1 / 116

PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT 2015/16 ANNUAL REPORT

PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT 2015/16 ANNUAL REPORT 14 March 2017. CONTENT. 2015/16 Annual Financial Statement Summary of 2015/16 Annual Performance Report Performance Highlights for 2015/16 Financial Year Service D elivery Environment

rgilyard
Download Presentation

PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT 2015/16 ANNUAL REPORT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRESENTATION TO THE SELECT COMMITTEE ON ECONOMIC AND BUSINESS DEVELOPMENT 2015/16 ANNUAL REPORT 14 March 2017

  2. CONTENT • 2015/16 Annual Financial Statement • Summary of 2015/16 Annual Performance Report • Performance Highlights for 2015/16 Financial Year • Service Delivery Environment • Organizational Environment • Key Policy development and legislative changes • Government Priority Outcomes and SOOGs • Performance Challenges

  3. 2015/16 ANNUAL FINANCIAL STATEMENTS 4

  4. INTRODUCTION • AFS Preparation • The financial statements has been prepared on the modified cash basis as required in terms of the Departmental Financial Reporting Framework Guide issued by National Treasury. • Challenges • Key vacancies during year end audit period • Excessive study leave during the year end process • NECSA Liability • Verification of projects activities • Slow moving projects • Payment of suppliers within 30 days • Targets not being achieved 5

  5. Financial PERFORMANCE Statement of Financial Performance as at 31 March 2016 6

  6. FINANCIAL PERFORMANCE FOR 2015/16

  7. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • Analysis of financial performance: • By 31 March 2016, the Department had utilized R7.14 billion or 98.27% of its 2015/16 adjusted budget. • A budget balance of R125.50 million or 1.73% of the adjusted allocation. • The composition of the budget balance of R125.50 million is as follows: • Compensation of Employees :R 210 thousand • Goods & Services :R 2.29 million • Transfer Payments :R 123 million • Capital Assets :R 8 thousand • Financial Assets :R 1 thousand

  8. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) 9

  9. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) * Actual transfer on the statement of financial performance includes aid assistance of R185 537 10

  10. Financial PERFORMANCE Statement of Financial Position as at 31 March 2016 11

  11. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • Note: 11 Unauthorised Expenditure • The unauthorized expenditure of R14.86 million is due to an Infrastructure Grant transfer payments paid to the Mthonjaneni Municipality in May 2010. • The transfer was appropriated in the 2009/10 financial year, however the payment to the municipality was processed in March 2010, but only transferred in May 2010 due to the system rejection of the banking details. • A request for condonation has been submitted to National Treasury for consideration. Condonation was approved without funding. • The Department presented the matter to SCOPA on 12 November 2014 and is awaiting the committee’s decision. • No unauthorised expenditure was incurred in the 2015/16 financial year. 12

  12. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • The total amount of R110 276 million consists of : • - Cash receipts R110 188 million. • - Cash on hand R46 thousand. • - Cash with commercial banks (local) R42 thousand 13

  13. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • During 2015/16 Fruitless expenditure to the value of R12 thousand was identified. This amount was due to interest paid for a late payment of contributions to the Government Employees Pension Fund. • The matter was referred to labour relations for investigation as per the Departmental policy. • During 2014/15 Fruitless and wasteful expenditure amounting to R15 thousand was identified. The payment made was in respect of interest on international membership fees. 14

  14. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • The Department is a 100% shareholder in The South African Nuclear Corporation Limited (NECSA) and own 2 205 000 shares of R1 each. 15

  15. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) Disclosure Notes • During 2015/16 financial year irregular expenditure to the value of R678 thousand was identified. This amount was due to the non-compliance of the procurement process. • The matter was referred to labour relations for investigation as per the Departmental policy. • During 2014/15 irregular expenditure to the amount of R55 thousand was identified. This amount was due to non-compliance to procurement process 16

  16. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • The Department had a potential liability arising from the decontamination and decommissioning of past strategic nuclear facilities as per section 1 (xii) (a) of the Nuclear Energy Act, Act No. 46 of 1999. • NECSA then submitted to Cabinet, in 2004, through the former DME, a Nuclear Liabilities Management Plan of the total nuclear liability for the nuclear facilities on NECSA site at Phelindaba. This Plan was divided into three major stages as follows: 17

  17. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • Provision for disused past strategic nuclear facilities • Stage 1 -Decontamination and Decommission (D&D) and waste management of all disused strategic nuclear facilities • Stage 2 -D&D and waste management of all remaining (currently operating) nuclear facilities i.e. operational past nuclear facilities • Stage 3 - Disposal of long-lived and high level waste (including SAFARI-1 Spent Fuel) when an appropriate disposal facility for such waste becomes available. • The department carried the liability of the Stage 1 of the D& D liability for the strategic past disused – 2014/15 valued at R3.6 Billion. • There were on going disputes regarding the legal liability of the costs of decontamination and decommissioning of past strategic nuclear facilities. • To assist with concluding this long outstanding matter and to assist NECSA with the process of tabling their outstanding Annual Report, the department sought a legal opinion in this regard. • The legal opinion was sought to determine the legal liability and the funding responsibility thereof. • After a lengthy process with Senior Counsel, it was concluded that the legal liability should be carried by NECSA and the funding responsibility resides with the state. 18

  18. FINANCIAL PERFORMANCE FOR 2015/16 (Cont.) • Provision for disused past strategic nuclear facilities- (Cont.) • The legal opinion was shared with NECSA and AGSA – the information was used in concluding the 2014/15 and 2015/16 Annual Financial Statements of NECSA. • The legal opinion also gave clarity to the Decontamination and Decommissioning liability disclosed by DoE in their Annual Financial Statements. • This resulted in the liability being transferred from DoE Annual Financial Statements and disclosed by NECSA. • Extract - Legal Opinion Advocate MM Oosthuizen SC • “ In conclusion my opinion is therefor that NECSA carries the legal liability for the costs of the decontamination and decommissioning of certain so called ‘past strategic nuclear facilities’ licensed to and still in operation by NECSA - but that, subject to proper compliance with policy and procedure , the State and/or the Minister of Energy has a funding responsibility in this regard”. 19

  19. SUMMARY OF KEY AUDIT FINDINGS FOR 2015/16 • 1. Oversight • Non-compliance with SOC oversight framework • 2. AOPO (Audit of Predetermined Objectives) • Fourth quarter report of 2015/16 relating to IPPP was excluded from the of AoPO draft • 3. Commitments • Understatements of commitments • 4. Transfer payments • Non-compliance with DoRA: Quarterly reports not submitted within the required 45 days • 5. Procurement • Deviations not reported to National Treasury and AGSA within the required timelines • 6. Information Technology • Evidence for approval of the initial ICT plan for 2011/12 – 2015/16 could not be provided. • The engine monitoring report was not updated to show the current status. 20

  20. Audit outcomes AND FINDINGS for the last 5 years * The Department received an unqualified audit opinion for the year under review

  21. NON -FINACIAL PERFORMANCE INFORMATION 22

  22. INTRODUCTION DoE implements its Annual Performance Plan (APP) through six programmes; • Programme 1 – Administration, • Programme 2 – Energy Policy and Planning, • Programme 3 – Petroleum & Petroleum Products Regulation, • Programme 4 – Electrification & Energy Programme and Projects, • Programme 5 – Nuclear Energy and • Programme 6 – Clean Energy.

  23. SUMMARY2015-16 ANNUAL PERFORMANCE REPORT

  24. PERFORMANCE HIGHLIGHTS FOR THE_2015/16 FY • 20YLFMP was incorporated as part of IEP tabled at DGs Cluster in February 2016 • 75% of licence applications approved had at least 50% BEE Ownership. • National Electrification Master Plan was developed in 6 Provinces . • Municipalities electrified 72 399 additional households and Eskom electrified 158 613 ( including rollovers)TOTAL = 231 012. • 2 New bulk substations were built and 6 additional substations were upgraded. • A total of 1 956 site compliance inspections were conducted for the year against an annual target of 1 500. The target was exceeded by 456 inspections; • 1847 fuel samples were collected and analysed during the year; • 8 Nuclear safeguards inspections, 4 Nuclear Audits were conducted, and 4 Nuclear Security Inspections were conducted • 8 nuclear awareness events were conducted in the year due to interest from stakeholders on nuclear matters. • Municipalities have only achieved a verified savings of 0.6 TWh to date. • Draft National Biogas Strategy has been completed, however, the scope has been expanded to cover Biomass as well.

  25. PERFORMANCE HIGHLIGHTS FOR THE_2015/16 FY • In line with the national commitment to transition to a low carbon economy, and the Integrated Resource Plan (IRP), 17800 MW of the 2030 target are expected to be generated from renewable energy sources, with 5000 MW to be operational by 2019 and a further 2000 MW (i.e. combined 7000 MW) operational by 2020. • In order to adhere to these targets and the power invested in the Department of Energy, the following new capacity determinations have been made: • 13 225 MW of renewable energy (comprising of solar PV: 4725 MW, wind: 6 360 MW, CSP: 1200 MW, small hydro: 195MW, landfill gas: 25MW, biomass: 210 MW, biogas: 110 MW and the small scale renewable energy programme: 400 MW); • 2500 MW designated from coal-fired plants (excluding cross-border projects); • 1800 MW of cogeneration; • 3126 MW of gas-fired power plants; and • 2609 MW of imported hydro. • In the past 4 years, REI4P has successfully connected 43 REIPP to the grid, which has add an additional about 2 350 MW capacity to the national grid.

  26. PERFORMANCE HIGHLIGHTS FOR THE_2015/16 FY • The total projects costs invested in the Windows currently been announced is ZAR 192.6 billion. In this way a substantial portion of the investments have been structured and secured as local community equity. An individual community’s dividends earned will depend on the terms of each transaction corresponding with the relevant equity share. • To date all shareholding for local communities have been structured through the establishment of community trusts. For projects in BW1 to BW4 and 1S2, qualifying communities will receive R29.2 billion net income over the life of the projects which is 20 years. The R30.7 billion spent on BBBEE during construction for BW1 and BW2 already exceeded the R26.6 billion that had originally been anticipated by IPPs. • Even though BW3 projects have only just started construction, employment opportunities are 111 % of the planned numbers during the construction phase (i.e.19523 job years), with 23 projects still in construction and employing people. The number of employment opportunities should therefore continue to grow beyond original expectations. These IPPs been completed had planned to deliver 8451 job years during the construction phase, but achieved actually 14 334 new jobs. This is 70 % more than planned. • Department has procure private peaker stations to the capacity of about 1 000 MW that can be used when there are a larger demand than what the Eskom generators can produces. The plant in Eastern Cape was completed in September 2015 and can produce 330 MW, while the plant in Kwa-Zulu Natal, when completed by the end of 2016, can produce 630 MW. Total projects costs were ZAR 8 billion, while 210 permanent jobs and 6190 temporary jobs were created at both plants.

  27. INEP 2015/16 CONSOLIDATED INFORMATION

  28. INEP 2015/16 CONSOLIDATED INFORMATION

  29. INEP 2015/16 CONSOLIDATED INFORMATION

  30. CHALLENGES Infrastructure • The current bulk infrastructure is constraint and there is a challenge of connecting additional households.(eg. KZN and EC) • There is an urgent need for bulk infrastructure which takes multiple years to complete and hence to be reflected in households connections. Non-grid programme • Slow roll-out of non-grid connections due to internal practical short comings. • Current non-grid systems not addressing all basic electricity needs of customers – heating and cooking addressed by means of other sources. • Non-grid service providers struggle financially to survive due to small customer base and rural location. Funding and cost of connections • INEP budget for the 2016/17 financial year has been reduced by R240 million. • The budget cut has led to the reduction of targeted connection leading to universal access not being achieved as planned for 2025 but has to be extended to 2030. • Most of the projects to be implemented are in deep rural areas – connections costs have increased sharply and subsidy level have to be increased accordingly.

  31. CHALLENGES • Lack of resources to fast tract the amendment process of nuclear legislation. • Lack of resources to deal with the larger amount of authorisations applications been lodged with the Department. • Un-integrated regulatory control for nuclear and radiological (i.e. Group III and IV) activities – delayed decision making. • Challenges on issues around National Liason Officer's unapproved structure and delays in processing of fellowship's payments.

  32. INEP IN ADDRESSING THE CHALLENGES Municipalities • DoE focused oversight and monitoring role in key municipalities (listed) and in areas Eskom is not performing • DoE in close co-operation with MISA in order to address challenges in a combined effort regarding non-performing Municipalities, by for instance assist struggling Municipalities with Technical assistance by deploying Electrical Engineers. Eskom • INEP will continue with quarterly Eskom performance meetings, where performance, progress and challenges are discussed and escalated to management meeting. • Management meeting between DoE and Eskom to address challenges identified during quarterly performance meetings. • Weekly dashboard from Eskom provides update on the status of the programme. Funding • Ensure that programmed delivers against approved targets been set and in line with the overall master plan. • Actively focusing on cost cutting measures, but at the same time ensure that oversight and support are optimized.

  33. Strategy to overcome areas of under performance

  34. Strategy to overcome areas of under performance

  35. Strategy to overcome areas of under performance

  36. Strategy to overcome areas of under performance

  37. Strategy to overcome areas of under performance

  38. Strategy to overcome areas of under performance

  39. Strategy to overcome areas of under performance

  40. Strategy to overcome areas of under performance

  41. Strategy to overcome areas of under performance

  42. Strategy to overcome areas of under performance

  43. Strategy to overcome areas of under performance

  44. Strategy to overcome areas of under performance

  45. Strategy to overcome areas of under performance

  46. Service Delivery Environment Electricity and Electrification • The year under review was characterised by severe shortages in electricity supply resulting in load shedding in various parts of the country. In order to address these challenges, Cabinet adopted the five point plan as a blueprint to mitigate those challenges. The five point plan consisted of supply side option to encourage Eskom to improve the availability and reliability of the power stations, while increasing power capacity through Independent Power Producers (IPPs). Programmes that were largely earmarked under IPP programme related to the renewables, coal technology as well as cogeneration. • In this regard plans to ensure that we bring as many megawatts into the system as possible in order to alleviate load shedding were in place . Part of the five point plan included demand side options whereby South Africans were encouraged to reduce the electricity usage and to become more energy efficient.The Department’s electrification programme (INEP), flagship programmes in the delivery of services to our people was allocated R5, 6 billion during the 2015/16 financial year. INEP and its implementing agencies Eskom, municipalities and non-grid service providers have made remarkable progress in increasing access to electricity in South Africa and connected over 6.7 million households between 1994 to March 2016. Access to electricity is at 88% since 1994. • Government also recognised that, while this was a short term challenge, there was a need to accelerate the conclusion of a long term plan or the integrated energy plan in order to outline our future energy mix and to prioritise key policy interventions within the energy sector.

  47. Service Delivery Environment Electricity and Electrification • Through the Independent Power Producer (IPP) programme, renewable energy, coal, gas and cogeneration against the target of 17000 megawatt by the end of 2022 has progressed significantly. The renewable energy IPP programme has been very competitive in respect of pricing and time to produce power in the grid at the same time making real socio-economic impact in the communities where these projects are located. • So far the programme has injected more than 170 billion Rand in capital investment into the South African economy with South Africans owning an average of more than 48% in all IPPs with Black South Africans owning at least 28% of the projects on average. • In order to ensure than new generation capacity is increased, new determinations under the Electricity Regulation Act for additional 6000 megawatt under the renewable energy IPP Programme as well as 1800 megawatt for cogeneration was promulgated. This is in line with the existing Integrated Resource Plan (IRP) and various request for proposals were issued during the year under review in order to procure these projects. Side by side with the renewable IPP Programme, we have introduced a small renewable energy request for proposals which targeted smaller projects equal to 5 megawatt and under which programme we provide for a less costly and less complex bidding process.

  48. Service Delivery Environment Electricity and Electrification • The Small Scale Renewable Energy Programme procured renewable energy from small-scale Independent Power Producers, with projects that are between 1 and 5MW in size in order to ensure that small and medium enterprises owned by black people are able to participate in the green economy. Since the inception of the renewable energy IPP programme the department has been successful in (i) increasing the contribution of clean energy from 0 percent in 2010 to over 4.5 percent within 5 years; (ii) the creation of 24 965 job-years of employment opportunities for South African citizens, where a job-year is defined as the equivalent of a full time employment opportunity for one person for one year. To date, a total of R53 million has been contributed to enterprise development by operating IPPs. The programme has also broadened Black Economic Empowerment, as Black South Africans own, on average, 30% of these projects. • The request for information for gas power generation was released during the year under review. This is a precursor of the gas to power procurement programme in respect of which we will be procuring 3126 megawatt, with bids expected to be invited in 2016. Proposal in relation to coal technology was also released. Preferred bidders under the coal programme were announced during the year under review projects proposals were received and adjudicated.

  49. Service Delivery Environment Electricity and Electrification • Challenges experienced by developers who would like to generate their own power and include transmitting the power to third parties across networks owned by licences were identified. NERSA has concluded the process of developing the necessary rules for third party access at the same time as the department is putting the necessary policy framework in place. • We have taken the biofuels regulatory model forward and have concluded addressing concerns about the risk posed by this programme to the fiscus and to free food security. Through collaboration with National Treasury, Department of Agriculture, Forestry & Fisheries, Department of Economic Development and other government departments, we have provided a framework which we believe will take the biofuels industry forward. • The Solar Water Heater implementation model was revised and approved by cabinet for management under the Department of Energy. This programme has seen the collaboration by national, provincial and local government together with private and public sector stakeholders. The department concluded an agreement with the SETAs responsible for energy and water in terms of which comprehensive and accredited training is a central element of the Solar Water Heater roll out model.

More Related