewing of main line and major OHE alterations completed. PF extension work completed except stone surfacing.


Slide40 l.jpg

Contd.

In. Crs.

Remarks

Existing relay room will be used. 100 % E/W, bridge work and ballast supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation out of 53 done & 28 mast erected, steel received. S & T progress - 80%. CRS sanction obtained.


Slide41 l.jpg

Contd.

In Crs.

Remarks

Work is planned in two stages.

Stage -I – Up loop and one Dn loop work at KDTR.

Stage – II – 2nd Dn loop.

Connection for all 3 loops planned for simultaneous commissioning to avoid redundant works. CRS sanction awaited. E/W – 95%, Building & Bridge work – 100%, S & T – 95%, Track Linking in progress.


Slide42 l.jpg

Contd.

In. Crs.

  • Completed work

  • Formation, track, extension of culvert.

  • Shed (40x12) 140 ton for crane.

  • S & T goomty (3mx3m) & Inspection pit.

  • Balance work in progress

  • Service building for C&W staff – Upto plinth level completed.

  • SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be

    manned & relocation of point.

  • CRS sanction for D cabin submitted on 20.09.10


Slide43 l.jpg

Contd.

In. Crs.

  • Goods platform work nearly completed.

  • Placement/withdrawal of trains being done from BSP end.

  • Connectivity from NGP end should be done along with 3rd line bet.

    Durg – Rajnandgaon to avoid repeated NI and yard modification.

  • Renovation of existing shed for labour rest room and merchant room

    in progress.


Slide44 l.jpg

In. Crs.

Contd.

Full quantity of cable procured. Electrical work completed. MDH-URK commissioned on 28.7.09.Tender awarded for Dadhapara - Belha section. Work in progress.


Slide45 l.jpg

Contd.

In. Crs.

Remarks

Work proposed for dropping.


Slide46 l.jpg

Contd.

In. Crs.

Remarks

ESP Approved. Cost of work is exceeding the abstract estimate substantially. Detailed estimate is under revision.


Slide47 l.jpg

Contd.

In. Crs.

Remarks

Scope of work revised. ESP approved. Estimate sanctioned. Civil tender finalised recently. OHE tender finalised. S & T tender opened on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and under finalisation.


Slide48 l.jpg

Contd.

In. Crs.

Detailed estimated sanctioned. Tender awarded & work under progress. SWR’s pending in division.

TDC

Dadhapara -Belha - Oct-10

Jairamnagar - Latia - Nov-10

Gatora - Jairamnagr - Nov-10

BSP - Gatora - Dec-10


Slide49 l.jpg

Contd.

In. Crs.

Remarks

Land acquisition required at JSG end land plan submitted. Revised ESP approved. Land acquisition proceedings stalled. Work to be truncated to avoid land acquisition and revised ESP prepared & under finalisation.


Slide50 l.jpg

Contd.

In. Crs.

S & T and OHE tender finalised. E/W in progress. One high tension tower in the alignment is yet to be dismantled by CSEB.


Slide51 l.jpg

Contd.

In. Crs.

Remarks:-

Scope of work finalised recently by the division. Detailed estimate sanctioned during July- 10. ESP under finalisation.


Slide52 l.jpg

Contd.

In. Crs.

Remarks:-

ESP approved. Work to be executed with 3rd line.


Slide53 l.jpg

Contd.

In. Crs.

Remarks:-

ESP approved. Work to be executed with 3rd line.


Slide54 l.jpg

Contd.

In. Crs.

Remarks:-

Site details collected. ESP approved. Estimate vetted. Tender to be floated.


Slide55 l.jpg

Contd.

In. Crs.

Remarks:-

Heavy cost over runs are noticed in S & T portion of the estimate. Scope of work reviewed and referred to Board.


Slide56 l.jpg

In. Crs.

Remarks:-

ESP approved. Estimate under vetting.


Jabalpur nainpur 113 5 km non electrified section l.jpg

JABALPUR – NAINPUR (113.5 km.) (Non – Electrified section)

  • This part of the project is falling in Seoni, Mandla & Jabalpur distt. of MP.

  • Total land acquisition is 344 hec. (Pvt. 261 + Govt. 50 + Forest land 33 hec.)

  • 25 hect of Pvt./Govt. & 30 hect of forest land is balance for acquisition (Seoni district).

  • One important bridge over Narmada (18 x 30.5 m PSC box) completed.


Slide58 l.jpg

Contd.

  • There are three major detours (Pindarai - Ghansore 20 km, Vinayaki - Shikara 9 km, and Bargi - Kachpura 20.7 km), two minor detours in Shikara – Sukari plus mini diversions at major bridge approaches. Total length of detour alignment is 62 km. Earth Work is progressing in 56 Km length .


Gondia jabalpur gauge conversion incl balaghat katangi 275 20 km l.jpg

Gondia – Jabalpur gauge conversion incl. Balaghat – Katangi (275.20 Km.)

Gondia – Balaghat section including MOIL siding (42+7 Km) already commissioned.

Balaghat–Katangi section 46.8 km completed. CRS after inspection on 23.02.2010. & section commissioned on 07.05.10


Slide61 l.jpg

Contd.

  • Track Linking – 125 Km. Indent placed for all P. way materials. 12000 Sleepers transported .

  • JBP-Gwarighat (20km) can be opened in June-2011. Thus abandoning NG alignment from JBP – Gwarighat (9.2 km).

  • TDC


Slide62 l.jpg

BALAGHAT – NAINPUR (75.41 km. non – electrified section)

I- Section falling in distt. of Balaghat & Mandla in MP state.

II-Acquisition of land

Pvt. & Govt land (50.56 hect.) – nearly 100%.

Mandla distt- 100% (20.60 hect.)

Balaghat distt(75.47 hect) case pending with MOEF since Feb-09 .


Contd l.jpg

  • Progress of Major Items as under.

Contd.


Slide64 l.jpg

Contd.

TDC - 30 months after possession of forest land i. e. Oct - 2012.Full 75 Km will be opened in one stretch.


Mandala fort nainpur chhindwara 182 25 km non electrified l.jpg

MANDALA FORT- NAINPUR - CHHINDWARA (182.25 Km. Non-Electrified)

  • The project is being tackled in two phases i. e. (i) Mandla Fort - Nainpur (42.25 Km.) (ii) Nainpur - Chhindwara (140 Km.)

  • Final location survey of Mandla Fort – Chhindwara completed. Part detailed estimate sent to Rly. Board in May-10.

  • Tender floated for Major Bridges on 04.10.10.

  • TDC – Dec-2012


Nainpur chhindwara 140 km non electrified l.jpg

Contd..

NAINPUR - CHHINDWARA (140 Km. Non-Electrified)

  • Final location completed 50 Km. and balance is under progress.

  • Detailed estimate will be submitted to Rly. Board by April – 2011.

  • TDC


Chhindwara nagpur gc 149 52 km non electrified l.jpg

CHHINDWARA – NAGPUR GC (149.52 Km. Non-Electrified)

  • The project is covering 53 Km. in Nagpur distt. of Maharastra & 96.52 km. in Chhindwara distt. of M.P.

  • Total land required 328 hec. (128 hec. forest & 200 hect. private/Govt. land. 80% in M. P. & 20% in Maharastra.

  • 2nd stage clearance of MOEF for forest land received on 30.9.09. & trees cutting in progress.


Slide68 l.jpg

Contd.


Slide69 l.jpg

Contd.

  • Tender for 2 tunnels of 750 m & 150 m long opened on 22.03.2010.

  • Tender for 3 viaducts are invited.


Slide70 l.jpg

All indents for span of 12.2 m & 18.3 m placed on CEWS/Manmad. 30.5 m spans are being manufactured by agency. Indents for 45.73 m are being placed with modified 25 tonnes loading on CEWS/Manmad.

  • Ballast - Total requirement 3.36 lac. cum. Tender finalised for the stretch falling in Maharastra State of 0.84Lac cum and 0.85cum for MP.state and progressed 0.58 lac cum.

  • TDC