PIP. Wednesday April 10 th ,2012. 4/4/12 Agenda. Project Update(s) Pellico - PIP Status Talk(s) None –(Review Status Report Effort) . Updates -. RFQ/LEBT RFQ energy issue continues – Spectrometer Measurement Thursday and Friday RFQ reconnected – working on feedback control loops

Download Presentation

PIP

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Pip

PIP

Wednesday April 10th,2012


4 4 12 agenda

4/4/12 Agenda

  • Project Update(s)

    Pellico - PIP Status

    Talk(s)

  • None –(Review Status Report Effort)


Updates

Updates -

  • RFQ/LEBT

    • RFQ energy issue continues – Spectrometer Measurement Thursday and Friday

    • RFQ reconnected – working on feedback control loops

  • Long Shutdown just 3 weeks away!

    • Lots of PIP related studies underway

      • Phase Lock

      • Cogging Tests

      • Orbit Work Continues

  • Fernanda has set up a new network drive dedicated for PIP project

    • beamssrv1/pip.bd

  • Discussions of Shutdown Work/Beam Studies

    • http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html

    • Mary and I will present shutdown schedule – work list next Wednesday (look at schedule)

  • Today - RLS/Effort Update

    • Elmie sent out “a slightly-revised report template” for the schedule update worksheet

    • Keith and Fernada

      • QA on recent report


Talks

Talks

Next Week April 18th 2012

  • Pellico, Convery: Review of the Shutdown Schedule


  • Login